Permit Information
Permit NumberBLD00-03348
StatusFinaled
Name PRIMARY HEALTH
Site Address 800 PARK BLVD Unit: (7 FLR)
Project NameMK PLAZA IV-7TH FLR
Customer Number 
ePlanReviewNo
Description
(PRIMARY HEALTH) Fire sprinklers are used for building area increase and to meet high-rise provisions. To create a 10,139 square foot office tenant space on the 7th floor of MK Plaza IV. To resolve exit separation concerns, a 1-hr tenant demising wall divides this tenant space into two separate areas for exiting. Non-structural demolition is also covered by this permit. Work is to include interior nonbearing walls, 1-hr tenant demising walls, relocated and new doors, relocated and new windows, suspended ceiling repairs, 1-hr corridor modifications, and interior finishes all per approved drawings and plan review conditions on file. The location of fire sprinkler heads shall comply with NFPA 13-1996 as regulated by the Fire Department. PC-955-00 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy  7/24/2001 DONE
Perm. Occ. Cert. #8773 issued 7-24-01 to Primary Health.
Permanent Occupancy 7/23/20017/23/2001 DONE
Details
BLD-Final7/23/20017/23/20017/23/2001PPASS
DetailsTony Young
7th floor Dave ###-####
DOC - Permit Finaled7/23/20017/23/20017/23/2001PPASS
DetailsTony Young
Finaled by inspector at 7/23/2001 3:56:55 PM
Fee Review-notes11/6/200011/6/20004/11/2001 DONE
FIRE-Final Inspection2/26/20012/26/20012/26/2001APASS
DetailsRick Jackson
Added by Inspector: 409 On 2/26/2001 1:01:13 PM
BLD-Framing/Rough-in2/21/20012/22/20012/22/2001APART
DetailsTom Arcoraci
###-####\\ceiling grid grid ok 2/22/2001 10:39:33 AM
FIRE-Final Inspection2/22/20012/22/20012/22/2001PFAIL
DetailsRick Jackson
###-#### Tim need to test alarms; rated doors; sprinkler heads 2/22/2001 3:24:19 PM
BLD-Framing/Rough-in2/6/20012/8/20012/8/2001APART
DetailsTony Young
###-####
interior walls ok to cover on phase 2, need to verify bracing of walls later @ ceiling grid inspection, also corridor compliance 2/8/2001 11:28:57 AM
FIRE-Sprinkler Rough-in1/22/20011/22/20011/22/2001PPART
DetailsRick Jackson
###-#### okay to occupy phase 1 only 1/24/2001 3:50:23 PM
BLD-Framing/Rough-in1/18/20011/19/20011/19/2001PPART
DetailsTony Young
Dave ###-####
ok for ceiling grid on 1st phase, verify the rest of wall bracing @ final 1/19/2001 2:17:51 PM
BLD-Framing/Rough-in1/5/20011/5/20011/5/2001PPART
DetailsTony Young
fr dave miller ###-#### -7th floor
c/n posted, ok to cover 1st phase of interior walls, pending architect letter. verify bracing of walls @ ceiling grid inspection. see prior notes 1/5/2001 1:54:00 PM
BLD-Framing/Rough-in1/4/20011/4/20011/4/2001PFAIL
DetailsTony Young
###-####
conf. w/ dave on framing, no c/n/// wall bracing, headers, jambs, seismic pods in existing ceiling, height of demising wall 1/4/2001 2:57:50 PM
Issue PAID IN FULL permit  12/19/2000 DONE
Print Occupancy Form  12/8/2000 DONE
Inspection Record Card- Bld  12/8/2000 DONE
Telephone call  12/8/2000 DONE
called permit ready
Print Occupancy Form  12/8/2000 DONE
Inspection Record Card- Bld  12/8/2000 DONE
Routing - PLAN CHECK11/30/2000 12/7/2000 PASS
Drawings approved, with conditions, after resubmittal review.
Plan assigned to (CJW)11/13/2000 12/7/2000 PASS
DetailsCarl Westfall
12/7/00 17:41:34 CJW - activity updated through activity BLDA022 from case BLD00-03348.
PLANS/APPL TAKEN TO FRONT DESK  12/7/2000 PASS
Plan resubmittals received  12/6/2000 DONE
Received Plan Resubmittalsfrom CSHQA Two sets of revised drawings A0.1, A1.1, A2.1, A6.1 and A8.1, forwarded same to Carl Westfall. 12/6/00 DAR
Routing - FIRE11/27/200011/30/200011/30/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  11/30/2000  
Drawings failed first UBC plan review.
Routing - PLAN CHECK11/14/2000 11/27/2000  
Drawings failed first review.
Plan Reviewer's activity  11/24/2000  
UBC plan review started November 24, 2000 and finished November 27, 2000. A response from the architect was required. See the conditions list.
Routing - PUBLIC WORKS11/13/2000 11/14/2000 PASS
Plans ACCEPTED BY PLAN TECH  11/7/2000 DONE
Application received  11/6/2000  
Recd Pcfee & Taken To Pln CK  11/6/2000 DONE