Fee Review-notes | 11/27/2000 | 11/27/2000 | 11/9/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/18/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8816 issued 9-18-01 to Idaho Custom Wood.
|
Permanent Occupancy | | 9/5/2001 | 9/5/2001 | | DONE |
|
|
|
|
BLD-Final | 9/5/2001 | 9/5/2001 | 9/5/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/05/2001 at 08:52:00. Contact: .ok pemanent oc. 9/5/2001 2:08:01 PM
|
BLD-Final | 8/30/2001 | 8/31/2001 | 8/31/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/30/2001 at 12:39:31. Contact: ###-####. left a c/n to fire/caulk over exposed rock wool at roof joist at 1 hour fire wall shop/spray room side only. all othEr items for perm oc have been resolved/signed approved. 8/31/2001 10:10:35 AM
|
FIRE-Final Inspection | 8/16/2001 | 8/16/2001 | 8/16/2001 | P | PASS |
Joe Tawney
|
|
|
Reinsp OK for permanant occupancy 8/16/2001 4:01:36 PM
|
BLD-Final | 8/16/2001 | 8/16/2001 | 8/16/2001 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 08/16/2001 at 07:08:56. Contact: ###-####. 8/16/2001 2:47:48 PM ok for temp occ 8/16/2001 3:59:19 PM
|
BLD-Final | 8/16/2001 | 8/16/2001 | 8/16/2001 | P | PART |
Dave Hannah
|
|
|
per dave fn ok for temp occ still needs mec to sing off perm occ 8/16/2001 3:58:56 PM
|
FIRE-Final Inspection | 8/11/2001 | 8/13/2001 | 8/13/2001 | P | CANC |
Joe Tawney
|
|
|
Cancel not ready 8/13/2001 9:56:55 AM
|
BLD-Final | 8/11/2001 | 8/13/2001 | 8/13/2001 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/11/2001 at 11:57:55. Contact: ###-####.
|
BLD-Conference | 8/8/2001 | 8/9/2001 | 8/9/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/08/2001 at 17:13:31. Contact: ###-####. 8/9/2001 12:12:32 PM
|
FIRE-Final Inspection | 8/7/2001 | 8/8/2001 | 8/8/2001 | P | PART |
Joe Tawney
|
|
|
Final Spklr and alarm systems OK. Need to verify interlocks on spray booth and dust collection system. 8/8/2001 5:09:22 PM
|
BLD-Other | 7/31/2001 | 8/1/2001 | 8/1/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/31/2001 at 15:05:39. Contact: ###-####..ok to drop ceiling tile. note at this time the firewall penetrations have not yet been caulked. 8/1/2001 10:43:20 AM
|
BLD-Other | 7/26/2001 | 7/27/2001 | 7/27/2001 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/26/2001 at 15:40:32. Contact: ###-####.c/n posted. 7/27/2001 10:49:43 AM
|
Code Occupancy Approval | | | 7/24/2001 | | PASS |
|
|
|
all conditions have been met and final signed off.
|
FIRE-Conference | 7/20/2001 | 7/23/2001 | 7/23/2001 | P | PASS |
Joe Tawney
|
|
|
###-#### Conf with contr regarding dust equip interlock and spray booth 7/23/2001 5:21:25 PM
|
BLD-Aging Inspection | 6/4/2001 | 6/4/2001 | 6/4/2001 | | PART |
Russ Owen
|
|
|
exp 9/10/01. 1/4/2002 4:00:23 PM
|
BLD-Framing/Rough-in | 4/3/2001 | 4/4/2001 | 4/4/2001 | A | PART |
Russ Owen
|
|
|
steel\\###-####
|
BLD-Footing | 3/14/2001 | 3/15/2001 | 3/15/2001 | A | PART |
Tom Arcoraci
|
|
|
###-#### spec insp wip 3/15/2001 9:23:56 AM
|
(F) Reprint permit | | | 3/15/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/14/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/14/2001 | | DONE |
|
|
|
|
Routing - FIRE | 3/8/2001 | 3/13/2001 | 3/12/2001 | | DONE |
Bill Alexander
|
|
|
|
Plan assigned to (MLO) | 11/28/2000 | | 3/12/2001 | | PASS |
Mike Otto
|
|
|
3/12/2001 14:55:11 MLO - activity updated through activity BLDA022 from case BLD00-03498.
|
Routing - PLAN CHECK | 3/12/2001 | | 3/12/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/12/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/12/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/12/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/12/2001 | | DONE |
|
|
|
TALKED TO WES TO VERIFY PLANS ARE READY
|
Routing - PLAN CHECK | 3/7/2001 | | 3/8/2001 | | PEND |
|
|
|
need hazmat verification from Fire Dept. to approve with F-1 Occupancy. MLO
|
Routing - PLUMBING | 3/2/2001 | | 3/7/2001 | | PASS |
|
|
|
this review also addresses the t.i. as noted on the front for the plans' plumbing drawings do not show floor drains in the restrooms detail 6 page A-7.1 shows floor drains, verify with arch., downspout nozzel at col. A-2.75 needs to increase to 5" min., the water system drawing quality is so poor code compliance can not be determined, install to upc 610 requirements.
|
Routing - PUBLIC WORKS | 3/1/2001 | | 3/1/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 2/28/2001 | | 2/28/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/28/2001 | | DONE |
|
|
|
Received three copies of revised mech. and dust collection drawings. Three sets of revised hazardous materials inventory. One copy of cover letter. Put with plans. KMM
|
Telephone call | | | 2/28/2001 | | DONE |
|
|
|
Called Wes to let him know that Brian did approve his portion of Public Works, but PW still needs plumbing plans to look at before signing off of plans. Plumbing needs to sign off as well. I will give plans back to Mike O. until plumb. plans, that were submitted on 2.14.01, can be put with the plans. I will reroute to PW and Plumbing when Mike is ready. Marty did sign off. KMM
|
Plan resubmittals received | | | 2/14/2001 | | |
|
|
|
received 2 copys of M-1-M-2-D1-D2-P.1-P.2-P.3-P.4-E1.0-E1.1-E1.2-E2.1-E2.2-E3.0 TAKEN TO MIKE OTTO 2/14/2001/PE HAZARDOUS MATERIALS INVENTORY SUMMARY.PE
|
Routing - PLAN CHECK | 2/14/2001 | | 2/14/2001 | | FAIL |
|
|
|
hazmat report incomplete arhitect contacted by phone. MLO
|
Routing Off Site - STRUCTURAL | 12/28/2000 | | 1/26/2001 | | PASS |
|
|
|
Sent small documents to consultanting engineer. 12/27/00 DAR
|
Routing Off Site - A.C.H.D | 1/25/2001 | 1/25/2001 | 1/25/2001 | | DONE |
|
|
|
Fee's will be assessed with building permit.
|
Plan resubmittals received | | | 1/22/2001 | | DONE |
|
|
|
Received five copies of revised sheets A1.1, C1.0, C1.1, C1.2, C1.3, put with grading and drainage plans, under permit Bld00-03499. One copy of cover letter addressed to Marty S. KMM
|
Routing - PLAN CHECK | 12/26/2000 | | 1/4/2001 | | FAIL |
|
|
|
Project will be complete for occupancy under this permit and will not be a shell per Wes Steele Habitec Architecture. Additional information and plans are needed to complete plan review - corrections faxed and mailed to architect. MLO
|
Plan resubmittals requested | | | 1/4/2001 | | FAIL |
|
|
|
UBC Corrections
|
Routing Off Site - STRUCTURAL | 12/21/2000 | | 12/22/2000 | | FAIL |
|
|
|
Sent structural caculations to consultanting engineer. 12/21/00 DAR
|
Plan resubmittals received | | | 12/22/2000 | | DONE |
|
|
|
Received two copies of revised sheets A2.1 A2.2, A3.1, A4.1, response letter, site plan and United Water letter. Routed to Mike O. KMM
|
Plan resubmittals requested | | | 12/22/2000 | | FAIL |
|
|
|
structural review corrections sent to architect.
|
Plan resubmittals received | | | 12/21/2000 | | DONE |
|
|
|
received response for structural comments sent to engineer. MLO
|
Routing - FIRE | 12/13/2000 | 12/18/2000 | 12/18/2000 | | FAIL |
Bill Alexander
|
|
|
Lack building access, lack hydrant location and available flows, fire line location, lack sprinkler desing water supply.
|
Plan Review Completed(1st rev) | | | 12/18/2000 | | FAIL |
|
|
|
plans sent back to plan review
|
Plan resubmittals requested | | | 12/13/2000 | | FAIL |
|
|
|
UBC corrections
|
Routing Off Site - STRUCTURAL | 11/29/2000 | | 12/13/2000 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside eng. KMM corrections sent to architect. MLO
|
Routing - PLAN CHECK | 12/7/2000 | | 12/13/2000 | | FAIL |
|
|
|
corrections sent to architect.
|
Routing - PLUMBING | 12/4/2000 | | 12/7/2000 | | FAIL |
|
|
|
|
Routing - PLANNING | 12/1/2000 | | 12/4/2000 | | FAIL |
|
|
|
Plans do not comply with DRH00-200.
|
Routing - PUBLIC WORKS | 11/29/2000 | | 12/1/2000 | | FAIL |
|
|
|
requires drainage plan revision. per Brian M. KMM
|
Plan routing begun/NEW & ADDTN | | | 11/29/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/29/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/28/2000 | | HOLD |
|
|
|
Structural sheets not stamped or signed. Requires outside eng. copy of plans. Contacted Wes Steele at ###-####. KMM
|
Received Certificate of Value | | | 11/27/2000 | | DONE |
|
|
|
|
Application received | | | 11/27/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/27/2000 | | DONE |
|
|
|
|