Letter of compliance | | | 11/14/2001 | | DONE |
|
|
|
Letter of Compliance #22055 issued 11-14-01.
|
BLD-Final | 11/1/2001 | 11/2/2001 | 11/2/2001 | A | PASS |
Steven Webb
|
|
|
###-####
|
FIRE-Final Inspection | 10/31/2001 | 11/1/2001 | 11/1/2001 | A | PASS |
Rick Jackson
|
|
|
###-#### GEORGE
|
BLD-Final | 10/30/2001 | 10/31/2001 | 10/31/2001 | A | CANC |
Steven Webb
|
|
|
###-####
|
BLD-Other | 9/26/2001 | 9/26/2001 | 9/26/2001 | P | PASS |
Steven Webb
|
|
|
george ###-#### fire taping
|
BLD-Framing/Rough-in | 9/4/2001 | 9/4/2001 | 9/4/2001 | P | PASS |
Steven Webb
|
|
|
george ###-#### fr
|
BLD-Framing/Rough-in | 8/31/2001 | 8/31/2001 | 8/31/2001 | P | NR |
Steven Webb
|
|
|
GEROGE -###-####
|
Case Summary (BLD) | | | 8/22/2001 | | |
|
|
|
|
BLD-Aging Inspection | 7/18/2001 | 7/18/2001 | 7/18/2001 | | PART |
Steven Webb
|
|
|
wip 7/18/2001 7:37:30 AM
|
Override - Parcel Holds | | | 7/17/2001 | | |
|
|
|
|
CHANGE ISSUED DATE | | | 7/17/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 7/16/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/16/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/16/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/24/2001 | | 7/13/2001 | | DONE |
|
|
|
Plan Modification
|
Plan assigned to (M_P) | 6/1/2001 | | 7/13/2001 | | PASS |
Mike Phillips
|
|
|
7/13/2001 10:31:08 M_P - activity updated through activity BLDA022 from case BLD00-03272.
|
Plan Reviewer's activity | | | 7/13/2001 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 7/13/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/13/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/13/2001 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/18/2001 | | 6/26/2001 | | PASS |
|
|
|
contacted pdq to take revised calcs to outside eng. kmm
Additional information required for further review. Does not need to go to outside engineering firm. MJP
|
Plan resubmittals received | | | 6/15/2001 | | |
|
|
|
2 copies plan review response and calc from eng of record/pe
|
Routing Off Site - STRUCTURAL | 6/4/2001 | | 6/8/2001 | | FAIL |
|
|
|
contacted pdq to take plan mod to outside eng. kmm
Additional information required for further review. MJP
|
Plan resubmittals received | | | 6/4/2001 | | |
|
|
|
1 SET CONST PLANS AAS SUBMITTED BY RIB-ROOF
1 LETTER RELEASING STAPLEY ENG AS ENG OF RECORD
1 EACH 1 THRU 38/ T-1--D1--D2--D3--F1/ TOOK TO MIKE P 6/4/2001/PE
|
Plan Modification Accepted | | | 5/24/2001 | | |
|
|
|
|
CHANGE STATUS TO (PND) | | | 5/22/2001 | | |
|
|
|
|
BLD-Foundation | 5/17/2001 | 5/17/2001 | 5/17/2001 | P | PASS |
Steven Webb
|
|
|
George ###-####slap/turn down 5/17/2001 12:33:10 PM
|
Print Occupancy Form | | | 5/16/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/16/2001 | | DONE |
|
|
|
|
Telephone call | | | 5/16/2001 | | DONE |
|
|
|
called permit ready
|
Issue PAID IN FULL permit | | | 5/16/2001 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 5/16/2001 | | |
|
|
|
|
Plan assigned to (M_P) | 10/31/2000 | | 5/15/2001 | | PASS |
Mike Phillips
|
|
|
5/15/2001 16:11:22 M_P - activity updated through activity BLDA022 from case BLD00-03272.
|
Routing - PUBLIC WORKS | 5/14/2001 | | 5/15/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 5/15/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/15/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/15/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 12/14/2000 | | DONE |
|
|
|
project value $19,110 elect. $2,000 plumb. mech. fire sprinkler fire alarm systems N/A
|
Plan Reviewer's activity | | | 12/6/2000 | | FAIL |
|
|
|
Additional information required for further review.
|
Application received | | | 10/31/2000 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/31/2000 | | DONE |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Routing - PLANNING | 2/16/2001 | | | | |
|
|
|
|