Fee Review-notes | 11/6/2000 | 11/6/2000 | 4/3/2002 | | DONE |
|
|
|
|
BLD-Final | 3/13/2002 | 3/14/2002 | 3/14/2002 | A | PASS |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/13/2002 5:24:39 PM Ok all signatures on final . Permanent oc. 3/14/2002 10:22:09 AM
|
Case Summary (BLD) | | | 3/14/2002 | | |
|
|
|
|
Letter of compliance | | | 3/14/2002 | | DONE |
|
|
|
Letter of Compliance #22308 issued 3-14-02.
|
BLD-Final | 3/6/2002 | 3/7/2002 | 3/7/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/06/2002 at 11:37:22. Contact: ###-####. Ok temp oc . c/n for guard rail at upper landing at exterior. 3/7/2002 12:05:54 PM
|
FIRE-Final Inspection | 2/15/2002 | 2/15/2002 | 2/15/2002 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 2/15/2002 5:00:27 PM fire life/safety finaled
|
FIRE-Final Inspection | 1/23/2002 | 1/23/2002 | 1/23/2002 | P | PART |
Troy Cobbley
|
|
|
Items on the correction notice have been complete for the life safety inspection. Still need to final the fire alarm system before signing off on life safety per Sam Rogers 1/23/2002 1:39:58 PM
|
FIRE-Final Inspection | 1/7/2002 | 1/8/2002 | 1/8/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide three additional emergency lights in the training corridor, repair exit sign at main entrance and repair emergency light at the top of the stairs 1/7/2002 2:10:00 PM
|
BLD-Framing/Rough-in | 10/19/2001 | 10/22/2001 | 10/22/2001 | A | PART |
Russ Owen
|
|
|
###-#### TEDupper floor walls,exterior stairway not completed yet.f 10/22/2001 12:00:16 PM
|
BLD-Aging Inspection | 10/11/2001 | 10/11/2001 | 10/11/2001 | | PART |
Russ Owen
|
|
|
plans have been submitted for a 10/15/2001 3:55:13 PM
|
CHANGE STATUS TO (ISS) | | | 10/8/2001 | | DONE |
|
|
|
already pd for/mls
|
Receive PAYMENT IN FULL | | | 8/1/2001 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 7/24/2001 | | 7/30/2001 | | PASS |
|
|
|
7/30/2001 11:53:28 RMH - activity updated through activity BLDA022 from case BLD00-03353.
|
Plan Reviewer's activity | | | 7/30/2001 | | PEND |
Ron Hill
|
|
|
No corrections required from building plan review, Permit pending fire departments review and approval.
|
Case Summary (BLD) | | | 7/30/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 7/30/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2001 | | PASS |
Ron Hill
|
|
|
|
Inspection Record Card- Bld | | | 7/30/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/30/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/30/2001 | | DONE |
|
|
|
|
CHANGE STATUS TO (PND) | | | 7/23/2001 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 7/23/2001 | | |
Ron Hill
|
|
|
Two sets of plan modifications excepted by RmH at front desk.
|
BLD-Aging Inspection | 7/16/2001 | 7/16/2001 | 7/16/2001 | | PART |
Russ Owen
|
|
|
this permit has expired but i have had contact with architect ,if nothing is done in 2 mo expire. 7/17/2001 11:56:06 AM
|
BLD-Aging Inspection | 5/16/2001 | 5/16/2001 | 5/16/2001 | | PART |
Russ Owen
|
|
|
This is an aging activity, i had spoke with the architect about a month ago, he told me they would like more time on the permit, i told him when it was about to expire to give me a call 12/17/2001 10:28:42 AM
|
BLD-Framing/Rough-in | 2/21/2001 | 2/23/2001 | 2/23/2001 | A | PART |
Russ Owen
|
|
|
###-####interior walls not part of the ,1 hr coridoo.r 2/23/2001 11:44:52 AM
|
BLD-Framing/Rough-in | 1/17/2001 | 1/18/2001 | 1/18/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 01/17/2001 at 13:52:29. Contact: ###-####.Note: work in 1hr corridor not started at this time. need to brace the tops of new walls as per plans. 1/18/2001 2:39:08 PM
|
Print Occupancy Form | | | 1/12/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/12/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/12/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/12/2001 | | DONE |
|
|
|
|
Routing - FIRE | 1/2/2001 | | 1/9/2001 | | PASS |
|
|
|
Resubmittal acceptable.
|
Routing - PLAN CHECK | 1/9/2001 | | 1/9/2001 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2001 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (R_H) | 11/13/2000 | | 1/9/2001 | | PASS |
|
|
|
1/9/2001 14:14:51 RMH - activity updated through activity BLDA022 from case BLD00-03353.
|
Routing - PLANNING | 11/14/2000 | | 1/9/2001 | | PASS |
Ron Hill
|
|
|
I spoke with Marty Santoyo on 01-09-01 he had no concerns with issuance of this permit. RMH
|
Routing - PLAN CHECK | 12/8/2000 | | 1/2/2001 | | PEND |
Ron Hill
|
|
|
Pend fire department approval,
|
Plan resubmittals received | | | 1/2/2001 | | DONE |
|
|
|
Received plan resubmittals from BRS Architects, Rick Toews, small documents and two sets of sheet A-3, forwarded same to Ron Hill. 1/2/01 DAR
|
Case Summary (BLD) | | | 1/2/2001 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/2/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/20/2000 | | DONE |
|
|
|
Received two copies of revised sheets A-1, A-1.1, A-3, M-1, E2.0S. Routed to Ron Hill. KMM
|
Plan resubmittals received | | | 12/13/2000 | | DONE |
|
|
|
Received two copies of revised sheets A-1, A-2, A-3, M-1, E.2.0L, E2.0P, E2.0S, E4.0. One copy of response letter to plan review. Routed to Ron Hill. KMM
|
Routing - FIRE | 12/5/2000 | | 12/7/2000 | | FAIL |
|
|
|
faxed comments to architect
|
Plan Review Completed(1st rev) | | | 12/7/2000 | | FAIL |
|
|
|
failed UBC and UFC reviews
|
Plan Reviewer's activity | | | 12/5/2000 | | FAIL |
Ron Hill
|
|
|
Faxed and requirements to Mike Capshaw Of Brs Architects on 12-05-00 at 2:45. Will route to fire department.
|
Case Summary (BLD) | | | 12/5/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/14/2000 | | 12/5/2000 | | FAIL |
Ron Hill
|
|
|
|
Routing - PUBLIC WORKS | 11/13/2000 | | 11/14/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/7/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 11/6/2000 | | DONE |
|
|
|
|
Application received | | | 11/6/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/6/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/23/2001 | | | | |
Ron Hill
|
|
|
Routed to my desk
|