Permit Information
Permit NumberBLD00-03428
StatusFinaled
Name NEW TERMINAL BUILDING
Site Address 3201 W AIRPORT WAY
Project NameAIRPORT-NEW TERMINAL
Customer Number 
ePlanReviewNo
Description
BOISE AIRPORT PASSENGER TERMINAL BUILDING - TO CONSTRUCT A NEW 321,450 SQ. FT. (INCLUDING MODIFICATION CCD-008 & PR-082.1 & PR082.2), THREE STORY WITH 45,000 SQ. FT. BASEMENT AIRPORT PASSENGER TERMINAL BUILDING AND RELATED SITE IMPROVEMENTS. THE NEW TERMINAL BUILDING WILL BE CONSTRUCTED OF CONCRETE AND STEEL STRUCTURAL FRAME; IT WILL BE FULLY FIRE SPRINKLERED. THIS TERMINAL BUILDING IS BEING CONSTRUCTED TO REPLACE THE EXISTING TERMINAL BUILDING. THE PROJECT WILL BE CONSTRUCTED IN PHASES. SCHEDULE I WILL BE CONSTRUCTED OUTSIDE OF THE EXISTING TERMINAL FOOTPRINT AND WILL INCLUDE THE BASEMENT SUPPORT AREAS, FIRST FLOOR BAGGAGE CLAIM/MAKE-UP, SECOND FLOOR TICKETING, ATO AND LEASE AREAS AND THE THIRD FLOOR ADMINISTRATIVE AND LEASE AREAS. SCHEDULE II WILL INCLUDE DEMOLITION OF THE WEST END OF THE EXISTING TERMINAL BUILDING AND THE CONSTRUCTION OF THE FIRST FLOOR RENTAL CAR LOBBY AND GROUND LOAD LOBBY AND SECOND FLOOR SECURITY CHECKPOINT, FOOD COURT AREAS AND PASSANGER LINK TO EXISTING CONCOURSE 'B'. SCHEDULE I ALSO INCLUDES CONSTRUCTION OF TEMORARY ELEVATED WALKWAYS AND SECURITY CHECKPOINTS CONSTRUCTED OVER THE EXISTING TERMINAL BUILDING, TO CONNECT THE COMPLETED AND OPERATING SCHEDULE I BUILDING WITH THE EXISTING CONCOURSES. AFTER COMPLETION OF SCHEDULE II, THE REMAINDER OF THE EXISTING TERMINAL BUILDING, THE TEMPORARY ELEVATED WALKWAYS AND CONCOURSE 'A' WILL BE DEMOLISHED AND REMOVED. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. DRH99-00206/CUP99-0130/PC#970-00/JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD4/26/20054/26/20054/27/2005 DONE
First Notice has not been responded to.
First Notice 12/29/20044/26/2005 DONE
Case Summary (BLD)  4/13/2005 DONE
(F) Reprint permit  3/16/2005  
Permanent occupancy UNPAID FEE  12/29/2004 DONE
Perm. Occ. Cert. # 10399 issued 12-29-04 to the Boise Airport Terminal.
Permanent Occupancy 12/23/200412/23/2004 DONE
Details
BLD-Final12/23/200412/23/200412/23/2004PPASS
DetailsJim Storey
final ok 12/23/2004 4:44:57 PM
FIRE-Final Inspection11/8/200411/8/200411/8/2004PPASS
DetailsRick Jackson
Calvin; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner Exit signs in tunnel are okay as is; hydrant by job trailer to remain inside fence as the fence is being relocated back from retaining wall 11/8/2004 3:12:55 PM
BLD-Final9/16/20049/17/20049/17/2004APART
DetailsJim Storey
calvin; Phone #: ###-#### Internet Inspection Request from: Barbara Moore temp ok pending resolve of restarooms to meet a117 ada/and others based on phasing. 9/17/2004 4:26:21 PM
BLD-Final9/16/20049/17/20049/17/2004ACANC
DetailsJim Storey
calvin; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
FIRE-Final Inspection9/17/20049/17/20049/17/2004PPART
DetailsRick Jackson
Phased project - Area D okay to occupy 9/17/2004 3:23:51 PM
BLD-Final9/15/20049/16/20049/16/2004ANR
DetailsJim Storey
calvin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ada restarooms pending/ 3rd floor mech damper lables/screws/fire proofing. 9/16/2004 11:04:05 AM
FIRE-Final Inspection9/14/20049/14/20049/14/2004PFAIL
DetailsRick Jackson
calvin--exit signs; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Test overhead door release; install exit signs as shown on plans; complete sprinkler tie-in to concourse B and complete hydro test on second floor; remove tape and add escutcheons on all sprinklers; complete rated doors with seals and closures; NFPA 72 record of completion for alarms; provide certificates for sprinkler system and add calc stickers on risers; install signs for auxiliary drains and control valves; certify fire extinguishers 9/14/2004 3:45:36 PM
BLD-Framing/Rough-in9/13/20049/13/20049/13/2004PPASS
DetailsJim Storey
ceiling grid- call 1st before insp calvin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in9/10/20049/10/20049/10/2004PPASS
DetailsJim Storey
calvin ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie fire proofing patch. 9/10/2004 4:01:45 PM
BLD-Final9/3/20049/3/20049/3/2004APART
DetailsJim Storey
area c rental car area for temp occ. temp ok for area c. 9/3/2004 9:50:16 AM
FIRE-Final Inspection9/1/20049/2/20049/2/2004PPART
DetailsRick Jackson
calvin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Inspection from 11:00 pm - 2 am to test fire alarms; Area C first floor forcar rental area okay to occupy 9/3/2004 9:08:01 AM
BLD-Final8/30/20049/2/20049/2/2004PPASS
DetailsJim Storey
calvin; Phone #: ###-#### Internet Inspection Request from: Annette Moore area c rental car area alarms and 2 areas complet per c/n. 9/3/2004 1:12:27 AM
BLD-Framing/Rough-in8/31/20049/1/20049/1/2004PPASS
DetailsJim Storey
calvin - Note: ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Conference8/25/20048/26/20048/26/2004PPART
DetailsRick Jackson
1:30 at Layton trailer Met with Al and Bill about testing the fire alarms for this phase - I agreed to test after hours pending a request to Sam Rogers for approval; reviewed the exiting for this phase and there may be a problem with concourse A and one exit - Bill will check into it and to also let Jim S. know about the problem 8/26/2004 3:58:41 PM
FIRE-Sprinkler Rough-in8/17/20048/23/20048/23/2004AFAIL
DetailsRick Jackson
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Not a sprinkler rough-in but to test smoke/fire damper operation - damper at device M4-8 not working and need tot est damper at south end in office area on first floor 8/23/2004 12:36:32 PM
BLD-Framing/Rough-in8/17/20048/18/20048/18/2004APART
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles after 10:00
BLD-Framing/Rough-in8/16/20048/17/20048/17/2004ACANC
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles after 10:00 out of time rolled over. 8/17/2004 4:18:46 PM
BLD-Framing/Rough-in8/13/20048/16/20048/16/2004ACANC
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles rolled over to am 8/16/2004 3:16:48 PM
BLD-Framing/Rough-in8/4/20048/4/20048/4/2004PPART
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ceilling grid ok 1 st floor/glazing sg 4 locations 1st floor. 8/4/2004 4:46:03 PM
BLD-Other7/19/20047/20/20047/20/2004APASS
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ceilling in car rental area ok pending fd and ele approval. 7/20/2004 9:46:55 AM
BLD-Framing/Rough-in7/15/20047/19/20047/19/2004ACANC
DetailsJim Storey
cal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in6/30/20047/1/20047/1/2004APASS
DetailsJim Storey
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes fire proofing repaired handrailling reviewed for compliance in west stair well. 7/1/2004 9:13:38 AM
FIRE-Sprinkler Rough-in7/1/20047/1/20047/1/2004PPART
DetailsRick Jackson
calvin; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Will need additional EQ's at expansion joint and at 4 inch line to walkway to concourse 7/2/2004 10:18:15 AM
BLD-Framing/Rough-in6/29/20046/30/20046/30/2004APART
DetailsJim Storey
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes damper at car rental stair/ blow patch/fire stop/exalator 2 beam patches fp. 6/30/2004 9:27:04 AM
BLD-Framing/Rough-in6/21/20046/22/20046/22/2004PPASS
DetailsJim Storey
calvin - ceiling grid inspection please!; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles over escalator 2nd floor ok.fire proofing ok for c/n posted by si. 6/22/2004 3:20:35 PM
BLD-Framing/Rough-in6/17/20046/18/20046/18/2004PPASS
DetailsJim Storey
Randy; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes n & s soffits of walkway ok 6/18/2004 3:51:33 PM
BLD-Framing/Rough-in6/4/20046/7/20046/7/2004APASS
DetailsJim Storey
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes east walls floor fire saffing 2 and 3 rd floors complet only west and coridor left. 6/7/2004 9:17:35 AM
BLD-Framing/Rough-in6/4/20046/4/20046/4/2004PCANC
DetailsJim Storey
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes out of time 6/4/2004 4:23:29 PM
FIRE-Final Inspection6/1/20046/2/20046/2/2004PCANC
DetailsRick Jackson
Calvin; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Wrong inspection called in - needed structural inspector for wall cover 6/2/2004 12:26:11 PM
BLD-Wall cover6/2/20046/2/20046/2/2004PPART
DetailsJim Storey
curtin wall ok all but east wall at dog leg to rotunda. 6/2/2004 4:26:03 PM
BLD-Other5/28/20045/28/20045/28/2004PFAIL
DetailsJim Storey
Jeff Peterson, ###-#### - call 1st cutrin wall fire stop missing at 4 locations/ele need fire stop. 5/28/2004 3:33:15 PM
FIRE-Final Inspection5/25/20045/26/20045/26/2004ACANC
DetailsRick Jackson
Jeff; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Wrong type inspection called in - needed structural inspection 5/28/2004 8:31:18 AM
BLD-Framing/Rough-in5/17/20045/17/20045/17/2004PPASS
DetailsJim Storey
Cal; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes offices at rental area lowest level ok for cover. 5/17/2004 1:14:21 PM
BLD-Framing/Rough-in5/6/20045/10/20045/10/2004APART
DetailsJim Storey
###-#### calvin 2 hr septration at walkway at concorse b must be complet thru soffit areas . 5/10/2004 10:13:33 AM
BLD-Framing/Rough-in5/10/20045/10/20045/10/2004PPASS
DetailsJim Storey
floor curtin wall firesafing.ok for cover at corridor west side of 2nd floor. 5/10/2004 3:45:03 PM
BLD-Framing/Rough-in5/6/20045/6/20045/6/2004PPART
DetailsJim Storey
###-#### CALVIN remove vizqueen at sky lights/ fire proofing patch required throughout. 5/6/2004 3:46:01 PM
FIRE-Sprinkler Rough-in4/16/20044/19/20044/19/2004PPART
DetailsRick Jackson
calvin ###-#### See sprinkler FIR for info 4/19/2004 4:07:00 PM
BLD-Framing/Rough-in4/7/20044/12/20044/12/2004APASS
DetailsJim Storey
###-#### calvin wip ok 4/12/2004 9:40:49 AM
BLD-Framing/Rough-in4/6/20044/8/20044/8/2004ACANC
DetailsJim Storey
###-#### calvin rolled over to monday. 4/7/2004 5:40:46 PM
Telephone call  4/7/2004 DONE
talked to tom coughlin (g.c.) will send info to the airport for payment
Routing - PLAN CHECK3/12/2004 3/12/2004 PASS
Modification PR-091. JCM
PLANS/APPL TAKEN TO FRONT DESK  3/12/2004 PASS
Print Occupancy Form  3/12/2004 DONE
OVERRIDE  3/12/2004  
Permit Ready to Issue  3/12/2004 DONE
Telephone call  3/12/2004 DONE
permit ready and fee due
Plan assigned to (JCM)2/9/2004 3/12/2004 PASS
DetailsJohn Menard
3/12/2004 14:24:48 JCM - activity updated through activity BLDA022 from case BLD00-03428.
Routing - FIRE3/8/2004 3/11/2004 PASS
Plan modification approved subject to resubmittals for AS and FA permit plan modifications and field inspection of egress hardware, etc.
BLD-Framing/Rough-in3/9/20043/10/20043/10/2004APASS
DetailsJim Storey
CALVIN ###-#### conf with calvin ok 3/10/2004 9:19:43 AM
Plan Reviewer's activity  3/8/2004 PASS
Approval of plan modification PR-091. This modification is for the construction of interior partitions, two interior doors, suspended ceiling, mechanical & electrical to create a new approximate 1400 square foot office space for the charter bus service. this work is being done on the first floor of the terminal between grid lines C&E and 12&13. All construction per the approved plans on file. JCM
Routing - PLAN CHECK2/9/2004 3/8/2004 PASS
BLD-Framing/Rough-in3/4/20043/5/20043/5/2004APART
DetailsJim Storey
calvin ###-#### walk thru progess ok fire proofing in progess/ noted defence talk with special insp. and contractor for follow up / review of rated walls for opening protection at bagage claim rfi to arch. through contractor. 3/5/2004 11:39:38 AM
Plan Modification Accepted  2/9/2004 DONE
Plan Modification accepted for PR-091 Finish Charter Bus Office 143, and Lease Office Space 189 area C first floor. Finish out the spaces with 2x4 ceiling,carpet,painted walls and associated lighting and mechanical.
Plan resubmittals received  1/30/2004 DONE
Received two copies of transmittal addressed to Carl & John with two copies of letters dated 1-29-04 Fire Sprinkler permit plan review, two copies of review comments dated 12-22-03 also made a copy and gave it to Bill Alexander.
BLD-Foundation1/20/20041/23/20041/23/2004APART
DetailsJim Storey
randy ###-#### pwsi 1/23/2004 2:38:49 PM
BLD-Foundation1/20/20041/22/20041/22/2004APART
DetailsJim Storey
randy ###-#### pwsi 1/22/2004 3:26:43 PM
BLD-Foundation1/20/20041/21/20041/21/2004APART
DetailsJim Storey
randy ###-#### 1/21/2004 8:06:28 AM placed with special inspection. 1/21/2004 8:07:20 AM
CHANGE STATUS TO (ISS)  1/21/2004 DONE
BLD-Framing/Rough-in1/20/20041/20/20041/20/2004PPART
DetailsJim Storey
###-#### CALIVIN framing ok for north sky light/ mech space exterior hold at colum and beam fire proofing patches to be verified latter. 1/20/2004 1:34:27 PM
Override - Condition Holds  1/20/2004  
BLD-Framing/Rough-in1/5/20041/9/20041/9/2004PPART
DetailsJim Storey
BLD-Framing/Rough-in1/5/20041/8/20041/8/2004PCANC
DetailsJim Storey
cloned 1/8/2004 3:54:03 PM
BLD-Concrete1/8/20041/8/20041/8/2004PPART
DetailsJim Storey
wip 2nd floor deck pour/ roof framing inprogess. 1/8/2004 3:54:56 PM
BLD-Concrete1/7/20041/7/20041/7/2004PPART
DetailsJim Storey
2nd floor deck floor/tunnel lid 1/7/2004 4:11:58 PM
BLD-Framing/Rough-in1/5/20041/7/20041/7/2004PNR
DetailsJim Storey
cloned 1/7/2004 4:10:11 PM
BLD-Framing/Rough-in1/5/20041/6/20041/6/2004PNR
DetailsJim Storey
wip 1/6/2004 4:11:35 PM
BLD-Framing/Rough-in1/5/20041/5/20041/5/2004PPART
DetailsJim Storey
###-#### randy floor 2nd concrete placement. 1/5/2004 4:39:42 PM
Override - Condition Holds  1/5/2004  
Override - Condition Holds  1/5/2004  
Override - Condition Holds  1/5/2004  
Override - Condition Holds  1/5/2004  
Override - Condition Holds  1/5/2004  
BLD-Concrete12/4/200312/11/200312/11/2003APART
DetailsJim Storey
Randy ###-#### wip 12/11/2003 1:54:13 PM
BLD-Concrete12/4/200312/10/200312/10/2003APART
DetailsJim Storey
Randy ###-#### 2 nd floor deck pour j line ok pending density reports. 12/10/2003 9:18:34 AM
BLD-Concrete12/4/200312/9/200312/9/2003APART
DetailsJim Storey
Randy ###-#### wip covered with special insp. 12/9/2003 4:25:05 PM
BLD-Concrete12/4/200312/8/200312/8/2003APART
DetailsJim Storey
###-#### Randy recieved special insp. reports for truck load of steel damaged in shipment engineers of fabracator and site as well as special insp. records justified to repair minor isues. repairs complet and all parties sign off for use with out replacement of major componants. archived into city for record. 12/8/2003 10:13:34 AM wip placed with si. 12/8/2003 10:15:37 AM
BLD-Conference12/8/200312/8/200312/8/2003APASS
DetailsJim Storey
###-#### Randy recieved special insp. reports for truck load of steel damaged in shipment engineers of fabracator and site as well as special insp. records justified to repair minor isues. repairs complet and all parties sign off for use with out replacement of major componants. archived into city for record. 12/8/2003 10:13:34 AM
BLD-Conference12/8/200312/8/200312/8/2003APASS
DetailsJim Storey
responce to non-compliance report 400-599/b30418c/rpt081.doc ok under ubc table 7b # 6 cmu protection. to negate adheation testing. 12/10/2003 9:19:33 AM
BLD-Concrete12/4/200312/5/200312/5/2003APART
DetailsTom Arcoraci
###-#### randy spec on site mti 12/5/2003 8:19:39 AM 12/5/2003 8:21:08 AM
Override - Condition Holds  12/4/2003  
Override - Condition Holds  12/4/2003  
Override - Condition Holds  12/4/2003  
Override - Condition Holds  12/4/2003  
Override - Condition Holds  12/4/2003  
Override - Condition Holds  12/4/2003  
Override - Condition Holds  12/4/2003  
BLD-Footing11/21/200311/28/200311/28/2003PPART
DetailsJim Storey
###-#### Randy wip 12/1/2003 1:42:59 PM
BLD-Foundation11/21/200311/28/200311/28/2003PPART
DetailsJim Storey
###-#### Randy wip 12/1/2003 1:43:07 PM
OVERRIDE  11/28/2003  
Override - Condition Holds  11/28/2003  
Permit Ready to Issue  11/28/2003 DONE
Override - Condition Holds  11/28/2003  
Inspection Record Card- Bld  11/28/2003 DONE
Print Occupancy Form  11/28/2003 DONE
BLD-Foundation11/21/200311/26/200311/26/2003PPART
DetailsJim Storey
###-#### Randy
BLD-Footing11/21/200311/26/200311/26/2003PPART
DetailsJim Storey
###-#### Randy
BLD-Foundation11/21/200311/25/200311/25/2003PPART
DetailsJim Storey
###-#### Randy pwsi 11/25/2003 4:20:24 PM
BLD-Footing11/21/200311/25/200311/25/2003PPART
DetailsJim Storey
###-#### Randy pwsi 11/25/2003 4:20:08 PM
Plan assigned to (JCM)10/28/200310/28/200311/25/2003 PASS
DetailsJohn Menard
11/25/2003 09:46:34 JCM - activity updated through activity BLDA022 from case BLD00-03428.
Routing - PLAN CHECK11/25/2003 11/25/2003 PASS
Plan modification PR- 0-82.1 & PR 0-82.2
PLANS/APPL TAKEN TO FRONT DESK  11/25/2003 PASS
Plan Modification for PR-082.1 & PR-082.2.
BLD-Conference11/21/200311/24/200311/24/2003APASS
DetailsJim Storey
###-#### Randy meet with calvin over colm. protection.
BLD-Foundation11/21/200311/24/200311/24/2003PPART
DetailsJim Storey
###-#### Randy cwsi 11/24/2003 2:21:32 PM
BLD-Footing11/21/200311/24/200311/24/2003PPART
DetailsJim Storey
###-#### randy cwsi 11/24/2003 2:21:25 PM
Routing - FIRE11/19/2003 11/24/2003 PASS
Additional permits required; review comments faxed to architect.
BLD-Foundation11/21/200311/21/200311/21/2003PPART
DetailsJim Storey
###-#### Randy pwsi 11/21/2003 5:05:49 PM
BLD-Footing11/21/200311/21/200311/21/2003PPART
DetailsJim Storey
###-#### Randy pwsp 11/21/2003 5:05:28 PM
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
Override - Condition Holds  11/21/2003  
BLD-Framing/Rough-in11/20/200311/20/200311/20/2003PFAIL
DetailsJim Storey
field reports req from fabractor and struc. engineer of record for truck load of steel that fell off truck in transant as to acceptance for damage to meet building standards. truck load 190/
Routing - PLUMBING11/17/2003 11/19/2003 PASS
per plans and 2000 upc.
Routing - PLAN CHECK10/28/2003 11/17/2003 PASS
Plan Mod. for PR 0-82.1 & PR 082.2 taken to John M.
Plan Reviewer's activity  11/17/2003 PASS
Reviewed and approved plan mod. for airport second floor security area expansion. PR-082.1 and PR-082.2. JCM The modification is to expand the security checkpoint area to handle additional equipment and space for checkpoint offices. This expansion is approximately 700 square feet (8'x80') along the west side of the second level of schedule II Terminal between grid lines F.5&H. JCM
Plan Modification Accepted  10/28/2003 DONE
PR-082.1 Structural modifications at the security checkpoint.
PR-082.2 Architectural, Mechanical and Electrical modifications at eh security checkpoint.
PR-082.1 Structural modification related to PR-082.2 work.
PR-082.2 Enlarging the security checkpoint area to handle addition equipment for securtiy and additional space for TSA checkpoint offices. Second level of schedule II therminal building is expanding towards the west to increase floor space. PR-082.1 and PR-082.2 containsall required construction document modifications for this plan change.
CHANGE STATUS TO (PND)  10/28/2003 DONE
Plan mod.
BLD-Footing10/13/200310/14/200310/14/2003PPASS
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore rfi archived 00747 to justify bar lap and spacing on stair towersd and e ok. 10/14/2003 2:54:06 PM
BLD-Footing10/9/200310/9/200310/9/2003PPASS
DetailsJim Storey
RANDY; Phone #: ###-#### Internet Inspection Request from: Annette Moore massanary in progess/ west footing line progressing.special insp. on site and no descrepenes. 10/9/2003 2:06:35 PM
BLD-Footing10/8/200310/8/200310/8/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore placed with special insp. unable to insp. with work load. 10/8/2003 4:55:06 PM
BLD-Footing10/6/200310/6/200310/6/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore placed with special insp. 10/6/2003 4:29:15 PM
BLD-Footing10/2/200310/2/200310/2/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Foundation10/2/200310/2/200310/2/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Footing9/30/20039/30/20039/30/2003PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/30/2003 at 7:55:58 AM. Contact: ###-####.placed with si. 9/30/2003 2:16:58 PM
BLD-Foundation9/29/20039/29/20039/29/2003PPASS
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Footing9/29/20039/29/20039/29/2003PPASS
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Footing9/23/20039/23/20039/23/2003PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/23/2003 at 7:43:13 AM. Contact: ###-####. placed with special insp. pending report. 9/23/2003 3:59:27 PM
BLD-Foundation9/18/20039/18/20039/18/2003PPART
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Marc Lileks walls at previous ft location placed with special insp as well as elavator pit. 9/18/2003 2:55:39 PM
BLD-Footing9/16/20039/16/20039/16/2003PPASS
DetailsJim Storey
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore west ft rebar ok 8 inches oc for massanary wall up to not including elavator pit ft. 9/16/2003 2:55:55 PM
BLD-Footing9/8/20039/8/20039/8/2003PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/8/2003 at 9:25:30 AM. placed with special insp. 9/8/2003 3:10:26 PM
BLD-Footing9/2/20039/3/20039/3/2003APASS
DetailsJim Storey
RANDY; Phone #: ###-#### Internet Inspection Request from: Marc Lileks first pad ft. off rotunda south wip pending special insp. 9/3/2003 9:08:28 AM
BLD-Aging Inspection8/25/20038/25/20038/25/2003 PASS
DetailsJim Storey
wip 8/25/2003 10:03:57 AM
(F) Reprint permit  7/16/2003 DONE
CHANGE STATUS TO (ISS)  7/11/2003 DONE
Telephone call  7/3/2003 DONE
LEFT MESS FOR MARTIN HALE THAT PERMIT NEEDS TO BE PICKED UP
Plan resubmittals received  7/1/2003 DONE
PR-067 Received revised sheets C1.0, C1.0B, A0.2A, PH3.1, PH4.1, PH4.2, PH5.1, PH5.2, A1.1, A1.2B, A1.3B A1.3E, A1.3F, A4.1H A4.5H, A8.1A, A0.2B, S2.6, E2.USB, E4.1G, E6.1, E6.4, E6.8, E7.0, E7.6, E7.8.
PR-039 received revised sheets A0.2A, A0.3, A0.5A, A0.5B, A2.0, A2.1, A2.1E, A2.1H, A2.5, A2.5B, A2.7A, A2.7C, A2.9B, A2.9D, A4.1H, A4.5D, A4.5H, A6.1E, A6.1H, A7.1B, A7.1F, A7.2A, A8.6C, V2.1E, A0.2B, S0.1, S0.2, S1.1C, S1.2E, S2.1C, S2.1E, S2.1H, S4.5, S4.7, S4.8, S4.9, S5.38, S5.39, S7.11. Plans routed to the records department. Plans will be verified and approved in the field. All per John Menard. kmm
FIRE-Conference6/24/20036/25/20036/25/2003PPART
DetailsRick Jackson
###-#### calvin concourse A and B and the new terminal are now a networked fire alarm system; old terminal doesn't have alarms and the pump and sprinkler system will be left on until the building is ready for demo; outside bell isn't working on the old building 6/26/2003 2:24:29 PM
BLD-Conference6/24/20036/24/20036/24/2003PPASS
DetailsJim Storey
###-#### calvin
Override - Parcel Holds  6/24/2003  
Override - Parcel Holds  6/24/2003  
Override - Parcel Holds  6/24/2003  
Override - Parcel Holds  6/24/2003  
Override - Parcel Holds  6/18/2003  
Office Staff conference/action  6/18/2003 DONE
2 hrs of fire after hour inspections 44.10 each hour lh
FIRE-Conference6/16/20036/17/20036/17/2003PPART
DetailsRick Jackson
###-#### alvin conducted alarm testing inspection from 5-7 pm; Linda Hartwell notified 6/18/2003 10:34:53 AM
BLD-Conference6/16/20036/17/20036/17/2003PPASS
DetailsJim Storey
###-#### alvin 5:30pm 6/16/2003 3:50:34 PM walkways ok for temp occ. per phased aproved plan a and b access/ egress. 6/17/2003 6:47:28 PM
Override - Parcel Holds  6/16/2003  
Override - Parcel Holds  6/16/2003  
BLD-Conference6/12/20036/13/20036/13/2003ACANC
DetailsJim Storey
###-#### alvin called and changed time to pm. 6/13/2003 10:45:56 AM
BLD-Final6/13/20036/13/20036/13/2003PPASS
DetailsJim Storey
ok for temp occ. of main termnal bldg. walk ways sch. for 6/17 to complet phase in of aproved plan. 6/13/2003 5:41:27 PM
FIRE-Conference6/6/20036/12/20036/12/2003APART
DetailsRick Jackson
###-#### calvin main portion of new building on temp; using fire watch until all systems are monitored at new panel 6/13/2003 9:11:31 AM
BLD-Conference6/6/20036/12/20036/12/2003AFAIL
DetailsJim Storey
###-#### calvin ###-#### calvin it an surcerity membrane penatrations. 6/12/2003 1:18:48 PM
Override - Parcel Holds  6/12/2003  
Override - Parcel Holds  6/6/2003  
Override - Parcel Holds  6/6/2003  
BLD-Conference6/3/20036/5/20036/5/2003PFAIL
DetailsJim Storey
###-#### calvin ###-#### calvin gen test failled. 6/5/2003 2:46:38 PM
FIRE-Conference6/3/20036/5/20036/5/2003PFAIL
DetailsRick Jackson
###-#### calvin attempted to test the generator and it failed to provide power when building power was shut off 6/5/2003 5:17:44 PM
Override - Parcel Holds  6/3/2003  
Override - Parcel Holds  6/3/2003  
BLD-Framing/Rough-in5/30/20036/2/20036/2/2003APART
DetailsJim Storey
area b fire proofing 3 locations/ 2 lights. ceillings ok 6/2/2003 9:52:06 AM
BLD-Conference5/30/20035/30/20035/30/2003PCANC
DetailsJim Storey
###-#### calvin ###-#### calvin out of time. 5/30/2003 4:53:38 PM
Override - Parcel Holds  5/30/2003  
BLD-Conference5/19/20035/21/20035/21/2003APART
DetailsJim Storey
###-#### calvin ###-#### calvin recieved oversized glazing for 3 rd floor ok. 5/21/2003 11:08:59 AM
FIRE-Conference5/19/20035/21/20035/21/2003APART
DetailsRick Jackson
###-#### calvin met with Jim Storey, Bill and Calvin about exit signs and requirements for final 5/21/2003 11:15:17 AM
BLD-Conference5/16/20035/19/20035/19/2003PPASS
DetailsJim Storey
###-#### all but 3 rd floor glazing doors ok 5/19/2003 4:13:11 PM
Override - Parcel Holds  5/19/2003  
Override - Parcel Holds  5/19/2003  
BLD-Final5/15/20035/16/20035/16/2003APART
DetailsJim Storey
list noted on plan with calvin mim. defic. left. 5/16/2003 11:26:27 AM
Override - Parcel Holds  5/16/2003  
BLD-Conference5/14/20035/15/20035/15/2003ACANC
DetailsJim Storey
###-#### calvin
BLD-Conference5/12/20035/14/20035/14/2003APASS
DetailsJim Storey
fire shudder test on mail rm /slider bagage 2/messinene over look 3 dr floor ok. pending all others 5/14/2003 10:06:10 AM
Override - Parcel Holds  5/14/2003  
BLD-Conference5/12/20035/13/20035/13/2003PFAIL
DetailsJim Storey
list of doors that no not meet listings or functioalty. 5/13/2003 5:05:13 PM
BLD-Conference5/12/20035/12/20035/12/2003PCANC
DetailsJim Storey
###-#### calvin
Override - Parcel Holds  5/12/2003  
Override - Parcel Holds  5/12/2003  
BLD-Conference5/8/20035/9/20035/9/2003APASS
DetailsJim Storey
###-#### calvin
FIRE-Conference5/7/20035/8/20035/8/2003APART
DetailsRick Jackson
CALVIN ###-#### verified operation of new smoke/fire dampers on third floor by horizontal exit - okay 5/8/2003 2:09:20 PM
Override - Parcel Holds  5/8/2003  
Override - Parcel Holds  5/7/2003  
BLD-Conference5/6/20035/6/20035/6/2003PFAIL
DetailsJim Storey
###-#### calvin 3rd floor 2hr wall not complet f/s/d ele problem, 5/6/2003 5:17:46 PM
Telephone call  5/6/2003 DONE
called Jim Storey to get direction on what to do with the plans that were dropped off today, transmittal letter, three copies of a letter and drawing index, three sets of PR-048.
Override - Parcel Holds  5/6/2003  
BLD-Conference5/2/20035/5/20035/5/2003APART
DetailsJim Storey
CALVIN ###-####
Override - Parcel Holds  5/2/2003  
BLD-Conference4/29/20034/30/20034/30/2003ACANC
DetailsJim Storey
###-####
BLD-Conference4/30/20034/30/20034/30/2003PFAIL
DetailsJim Storey
2 nd floor as noted with calvin. 4/30/2003 5:31:09 PM
BLD-Conference4/23/20034/24/20034/24/2003PPASS
DetailsJim Storey
CALVIN ###-#### basement fire stopping complet. 4/24/2003 5:02:18 PM
BLD-Conference4/22/20034/23/20034/23/2003AFAIL
DetailsJim Storey
###-#### calvin c/n listing for door butts as fire assembly/ justafy door closers in boiller rm with out side wind presure for self close and latch. 4/23/2003 10:40:37 AM
Print Occupancy Form  4/23/2003 DONE
Routing - PLAN CHECK4/23/2003 4/23/2003 PASS
CCD-066 See plan reviewer's activity 4/23/03 for additional information on modification. JCM
Plan Reviewer's activity  4/23/2003 PASS
Reviewed and approved three plan modifications to the airport approved plans. PR-056, CCD-065 & CCD-066. These modifications are as follows: PR-056 is to add one-hour fire-resistive tenant walls to divide Lease Space B10, in the basement, into three smaller lease spaces #B10, B10A & B10B. This also includes associated electrical and mechanical work. These areas are still future lease spaces and will require tenant improvement permits to finish for occupancy. Jim Storey has advised the contractor of such. CCD-065 is for the build-out of a small tenant space at the second floor office area for the TSA. To enlarge the mezzanine level ETD room in area "B" and to add a second exit stairway from the mezzanine area. CCD-066 is to construct an new Encode Station #187on the main floor level of area "B". All work per approved plans. JCM
PLANS/APPL TAKEN TO FRONT DESK  4/23/2003 PASS
Routing - PLAN CHECK3/31/2003 4/23/2003 PASS
Plan modification CCD 064/065 See plan reviewer activity for additional information on modification. JCM
Override - Parcel Holds  4/22/2003  
Routing - FIRE4/15/2003 4/22/2003 PASS
DetailsBill Alexander
CCD-066, Notes/requirements attached!
BLD-Conference4/18/20034/21/20034/21/2003PNH
DetailsJim Storey
###-#### ###-#### called left measage no call back. 4/21/2003 4:37:31 PM
BLD-Framing/Rough-in4/17/20034/18/20034/18/2003PPASS
DetailsJim Storey
RIGO CELL ###-#### CALL 1ST BEFORE INSP -FOR SECURITY DOORS IN TERMINAL 2 nd floor exit ok proto type/ basement override ok 4/18/2003 3:57:08 PM
Override - Parcel Holds  4/18/2003  
BLD-Conference4/17/20034/17/20034/17/2003PPASS
DetailsJim Storey
CALVIN ###-#### verified tempered on glazing pannels at rotunda at half way point of instulation./ third floor fire stopping in progess. 4/17/2003 3:20:56 PM
Override - Parcel Holds  4/17/2003  
Routing - FIRE4/14/2003 4/17/2003 PASS
DetailsBill Alexander
(No Notes Attached) Reviewed/approved plan modifications for CCD-064 and CCD-065. CCD-064 is the installation of some additional counter partitions and double acting half-doors at each end of the ticket counter on the second floor. Includes finishing a 170-ft/2 CTX Control Room #219B, a 375-ft/2 EDS Viewing Room #219 and TSA Communications Room #219A, with a remaining 515-ft/2 future lease space #219C. This work is on the second floor office area between grid lines E.3&F and 5&6. CCD-065 is to enlarge EDS Room # 208 to 1135 ft/2 and to add a second steel exit stair from the mezzanine to the ground level. This work is at the baggage screening mezzanine area between grid lines F.9&G.3 and 4.9&5.9.
Override - Parcel Holds  4/17/2003  
BLD-Conference4/14/20034/15/20034/15/2003APASS
DetailsJim Storey
CALVEN ###-####
Plan Reviewer's activity  4/15/2003 PASS
Reviewed and approved as submitted CCD-066 plan modification for the construction of a 220 sq. ft. stand alone metal and glass enclosure used as a computer monitoring station for the baggage conveyor system as well as an encode station where lost baggage will be reconciled back onto the conveyor system. this enclosure is located at the baggage make-up room between grid lines E3&F and 3&4.
BLD-Conference4/11/20034/14/20034/14/2003APASS
DetailsJim Storey
CALVIN ###-#### colored coded 2 nd floor for opening protection. 4/14/2003 9:55:31 AM
Override - Parcel Holds  4/14/2003  
Plan Reviewer's activity  4/14/2003 PASS
Reviewed and approved plan modifications for CCD-064 and CCD-065. CCD-064 is for the installation of some additional counter partitions and double acting half-doors at each end of the ticket counter on the second floor. Also to finish a 170 sq. ft. CTX Control Room #219B, a 375 sq. ft. EDS Viewing Room #219 and TSA Communications Room #219A, with a remaining 515 sq. ft. Future Lease Space #219C. This work is on the second floor office area between grid lines E.3&F and 5&6. CCD-065 is to enlarge EDS Room # 208 to 1135 sq. ft. and to add a second steel exit stair from the mezzanine to the ground level. This work is at the baggage screening mezzanine area between grid lines F.9&G.3 and 4.9&5.9
BLD-Conference4/8/20034/11/20034/11/2003PCANC
DetailsJim Storey
DON ###-####
Override - Parcel Holds  4/11/2003  
BLD-Conference4/8/20034/10/20034/10/2003AFAIL
DetailsJim Storey
calvin ###-####
Override - Parcel Holds  4/8/2003  
Override - Parcel Holds  4/8/2003  
BLD-Framing/Rough-in4/1/20034/3/20034/3/2003APART
DetailsJim Storey
first floor ok for ceilling all but restaroom and rental ares ajasent to south coridor. 4/3/2003 4:50:05 PM
BLD-Other4/3/20034/3/20034/3/2003PCANC
DetailsRick Jackson
see fire conference for this date 4/3/2003 5:03:21 PM
FIRE-Conference4/3/20034/3/20034/3/2003PPART
DetailsRick Jackson
met with Al Massi; Jim Story and Calvin about requirements for occupancy; requested written plan for sequence of events for fire alarm work and all areas sprinklered with preaction systems working
Override - Parcel Holds  4/1/2003  
BLD-Conference3/24/20033/31/20033/31/2003APART
DetailsJim Storey
CALVIN; Phone #: ###-#### Internet Inspection Request from: Darla Downs meeting to start temp occ. main terminal all but area b. letter to follow. 4/1/2003 8:52:32 AM
FIRE-Conference3/28/20033/31/20033/31/2003APART
DetailsRick Jackson
830 met with Jim Storey and airport reps about occupancy for May 9th; area B won't be complete; will need plan for alarm monitoring with concourse A and B and new panel 3/31/2003 10:46:51 AM
Plan Modification Accepted  3/31/2003 DONE
Plan modification for CCD064/065. Received three copies of additional sheets A2.1B, A2.2A, A2.2C, A2.7B, A2.9B, A2.9C, A3.1B, A3.1F, A4.5A, A5.1Q, A6.2A, A6.2C, A7.1C, A7.2A, A9.3B, A9.3C, S2.4B, S2.4B.1, S2.4B.2, S5.39, M2.2A, M2.2C, M2.6C, M3,2A, M3.2C, M4.3, M7.1A, M7.1B, E0.1, E1.2, E1.4, E1.11, E3.1H, E3.2A, E3.2C, E4.1F, E4.2A, E4.2C, E5.1H, E5.2A E5.2C, E6.0, E7.1, E7.3, E7.4, E7.5, E7.7, E9.1F, E9.2A, E9.2C, D10.1A, E10.1B, E10.1G, E10.2A, E10.2C * CCD-064 * viewing room and ETD's at oversize 1 and 2. CCD-065 * room modifications on area "B" mezzanine. KMM
Additional plans submitted  3/31/2003 DONE
Additional plans for CCD 064/065 plan modification.
Received Certificate of Value  3/31/2003 DONE
Received for plan modification CCD 064/065 Initial value * project value $518,000 elect. $324,000 plumb. $5,820 mech. $19,400 fire sprinkler $3,880 fire alarm systems $485,000
CHANGE STATUS TO (PND)  3/31/2003 DONE
Plan modification CCD 064/065
Plans ACCEPTED BY PLAN TECH  3/31/2003 DONE
Plan modification CCD 064/065 kmm
FIRE-Conference2/24/20032/26/20032/26/2003ACANC
DetailsRick Jackson
calvin ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie rescheduled for 2/25 2/25/2003 12:30:38 PM
FIRE-Conference2/25/20032/25/20032/25/2003PPART
DetailsRick Jackson
all dampers checked - one not working on third floor at AHU 6 return; will recheck it at a later date 2/25/2003 3:40:18 PM
BLD-Conference2/21/20032/24/20032/24/2003APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/21/2003 at 2:48:42 PM. Contact: ###-####. a line colm. floor septration ok. 2/24/2003 9:31:22 AM
FIRE-Sprinkler Rough-in2/19/20032/20/20032/20/2003AFAIL
DetailsRick Jackson
calvin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie not a sprinkler r/i' checked smoke/fire damper operation - basement dampers are all okay now; started checking other floors; first floor ceiling detectors at vestibules are sampling tube type on 2 west vestibules and should be in-duct detectors as the sampling tubes won't work properly due to location; several dampers on first and second floor not working and will need to verify operaration 2/21/2003 9:20:21 AM
BLD-Conference2/18/20032/19/20032/19/2003APASS
DetailsJim Storey
calvin ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie all basement areas with cilling grid ok for cover fire stopping and grid ok for cover. 2/19/2003 9:17:37 AM
FIRE-Final Inspection2/12/20032/14/20032/14/2003AFAIL
DetailsRick Jackson
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung started checking smoke/fire dampers - damper at detector M1-82 not closing otherwise the basement dampers are okay 2/14/2003 12:28:37 PM
BLD-Conference2/13/20032/14/20032/14/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/13/2003 at 11:34:16 AM. Contact: ###-####. coridor in basement ok for cover of ceilling all but chase in restaroom and securty rms . mech/ refegration rm/boiler rm pending insp basement. 2/14/2003 10:53:00 AM
BLD-Conference2/12/20032/13/20032/13/2003AFAIL
DetailsJim Storey
basement fire stopping not complet/ ceilling grind ok in all but vestabules. 2/13/2003 9:54:36 AM
BLD-Conference2/11/20032/12/20032/12/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/11/2003 at 11:39:10. Contact: ###-####.out of time 2/12/2003 5:56:11 PM
FIRE-Sprinkler Rough-in2/7/20032/7/20032/7/2003PPART
DetailsRick Jackson
okay to cover area between rotunda and ticket area on second floor; need fireproofing in spots at the "fish"
BLD-Framing/Rough-in1/30/20032/5/20032/5/2003AFAIL
DetailsJim Storey
calvin-fire caulking for ceiling; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie basement fire stopping not instaled per the listing on insulated pipes min 1/2 to 1 1/2 with 5/8 depth and 1/4 bead. other penatrations not complet through out. wall continuity must be maintaned. 2/5/2003 9:41:04 AM
BLD-Conference1/27/20031/30/20031/30/2003APART
DetailsJim Storey
###-#### bill ###-#### bill meeting with fire and mech for alarm system function . 1/30/2003 12:30:00 PM
FIRE-Conference1/27/20031/30/20031/30/2003APART
DetailsRick Jackson
###-#### bill met with working group about smoke fire damper control 1/30/2003 12:39:00 PM
BLD-Wall cover1/15/20031/16/20031/16/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/15/2003 at 07:58:12. Contact: ###-####. visqueen verified to meet fire restant/ fire prooffing reports to be followed up with special insp. 1/16/2003 12:07:12 PM
(F) Reprint permit  1/14/2003 DONE
BLD-Framing/Rough-in12/10/20021/3/20031/3/2003APART
DetailsJim Storey
fire stopping basement needed. 1/3/2003 10:33:26 AM
FIRE-Conference12/30/200212/30/200212/30/2002APART
DetailsRick Jackson
met with Steve of LEA Electirc; c/n issued - need detectors installed within 5 ft of smoke/fire dampers; need access doors at all dampers; will need to verify duct detector operation with air differential pressure test per Simplex manual instructions; duct detectors are installed at some smoke/fire dampers - plans show in-duct detectors; numerous pockets in computer room ceiling which will require detectors for pre-action system 12/30/2002 11:00:34 AM
BLD-Framing/Rough-in12/10/200212/26/200212/26/2002AFAIL
DetailsJim Storey
wip 3 rd floor top of corrordor gyp/ hydronic pipe fire stopping./ visqueen listing. 12/26/2002 10:39:48 AM
Inspection Record Card- Bld  12/26/2002 DONE
Print Occupancy Form  12/26/2002 DONE
Telephone call  12/26/2002 DONE
plan mod ready, talked to Martin w/ CSHQA
Plan resubmittals received  12/23/2002 DONE
Received (1) copy of letter with details regarding exiting modifications at east ramp to pedestrian walkway. Routed to Jim Storey.
BLD-Framing/Rough-in12/10/200212/19/200212/19/2002APART
DetailsJim Storey
Routing - PLAN CHECK12/16/2002 12/19/2002 PASS
(CCD-061) - This approval is for the plan Modification for the raising of a portion of the roof at the new baggage handling area and to construct a new mezzanine area for baggage screening equipment and personnel. This modification also required the rerouting of some of the baggage handling conveyer equipment.
Plan assigned to (JCM)10/29/2002 12/19/2002 PASS
DetailsJohn Menard
12/19/2002 15:48:57 JCM - activity updated through activity BLDA022 from case BLD00-03428.
PLANS/APPL TAKEN TO FRONT DESK  12/19/2002 PASS
Additional plans submitted  12/18/2002 DONE
CCD-061
Received two copies of final set of sheets, 354L001REV9, 354L008REV3, 354001REV5, 354P002REV3, 354P003REV7, 354P004REV4, 354P005REV1, 354P006REV1, 354P007REV1, 354P008REV1, 354E001REV2, 354E002REV2, 354E003REV5, 354E004REV4, 354E005REV6, 354E006REV1, 354E007REV3, 354E008REV4, 354E009REV3, 354E010REV1, 354E011REV1, 354E012REV1, 354E013REV1, 354F004REV2, 354F005REV2, 354F006REV2, 354F006aREV0, 354F014REV3, 354F015REV3, 354F016REV3, 354F016aREV1, 354F020REV1, 354F021REV1, 354F022REV1, 354F022aREV0, 354D015REV2, 354D027REV1, and a letter from AHJ. Routed one copy to John M and one copy to Jim S. kmm
Telephone call  12/18/2002 DONE
CALLED 12-18-02
Inspection Record Card- Bld  12/18/2002 DONE
BLD-Framing/Rough-in12/12/200212/17/200212/17/2002ACANC
DetailsJim Storey
###-#### JEFF
BLD-Final12/16/200212/17/200212/17/2002PCANC
DetailsJim Storey
calvin ###-####
FIRE-Final Inspection12/16/200212/17/200212/17/2002PPART
DetailsRick Jackson
calvin -###-#### -pending fn occ insp okay to use a portion of the elevated walkway per letter of agreement with PDS/FD and airport 12/18/2002 11:28:21 AM
Routing - PLAN CHECK12/16/2002 12/17/2002 PASS
CCD-063 - This approval was for a plan modification to construction a new steel stair, ramp and canopy at the roof of the existing terminal building only. Additional drawings will be required to review any further construction in this area and within the temporary elevated walkway. There is no approval to occupy the temporary walkway under this modification. JCM
BLD-Framing/Rough-in12/12/200212/16/200212/16/2002AFAIL
DetailsJim Storey
FR JEFF- ###-#### fire stopping signage area of refuge/ exit/ remove doors/ handrail returns./ door hardware. 12/16/2002 4:47:21 PM
Routing - FIRE12/12/2002 12/16/2002 PASS
Plan Modification (CCD-061)
Routing - FIRE12/12/2002 12/16/2002 PASS
CCD-063
BLD-Framing/Rough-in12/10/200212/12/200212/12/2002AFAIL
DetailsJim Storey
###-#### HAS NOTHING TO DO WITH THE RESUBMITTLE. first floor floor penatrations missing ele plm/ floor pour back one location at entry of road way/ fire proofing patch/ main shaft flue pipe clearance/ shaft intagraty not complet at curtin wall./ base track to stud screws missing exterior walls east half of bld./membrane penatrations not per listing and not complet./ top of wall slip track protecrtion back of bathrooms not complet as well as fire tapping./ clean up all debri fron unuseable spaces. 12/12/2002 11:43:14 AM 12/12/2002 11:50:27 AM
Plan Reviewer's activity  12/12/2002 PASS
Reviewed and approved the modification for CCD-061. This modification is to raise a portion of the roof at the baggage handling area and to construct a new mezzanine for the placement of baggage inspection machines and personnel. This modification also includes the revisions to reroute the baggage handling systems to accomodate the new mezzanine and equipment. JCM
Routing - PLAN CHECK11/26/2002 12/12/2002 PASS
Plan Modification (CCD-061)
Plan Reviewer's activity  12/9/2002 PASS
I am approving the structural portion of the baggage area modification for construction (CCD-061). JCM
Routing Off Site - STRUCTURAL12/4/2002 12/6/2002 PASS
Contacted PDQ to take revised modification CCD-061 of 12/3/02 to outside eng. kmm Received an e-mail from the consulting structural engineer indicating that all resubmittal items have been adequately addressed and no further review is required. JCM
Additional plans submitted  12/5/2002 DONE
Plan modification CCD-061 Received three copies of additional plans M0.1, M2.1B, M2.4A, M2.6C, M4.1, M4.2, P3.1A, P3.1B, P3.4A, P4.0, E0.1, E1.2, E1.3, E1.11, E3.1A, E3.1B, E3.1H, E3.4A, E4.1F, E5.1B, E5.1H, E7.2, E7.3, E7.4, E7.6, E7.7, E9.1A, E9.1B, E9.1F. One copy of letter. Routed to John M. kmm
Plan resubmittals received  12/3/2002 DONE
Plan Modification (CCD-061) Received three copies of revised sheets S2.4B, S2.4B.1, S2.4B.2, S4.8, S5.37, revised structural design calculations dated Dec 3,02. Structural review comment letter with attached building department struct. review comments dated 11/21/02. Routed one copy to outside eng. and two copies to John M. kmm
Plan Modification Accepted  11/27/2002 DONE
Plan modification for CCD-063. Received three copies of sheets A1.6B (revised), A1.6G, S3.1P, S3.1Q and two copies of associated calculations
. Plan mod consists of construction of a new covered ramp & stair system for access from the existing terminal, via the east terminal roof. to the temporary elevated passenger walkway. kmm
Plan Modification Accepted  11/26/2002 DONE
Received three copies of plan modification (CCD-061) drawings one copy of specifications for ADA lift one copy of 1/2 size approved baggage conveyor preliminary design drawings (for reference). kmm
FIRE-Conference11/25/200211/25/200211/25/2002PPART
DetailsRick Jackson
JEFF ###-#### FOR CONF met with Sam of TVFP about fire sprinklers for the temp ramp for the temp walkway; I was given some plans and will contact Sam Rogers and Bill A about it 11/25/2002 4:41:37 PM
Plan resubmittals requested  11/21/2002  
Faxed the architect of record a copy of the plan review comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL10/29/2002 11/21/2002 FAIL
Contacted PDQ to take plan modification (CCD-061) Area B Baggage Make-up Room #142 to outside eng. Received an e-mail from the consulting structural engineer requesting revisions. JCM
BLD-Wall cover11/13/200211/13/200211/13/2002PPASS
DetailsJim Storey
shaft in basment at boiller ok.
Routing - PLANNING10/29/2002 11/1/2002 PASS
Plan Modification (CCD-061) Area B Baggage Make-up Room #142
CHANGE STATUS TO (ISS)  10/29/2002 DONE
Per marlene this modification will not change the status of permit from issue to pend. I had already changed to pend so put back to issue status. kmm
Plan routing begun/TENANTS  10/29/2002 DONE
Plan Modification (CCD-061) Area B Baggage Make-up Room #142
Plan Modification Accepted  10/25/2002 DONE
Received three copies of plan modification (CCD-061) New Passenger Terminal Building * Area B Baggage Make-up Room #142
BLD-Final10/22/200210/23/200210/23/2002PPART
DetailsJim Storey
partial final conc A restroom; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
FIRE-Final Inspection10/14/200210/14/200210/14/2002APART
DetailsRick Jackson
okay for new bathroom in concourse A 10/14/2002 9:25:58 AM
BLD-Wall cover9/27/20029/30/20029/30/2002APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/27/2002 at 12:42:00. Contact: ###-####.a concorce walkway c/n made ok on strucral joist. / skylight at rotunda missing 4 bolts and 2 need tightened./ curtian wall fire stopping in progess ok/ f&t caculation to justify basment coridor as well as smoke and flame listing for wall assemblie./ floor penatrations at first and second not complet./east walkway engineer to aprove backer plates at fpj ok to cover walls. 9/30/2002 2:50:53 PM
Plan resubmittals received  9/5/2002 DONE
Received three copies of revised sheets A2.1C, A2.7C, A2.9A, A2.9D, A5.1H, A9.3D, F2.1C, E3.1C, E4.1C, E5.1C, E7.2, E7.5, E7.6, E8.1C, E9.1C, M2.1C, M3.1C, M4.3, M7.1B, P3.1C, P4.0, P5.1. AND THREE COPIES OF REVISED SHEETS A1.2A, A1.3D, A2.1B, A2.5A, A7.1C, A7.2A, A7.2B. Routed to John M. kmm
Contacted Matt P. to come and pick up plans to take to site. kmm
BLD-Framing/Rough-in8/29/20028/30/20028/30/2002APART
DetailsJim Storey
larry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie 2h at top of wall ok on d line west to expantion joint in bldg./a concorse temp walk way colm joist at roof knife plate and bottom chord cut need justication. 8/30/2002 10:20:02 AM
CHANGE STATUS TO (ISS)  7/26/2002 DONE
BLD-Framing/Rough-in7/24/20027/25/20027/25/2002PPART
DetailsJim Storey
calvin ###-#### skylight calvin ###-#### need shop drawninings and pick up permit at city//skylight 7/25/2002 12:48:37 PM
BLD-Framing/Rough-in7/19/20027/19/20027/19/2002PPART
DetailsJim Storey
fr & skylight calvin- ###-####--per marlene ok to insp in ready status
Plan assigned to (JCM)5/1/2002 7/17/2002 PASS
DetailsJohn Menard
7/17/2002 08:27:16 JCM - activity updated through activity BLDA022 from case BLD00-03428.
PLANS/APPL TAKEN TO FRONT DESK  7/16/2002 PASS
Deferred submittal for baggage handling system.
BLD-Framing/Rough-in7/11/20027/11/20027/11/2002PPASS
DetailsJim Storey
###-####- larry --fr insp basement ok 7/11/2002 6:00:32 PM
Override - Parcel Holds  7/11/2002  
Plan Reviewer's activity  7/10/2002 PASS
The deferred submittals for the baggage handling system is approved with compliance with the attached comment list. JCM A tenant improvement permit was created for the baggage handling system (BLD02-01716). JCM
BLD-Framing/Rough-in6/28/20027/1/20027/1/2002AFAIL
DetailsJim Storey
calvin-- ###-####--fr basement walk through maintane firewall deflection track top of wall and gyp. isi needs listings to address penatrations. 7/1/2002 11:41:03 AM
Override - Parcel Holds  6/28/2002  
Override - Parcel Holds  6/27/2002  
BLD-Conference6/19/20026/25/20026/25/2002APART
DetailsJim Storey
CALVEN ###-#### CALVEN deflection chart recieved from arch.###-#### 6/25/2002 1:43:26 PM
Plan resubmittals received  6/20/2002 DONE
Received two copies of revised sheets A2.3A, A2.3C, A2.7B, A2.8C, A2.9B, A6.3A, A6.3C, M2.3A,, M2.3C, M4.3, E3.3A, E3.3C, E4.3A, E4.3C, E5.3A, E5.3C, E7.1, E7.6, and one copy of cover letter. Routed to Jim S. kmm
Plan resubmittals received  6/19/2002 DONE
Received two copies of revised E3.2A, E3.2C, E4.2A, E4.2C, E5.2A, E52.C, E7.1,E7.3,E7.4, E7.5, E9.2A, E9.2C, E10.2A, E10.2C. Routed to Jim Storey. kmm
Override - Parcel Holds  6/19/2002 DONE
DetailsDarla L Downs
Parcel Tag Notes: OKAY TO SEND OUT INSPECTIONS FOR ALL TRADES ON BLD00-03428. The following note pertains to plan modifications in process involving future work.
CCD 008 Plan Modification includes:
1. Space added:
a. 3,215 S.F. first floor
b. 4,161 S.F. second floor
c. 1,533 S.F. third floor
d. basement
2. Security checkpoint has been rearranged to increase number of check points.
3. Relocation of restrooms
4. Meeter/greeter lobby was added at the second floor adjacent to security checkpoint as a holding area for people waiting for passengers.
5. Rental car lobby at the first floor was expanded in the area
below the meeter/greeter lobby on the second floor.
6. A third floor mech. room was added to support the additional building area.
CCD 011 Plan Modification includes:
1. Modifications to current basement layout (under to accomodate airport storage needs & additional space needs for airport police force.
(any questions contact John Menard at ###-####)

(5-20-02) Please override this tag for all activities associated with permit BLD02-01037. CJW Reason for OverRide:
Override - Parcel Holds  6/19/2002  
Plan resubmittals received  6/14/2002 DONE
Received two full size sets of resubmittal sheets AO.5C and three half-size sets of sheets A0.5C. Received one copy of revised sheets AT-1 thru AT-11. Routed to Jim Storey.
Plan resubmittals received  6/13/2002 DONE
Received three complete half sets of resubmittal plans showing CCD 2-12, CCD 19-21, CCD 39, CCD 40, CCD 41. Routed to Jim Storey.
Plan resubmittals received  6/13/2002 DONE
Received three sets of resubmittal sheets 354l001, 354m001, 354m002, 354p001, 354p002, 354P003, 354P004, 354E001, 354E001, 354E002, 354E003, 354E004, 354E005, 354E006, 354E007, 354E008, 354E009, 354E010, 354E011, 354S001, 354S002, 354S003, 354S004, 354S005, 354S006, 354S011, 354S012, 354S013, 354S014, 354S015, 354S016, 354D005, 354D015, 354D016, 354D017, 354D018, 354D019, 354D020, 354D021, 354D022, 354D023, 354D024, 354D025, 354D026, 354D027, (3) copies of Field Parts List w/PLC Network Communications drawings, (3) sets of Electrical drawings for Inbound System, (3) sets of Electrical Drawings for Outbound System, (3) sets of engineered approved submittals from Glidepath Steel Works Baggage Handling, (3) sets of structural calculations, (1) set of submittal addressing Flame testing of conveyor belting SCANDURA. (1) transmittal, Routed to John Menard.
Plan resubmittals received  6/11/2002 DONE
CCD-043 Received one set of resubmittal A1.6C-2 with cover letter/transmittal. routed to Jim Storey.
Plan resubmittals received  6/10/2002 DONE
CCD-039 Received two sets of resubmittal sheets A2.2, A2.2A, A2.2C, A2.7B, A2.9A, A2.9B, A3.1B, A3.1E, A5.1B, A5.1C, A5.1M, A5.1N, A5.1Q, A6.2A, A6.2C, A9.1D, A9.2A, A9.3B, F2.2A, F2.2C, M2.2A, M2.2C, M3.2A, M4.2, M4.3, M7.1A, M7.1B, P3.2A, P3.2C, P3.5C, P6.1, with cover letter. Routed to Jim Storey.
Print Occupancy Form  6/6/2002 DONE
Override - Parcel Holds  6/6/2002  
Print Occupancy Form  6/6/2002 DONE
Override - Parcel Holds  6/6/2002  
Inspection Record Card- Bld  6/6/2002 DONE
Telephone call  6/6/2002 DONE
Called plan mod ready
PLANS/APPL TAKEN TO FRONT DESK  6/5/2002 PASS
Plan modification for CCD-008. JCM
Routing - PLAN CHECK5/17/2002 6/5/2002 PASS
Plan Modification CCD-008
Plan assigned to (JCM)3/15/2002 6/5/2002 PASS
DetailsJohn Menard
6/5/2002 10:55:37 JCM - activity updated through activity BLDA022 from case BLD00-03428.
Routing Off Site - STRUCTURAL5/15/2002 5/31/2002 PASS
Plan Modification CCD-008, sent structural resubmittal to outside engineering.
Plan resubmittals received  5/29/2002 DONE
CCD-040 Received two copies of resubmittal sheets A2.3A, A2.3C. A2.7B, A2.8B, A2.8C, A2.9B, A5.1N, A5.1Q, A6.3A, A6.3C, M2.2A, M2.3A, M3.3A, M4.3, E3.3A, E3.3C, E4.3A, E4.3C, E5.3A, E5.3C, E7.1, E7.6, E9.2C, E9.3A, E10.3A, E10.3C. Routed to Jim Storey.
BLD-Conference5/21/20025/21/20025/21/2002PPASS
DetailsJim Storey
1. (Approved fabricators) Special inspections required by the 1997 UBC are not required where the work is done on the premises of a fabricator registered and approved by the building official to perform such work without special inspection. The approved fabricator shall submit a certificate of compliance that the work was performed in accordance with the approved plans and specifications to the building official and to the engineer or architect of record. (1997 UBC 1701.7)reviewed all submital with superviser to have fabracator SME steel fabracators meet ubc 1701.7 for aproval to discontinue third party insp. engineer of record letter as well as all documents required to meet 1701.7 are on file with the building dept. and aproved.
Plan resubmittals received  5/20/2002 DONE
CCD-008 PLAN MODIFICATION Received two copies of revised sheet A2.3C Routed to John M. kmm
Routing - FIRE5/16/20025/17/20025/17/2002 PASS
DetailsRichard Dailey
Not Notes Attached-Field Verify Changes
Plan resubmittals requested  5/16/2002  
Faxed the architect of record a request for minor revisions and resubmitted plan sheets for plan modification CCD-008. JCM
Routing - PLAN CHECK5/8/2002 5/16/2002 FAIL
CCD-008 & CCD-011 Plan Modification
Plan resubmittals received  5/15/2002 DONE
CCD-008 Plan Modification, Received three copies of resubmittal structural calculations with cover letter. routed to john menard.
Routing - PLANNING5/8/2002 5/8/2002 PASS
CCD-008 Plan Modification
Plan Reviewer's activity  5/8/2002 FAIL
Faxed Matt Huffield a list items that needed to be submitted before I can review the plans on the deferred submittal on the baggage conveyor system. JCM
Routing - PLAN CHECK4/23/2002 5/8/2002  
CCD-08 Modification
Routing - PLAN CHECK4/15/2002 5/8/2002  
CCD-011 PLAN MODIFICATION AIRPORT BASEMENT. KMM
Plan Reviewer's activity  5/1/2002 PASS
Reviewed and approved the deferred submittal plans and information for the Skywall, skylight systems. JCM
Plan resubmittals requested  4/29/2002  
Faxed the architect of record a copy of the comment list from the consulting structural engineer requesting additional revisions. JCM
Routing Off Site - STRUCTURAL4/18/2002 4/29/2002 FAIL
CCD-008 (contacted Pdq to take CCD-008 Plan mod. to outside eng.) kmm Received a letter from the consulting structural engineer requesting additional revisions. JCM
Plan resubmittals received  4/26/2002 DONE
Plan Modification CCD-08Received (1) copy of comment letter from CH2M Hill. Routed to John Menard.
Plan resubmittals received  4/24/2002 DONE
Received three copies of revised sheets 1of 9, 1A of 9 and 1 thru 17 for skylight. Routed two copies to John M. and put one copy in hold box. kmm
Plan resubmittals received  4/23/2002 DONE
CCD-008 Plan Modification * Received one copy of revised sheets S0.1, S1.2, S4.9, S5.25, S5.36, one copy of new terminal security checkpoint upgrades and one copy of response letter. Routed to John M. kmm
Routing - PLUMBING4/10/2002 4/23/2002 PASS
CCD-008 Plan Modification per plans and 2000 upc
Plan resubmittals received  4/18/2002 DONE
CCD-008 Plan Modification * Received two copies of revised sheets S0.1, S1.2C, S4.9, S5.22, S5.25, S5.36. Two copies of revised structural calculations dated 4/15/02 and one copy of structural review comment letter to Martin A. Hales dated 4/17/02 with attached building department structural review comments. Routed to John M. KMM
Plan Reviewer's activity  4/16/2002 PASS
Took the plan modification plans for CCD-011 to the front counter to release. This is the modification to finish additional areas in the basement. JCM
Telephone call  4/16/2002 DONE
brett ###-####
Routing - FIRE4/9/2002 4/15/2002 PASS
CCD-011 PLAN MODIFICATION
Additional plans submitted  4/11/2002 FAIL
Plans not stamped or signed. Did receive three copies of stamped and signed skylight calculations. Routed calculations to John M. CSHQA came and picked up unstamped and unsigned plans. kmm
BLD-Conference4/8/20024/10/20024/10/2002APART
DetailsJim Storey
for conf bill -- ###-#### waiting for design plan. 4/10/2002 11:28:02 AM
Plan Reviewer's activity  4/9/2002 PASS
Have reviewed and approved revised plans submitted for plan modification under change order CCD-011 for the finish of approximately 3220 square feet of the basement area for Apmco and airport storage; and to change the police locker room and plan storage room to men's and women's police locker rooms and a secure area. JCM
Routing - PLAN CHECK4/9/2002 4/9/2002 PASS
CCD-011 PLAN MODIFICATION
Override - Parcel Holds  4/8/2002  
Plan resubmittals requested  4/3/2002  
Faxed the architect of record a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL3/15/2002 4/3/2002 FAIL
CCD-008 CCD-011 PLAN MODIFICATION - CONTACTED PDQ TO TAKE PLAN MODIFICATION TO OUTSIDE ENG. Received comment list from consulting structural engineer requesting revisions. JCM
Routing - PUBLIC WORKS3/15/2002 3/28/2002 PASS
CCD-011 AND CCD-008 PLAN MODIFICATION
Routing - PLANNING3/28/2002 3/28/2002 FAIL
CCD-008 Modifications need to be discussed with the architect as per DR Requirements. Contacted CSHQA.
Routing - AIRPORT3/25/2002 3/26/2002 PASS
PLAN MODIFCATION: Plans taken to Airport for Jill to review for drainage, via the inter mail system. kmm
3/26/02 Routed plan back to pw. kmm
Waiting for Cert. of Value  3/21/2002 DONE
Waiting for revised cert. of value to reflect the additional plan modification of basement. $18,000. Contacted Martin Hahle at ###-#### of this need. kmm
Received Certificate of Value  3/21/2002 DONE
PLAN MODIFICATION REVISED CERT. OF VALUE * project value $1,158352.00 elect. $144,123.00 Plumb. $32,386.00 Mech. $116,079.00 Fire Sprinkler $22,579.00 Fire alarm systems $2,897.00 KMM
Received Certificate of Value  3/18/2002 DONE
PLAN MODIFICATION : Received cert. of value for plan modification. kmm
BLD-Conference3/13/20023/15/20023/15/2002APART
DetailsJim Storey
for conf calvin ###-#### walk through with r jackson/ work inprogess./ plm common coridor wall and sofit need pre rock/ ele box protection/ transpher duct openings reduced/ 2 hr shaft next to rotunda maintaned at beam seats. 3/15/2002 1:50:01 PM
FIRE-Conference3/13/20023/15/20023/15/2002APART
DetailsRick Jackson
fire for conf--calvin - ###-#### met with Jim Storey and Calvin. r/i of basement alarms; need resubmittals on larm wiring and changes 3/15/2002 11:24:18 AM
Plan Modification Accepted  3/15/2002 DONE
plan mod accepted aml paid through journal entry
CHANGE STATUS TO (PND)  3/15/2002 DONE
plan mod submitted 3/15/02 aml
Plan routing begun/NEW & ADDTN  3/15/2002 DONE
PLAN MODIFICATION
Plans ACCEPTED BY PLAN TECH  3/15/2002 DONE
PLAN MODIFICATION * WAITING FOR CERT. OF VALUE FOR MOD. ONLY. MARTIN WILL BRING IN ON MONDAY. KMM
BLD-Framing/Rough-in2/13/20022/14/20022/14/2002APART
DetailsJim Storey
interior systems insp--larry- ###-#### basement wall framing wip track sys ok job conf. 2/14/2002 11:20:37 AM
Plan resubmittals received  2/12/2002 DONE
Received two sets of plans for walkway modifications per CCD-007 with structural calculations and cover letter. Date stamped and routed to John Menard.
Plan resubmittals received  2/12/2002 DONE
Received two sets of engineered stamped skywall shop drawings with skywall calculations. Date stamped and routed to John Menard.
BLD-Conference1/22/20021/24/20021/24/2002PPART
DetailsJim Storey
###-#### 2:30 conference conf. to review rated const. of gyp.walls and occ. septrations before const begins 1/24/2002 2:21:09 PMwill need submitals for top of wall configurations at beams. 1/24/2002 3:33:45 PM
Plan resubmittals received  1/23/2002 DONE
Received three copies of plan resubmittal sheets 1of 24, 1A OF 24, 2 OF 24, 3 OF 24, 4 OF 24, 5 OF 24, 6 OF 24, 7 OF 24, 8 OF 24, 9 OF 24, 10 OF 24, 11 OF 24, 12 OF 24, 13 OF 24, 14 OF 24, 15 OF 24, 16 OF 24, 17 OF 24, 18 OF 24, 19 OF 24, 20 OF 24, 21 OF 24, 22 OF 24, 23 OF 24, 24 OF 24 AND THREE SETS OF STRUCTURAL CALCULATIONS. Since the permit was issued, routed (1) copy to Jim Storey (inspector), (1) copy to John Menard, and (1) copy to Records.
BLD-Framing/Rough-in1/10/20021/16/20021/16/2002APART
DetailsJim Storey
need to recieve engineers heat approval for beam camber of 6 line/ need engineers approval for not removing backer plsates on full pen welds to meet aws std. reviewed fireproofing material and hourly ratings required/ surface tempture min 40 deg. surface/ reviewed coridor wall conflict with 3 hr colms. 1/16/2002 11:42:01 AM
BLD-Framing/Rough-in1/10/20021/11/20021/11/2002APART
DetailsJim Storey
###-#### wip pending special insp report for first deck pour. 1/16/2002 7:42:40 AM
Plan resubmittals received  12/4/2001 DONE
Received two sets of plan resubmittals (CCD-05) sheets S1.2A, s1.2B, S1.2C, S2.4B, S4.2, S4.5, S4.7, S4.8, S5.5, S5.31, S7.1, S7.4, S8.1, S8.2. Routed to Jim Storey.
BLD-Foundation11/26/200111/26/200111/26/2001PPART
DetailsJim Storey
CALVIN ###-#### south east end wall at rotunda appears ok for cover. pending special insp. reports being keep on site. 11/26/2001 3:57:30 PM
BLD-Foundation10/24/200110/24/200110/24/2001PPART
DetailsJim Storey
###-#### CALVIN east /south ft placed with special insp.pending report. 10/24/2001 4:54:35 PM
BLD-Foundation10/8/200110/11/200110/11/2001PPART
DetailsJim Storey
###-#### kalven placed with special insp. pending report. 10/12/2001 3:40:21 PM
BLD-Foundation10/8/200110/9/200110/9/2001PPART
DetailsJim Storey
###-#### kalven center wall sec. north side of project ok pending special insp report for concrete. 10/9/2001 1:52:42 PM
(F) Reprint permit  10/4/2001  
BLD-Footing9/25/20019/27/20019/27/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/25/2001 at 12:06:07. Contact: . wip 9/28/2001 10:02:15 AM
BLD-Concrete9/10/20019/10/20019/10/2001PPART
DetailsJim Storey
CONCRETE- CALVIN -###-#### covered w/special insp. 9/10/2001 5:56:20 PM
BLD-Concrete9/4/20019/5/20019/5/2001PPASS
DetailsJim Storey
###-#### ###-#### CALVEN rebar a1-c ok wip pending special insp.report. 9/6/2001 1:42:44 PM
(F) Reprint permit  7/24/2001 DONE
Issue & PRINT to be Invoiced  7/23/2001 DONE
Plan assigned to (JCM)11/16/2000 7/19/2001 PASS
DetailsJohn Menard
7/19/01 08:37:42 JCM - activity updated through activity BLDA022 from case BLD00-03428.
Inspection Record Card- Bld  7/18/2001 DONE
Print Occupancy Form  7/18/2001 DONE
(F) Reprint permit  7/18/2001 DONE
Telephone call  7/18/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  7/18/2001 PASS
Routing - PLAN CHECK4/5/2001 7/18/2001 PASS
Routing Off Site - STRUCTURAL6/14/2001 6/19/2001 PASS
Contacted PDQ to send revised plans and calcs of 6/13/01 and 6/14/01 to outside eng. KMM received an e-mail from the consulting structural engineer that the structural plans have been approved. JCM
Plan resubmittals received  6/14/2001 DONE
Received three copies of revised S4.9 and S6.2. Routed to John M. KMM
Plan resubmittals received  6/13/2001 DONE
Received three copies S5.16, S5.30, S5.35 S5.7 and three copies of struc. calcs .Routed to John M. KMM
Routing Off Site - STRUCTURAL5/21/2001 6/8/2001 FAIL
sent one set of resubmittal plans and one book of caculations to consultanting engineer via PDQ. 5/21/01 DAR Received a faxed copy of the structural comment list from the consulting engineer requesting additional revisions. JCM
Plan resubmittals requested  6/8/2001  
Faxed the architect of record a copy of the comment list from the consulting structural engineer requesting additional revisions. JCM
Plan resubmittals received  5/21/2001 DONE
Received three sets of structural resubmittals plans and two sets of structural caculations, forwarded two sets of plans and one set of caculations to John Menard and one set of each to the consultanting structural engineer. 5/21/01 DAR
Plan resubmittals received  5/11/2001  
RESUBMITTAL 3 SETS(COPIES) ADDENDUM NO 4-NEW TERMINAL BLDG. TOOK TO JOHN M
Plan resubmittals received  5/3/2001 DONE
Received plan resubmittals from CSHQA Addendum Number Three , forwarded same to John Menard. 5/3/01 DAR
Routing Off Site - STRUCTURAL4/12/2001 4/27/2001 FAIL
Sent one full size set, Volumes 1 & 2 half size and project manuals 1,2 and 3. 4/12/01 DAR
Plan resubmittals received  4/16/2001  
Received complete sets of revised plans. These fulls sets of resubmitted plans and specifications will replace all of the original plans and specifications submitted with the original application. JCM
Routing - FIRE3/30/2001 4/5/2001 PASS
Routing Off Site - STRUCTURAL3/21/2001 4/3/2001 FAIL
Sent resubmittal plans to consultanting engineer via PDQ at John Menards request. 3/21/01 DAR Received e-mail from consulting engineer indicating that the structural review could not be completed without completed sets of drawing and calculations. JCM
Routing - PLAN CHECK3/23/2001 3/30/2001  
Inserted revisions required by the Fire plan review and routed to Fire for their review. JCM
Plan resubmittals received  3/29/2001 DONE
Received plan resubmittals from CSHQA two sets of electrical fire protection drawings and two sets of fire protection drawings plus small documents87 , forwarded same to John Menard. 3/29/01 DAR
Plan resubmittals received  3/27/2001 DONE
Received resubmittals from CSHQA 3 books of caculations, two sets of Architectual plans and two sets of concourse B addition plans and details. forwarded same to John Menard. 3/27/01 DAR
Plan resubmittals received  3/27/2001 DONE
Received one set of plan resubmittals from CSHQA on airport trmp walkway. Forwarded same to John Menard. 3/27/01 DAR
Routing - PLUMBING3/22/2001 3/23/2001 PASS
Routed roll two of plan set one and roll two of plan set two for review of resubmitted plumbing revisions. JCM per plans and 97 upc
Plan Reviewer's activity  3/22/2001 PASS
Plan resubmittals reviewed and approved as submitted. JCM
Routing - PLAN CHECK12/4/2000 3/22/2001 PASS
Routing - PLAN CHECK3/5/2001 3/22/2001  
TOOK TO JOHN M
Plan resubmittals received  3/15/2001 DONE
Received plan resubmittals from CSHQA two sets plus small documents,forwarded same to John Menard. 3/15/01 DAR
Plan resubmittals received  3/12/2001 DONE
Received three copies of revised plumbing sheets and letter from Mech. engineer of record. Three copies of revised structural sheets with supplemental calculations. Routed to John M. KMM
Plan Review Completed(1st rev)  3/5/2001 FAIL
Routing - FIRE2/27/2001 3/5/2001 FAIL
water flow & FDC locations
Plan resubmittals requested  2/27/2001  
Mailed the architect of record a copy of the comment list requesting revisions. JCM
Plan resubmittals requested  1/11/2001  
Faxed the architect of record a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL11/16/2000 1/11/2001 FAIL
Sent plans to structural consultant via PDQ . 11/16/00 DAR Received comment list from consulting engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL12/5/2000 1/11/2001 FAIL
SENT ADDITIONAL PLANS TO THE CONSULTANING ENGINEER VIA PDQ.12/5/00 DAR
Routing - PUBLIC WORKS12/8/2000 12/12/2000 PASS
Sent set one roll one to PW. 12/8/00
Additional plans submitted  12/5/2000 DONE
Received additional plans for consultanting engineer, forwarded same to consultanting engineer.12/5/00 DAR
Routing - PLUMBING11/28/2000 12/4/2000 FAIL
Sent Set one, roll one and two to plumbing. 11/28/00 DAR provide a floor drain in room B22A for water heater leakage, provide 3" waste to SS-1 in room B22A per fixture scedule, provide a floor sink for RBP-2 in room 264, secure public works pretreatment approval for OSI-1.
Routing - PLANNING11/17/2000 11/28/2000 PASS
Sent set one, roll one and two to P&Z,

Approved per DRH99-206 and per CUP99-130 (height exception).
Routing - PUBLIC WORKS11/17/2000 11/21/2000 PEND
Sent set roll one and two to PW. 11/17/00 DAR: PLANS WERE TAKEN TO MATT AT THE AIRPORT FOR REVIEW. NEEDS TO COME BACK TO PUBLIC WORKS WHEN RETURNED. LW pLANS WERE RETURNED FROM THE AIRPORT 12/8/00 AND FORWARDE BACR TO LW
Plans ACCEPTED BY PLAN TECH  11/16/2000 DONE
Application received  11/15/2000  
Fee Review-notes11/15/200011/15/2000   
Routing - PLAN CHECK11/1/2002    
Plan Modification (CCD-061) Area B baggage make-up room #142