Fee Review-notes | 11/15/2000 | 11/15/2000 | 3/23/2001 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 2/2/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8560 issued 2-2-01 to the Office of Aircraft Services.
|
BLD-Final | 1/25/2001 | 1/25/2001 | 1/25/2001 | P | PASS |
Jim Storey
|
|
|
harold ###-####
|
Permanent Occupancy | | 1/24/2001 | 1/24/2001 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/23/2001 | 1/23/2001 | 1/23/2001 | P | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Final | 1/18/2001 | 1/19/2001 | 1/19/2001 | A | NR |
Carl Dependahl
|
|
|
Harold ###-#### need fire, etc. recall 1/19/2001 10:32:29 AM
|
BLD-Framing/Rough-in | 1/5/2001 | 1/5/2001 | 1/5/2001 | A | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 1/5/2001 9:54:12 AM framing ok / coridor protection must be verified.
|
Print Occupancy Form | | | 12/27/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/27/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/27/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/26/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/26/2000 | | 12/26/2000 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 11/17/2000 | | 12/26/2000 | | PASS |
Jason Blais
|
|
|
12/26/2000 11:18:27 MYS - activity updated through activity BLDA022 from case BLD00-03430.
|
Plan Review Completed(1st rev) | | | 12/22/2000 | | PASS |
|
|
|
|
Routing - FIRE | 12/20/2000 | | 12/22/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/15/2000 | | 12/20/2000 | | PEND |
|
|
|
Plan review report sent and faxed to architect. No response required. Permit can be issued when approved by Fire Dept. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 12/18/2000 | | DONE |
|
|
|
Received three copies of revised sheets G01, A2 routed to Jason B. KMM
|
Routing - PLAN CHECK | 11/20/2000 | | 12/15/2000 | | HOLD |
|
|
|
Plans submitted do not indicate the alterations clearly to two tenant spaces. Two permits need to be submitted for approval. Both tenants are affected by this remodel. Called architect and let him know. He understood and said he would submit new paper work and plans clearly identifying the work for each tenant.
|
Routing - PUBLIC WORKS | 11/17/2000 | | 11/20/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 11/17/2000 | | 11/17/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/16/2000 | | DONE |
|
|
|
Certificate of value and Architect of Record to be sent at later by Brian Gilbreath of ZGA. 11/16/00 DAR
|
Application received | | | 11/15/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|