BLD-Final | 3/26/2001 | 3/27/2001 | 3/27/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 03/26/2001 at 15:18:30. Contact: ###-####.
|
DOC - Permit Finaled | 3/27/2001 | 3/27/2001 | 3/27/2001 | A | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 3/27/2001 10:06:00 AM
|
BLD-Final | 3/12/2001 | 3/12/2001 | 3/12/2001 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 03/12/2001 at 10:47:07. Contact: ###-####. c/n on site 3/12/2001 4:24:22 PM
|
BLD-Energy code compliance | 1/25/2001 | 1/25/2001 | 1/25/2001 | A | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 1/25/2001 9:06:26 AM
|
BLD-Grading Inspection | 1/25/2001 | 1/25/2001 | 1/25/2001 | A | PASS |
Rita DeYoung
|
|
|
Added by Inspector: 425 On 1/25/2001 9:07:23 AM
|
BLD-Framing/Rough-in | 1/23/2001 | 1/24/2001 | 1/24/2001 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/23/2001 at 15:39:34. Contact: ###-####. cn posted 1/24/2001 11:37:50 AM
|
BLD-Framing/Rough-in | 1/23/2001 | 1/23/2001 | 1/23/2001 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/23/2001 at 09:44:37. Contact: ###-####.fire blocking of basement walls 1/23/2001 2:36:52 PM
|
BLD-Framing/Rough-in | 1/18/2001 | 1/19/2001 | 1/19/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/18/2001 at 17:09:10. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/18/2001 | 1/18/2001 | 1/18/2001 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/18/2001 at 10:15:53. Contact: ###-####. c/n on site need engineering for truss that miss their bearing point need to check fire blocking after they finish insulating 1/18/2001 3:10:37 PM
|
BLD-Framing/Rough-in | 1/16/2001 | 1/17/2001 | 1/17/2001 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/16/2001 at 13:53:54. Contact: ###-####. 1/17/2001 12:43:51 PM shear nailing ok but need engineering for two set of hold downs not enstalled 1/17/2001 3:47:38 PM
|
BLD-Foundation | 12/7/2000 | 12/7/2000 | 12/7/2000 | P | PASS |
Dave Hannah
|
|
|
###-####
|
BLD-Footing | 12/7/2000 | 12/7/2000 | 12/7/2000 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 12/7/2000 1:09:49 PM
|
BLD-Footing | 11/30/2000 | 11/30/2000 | 11/30/2000 | P | FAIL |
Dave Hannah
|
|
|
FT INSP LAZARO ###-#### not per city aproved plans 11/30/2000 2:48:00 PM
|
Issue PAID IN FULL permit | | | 11/27/2000 | | DONE |
|
|
|
|
Office Staff conference/action | | | 11/13/2000 | | |
|
|
|
called me 11/13/2000 to see where plan was and how long before ready, transferred to permit desk as permit ready since 11/2/2000/pe
|
Inspection Record Card- Bld | | | 11/3/2000 | | DONE |
|
|
|
|
Pending Assignment by DJO | 10/31/2000 | | 11/2/2000 | | DONE |
Dan Overy
|
|
|
11/2/2000 14:35:47 PEP - activity updated through activity BLDA176 from case BLD00-03270.
|
Plan assigned to (PEP) | 11/2/2000 | | 11/2/2000 | | PASS |
Perry Paine
|
|
|
11/2/2000 16:38:52 PEP - activity updated through activity BLDA022 from case BLD00-03270.
|
(F) Reprint permit | | | 11/2/2000 | | DONE |
|
|
|
|
Plan Review Report | | | 11/2/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/31/2000 | 10/31/2000 | 11/1/2000 | | PASS |
|
|
|
|
Routing - PLANNING | 10/31/2000 | 10/31/2000 | 10/31/2000 | | PASS |
|
|
|
|
Application received | | | 10/31/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/1/2000 | 11/1/2000 | | | PEND |
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|