Fee Review-notes | 7/1/2003 | 7/1/2003 | 7/1/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/18/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8538 issued 1-18-01 to Pronto Pups at the Bank of America Center.
|
BLD-Final | 12/21/2000 | 12/22/2000 | 12/22/2000 | A | PASS |
Carl Dependahl
|
|
|
Peter, ###-#### - call 1st so he can meet you there - Bank of America Center, okto sign at office for c/o 12/22/2000 2:52:23 PM
|
Permanent Occupancy | | 12/22/2000 | 12/22/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/15/2000 | 12/15/2000 | 12/15/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 12/15/2000 10:15:43 AM
|
Issue PAID IN FULL permit | | | 12/14/2000 | | DONE |
|
|
|
|
Routing - FIRE | 11/22/2000 | | 11/22/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 11/22/2000 | 11/22/2000 | 11/22/2000 | | PASS |
|
|
|
RECEIVED APPROVAL REVIEW BY FIRE CODE ANALYST AND PUBLIC WORKS. APPROVED AS PER ATTACHED TO PLANS & ER #5148 FOR GILES RECIRCULATING GREASE HOOD. ROUTING TO PERMIT DESK.
|
Plan assigned to (DRS) | 11/20/2000 | 11/20/2000 | 11/22/2000 | | PASS |
Dan Stuart
|
|
|
11/22/2000 15:16:38 DRS - activity updated through activity BLDA022 from case BLD00-03478.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/22/2000 | | PASS |
|
|
|
TO PERMIT DESK FOR ISSUANCE.
|
Inspection Record Card- Bld | | | 11/22/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/22/2000 | | DONE |
|
|
|
|
Telephone call | | | 11/22/2000 | | DONE |
|
|
|
came in person permit ready
|
Routing - PUBLIC WORKS | 11/22/2000 | | 11/22/2000 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 11/22/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/20/2000 | 11/20/2000 | 11/21/2000 | | PEND |
|
|
|
Approved per the ER Report listing #5148 and fire department field inspection and approval based on required safety features being tested and approved. Routin to fire code analyst for review & comments.
|
Application received | | | 11/21/2000 | | |
|
|
|
|
Meeting | | | 11/20/2000 | | |
|
|
|
Met with Peter Peterson to review his proposed use and to determine if a building permit is required. The proposed hood unit requires connection to the existing structure; the giles hood is covered under an ICBO ER Report, and inspection and review are required by the Fire & Public Works Diviosions of PDS. A permit is required. This is also needed to tie the electrical & mechanical permits to a record.
|