Permit Ready to Issue | | | 8/21/2012 | | DONE |
|
|
|
|
CHANGE STATUS TO (FNL) | | | 8/21/2012 | | DONE |
Rita DeYoung
|
|
|
|
Case Summary (BLD) | | | 8/21/2012 | | |
|
|
|
|
BLD-Final | 7/17/2002 | 7/17/2002 | 7/17/2002 | A | PASS |
Carl Dependahl
|
|
|
rec'd eng's affidavit..ok
|
Letter of compliance | | | 7/17/2002 | | DONE |
|
|
|
Letter of Compliance #22547 issued 7-17-02.
|
BLD-Final | 6/17/2002 | 6/18/2002 | 6/18/2002 | A | FAIL |
Carl Dependahl
|
|
|
need eng's clarification & add'l statements re MTI's affidavit. 6/18/2002 11:34:36 AM
|
BLD-Final | 6/17/2002 | 6/17/2002 | 6/17/2002 | P | NR |
Carl Dependahl
|
|
|
SCOTT ###-####
|
BLD-Final | 6/14/2002 | 6/14/2002 | 6/14/2002 | P | NR |
Carl Dependahl
|
|
|
scott ###-#### fn will recall 6/14/2002 5:19:33 PM
|
BLD-Final | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | FAIL |
Jim Storey
|
|
|
repair exit sign and move handrail in center stair to 34 to 38 inches . 6/13/2002 2:21:06 PM
|
Fee Review-notes | 11/30/2000 | 11/30/2000 | 1/29/2002 | | DONE |
|
|
|
|
BLD-Final | 1/16/2002 | 1/17/2002 | 1/17/2002 | A | PART |
Carl Dependahl
|
|
|
###-####, rec'd eng's final report, ok for t/o 1/17/2002 1:25:28 PM
|
Temporary occupancy | | | 1/17/2002 | | PART |
|
|
|
Temp. Occ. Cert. #4705 issued 1-17-02 to the River Walk Apts. parking structure.
|
FIRE-Final Inspection | 1/16/2002 | 1/16/2002 | 1/16/2002 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 1/16/2002 2:01:31 PM
|
BLD-Final | 1/14/2002 | 1/14/2002 | 1/14/2002 | P | NR |
Carl Dependahl
|
|
|
###-####, need engs report, all ok's 1/14/2002 6:06:08 PM
|
BLD-Final | 1/10/2002 | 1/10/2002 | 1/10/2002 | P | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Aging Inspection | 12/10/2001 | 12/10/2001 | 12/11/2001 | | NR |
Carl Dependahl
|
|
|
wip 12/11/2001 9:58:32 AM
|
BLD-Aging Inspection | 10/8/2001 | 10/8/2001 | 10/8/2001 | | NR |
Carl Dependahl
|
|
|
apts...wip. 10/8/2001 10:46:28 AM
|
BLD-Aging Inspection | 8/7/2001 | 8/7/2001 | 8/7/2001 | | PASS |
Carl Dependahl
|
|
|
wip 8/7/2001 9:28:27 AM
|
BLD-Conference | 6/7/2001 | 6/7/2001 | 6/7/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/7/2001 1:49:28 PM met w/ bldr onsite, need eng's report
|
BLD-Concrete | 5/25/2001 | 5/30/2001 | 5/30/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/25/2001 at 12:09:08. Contact: ###-####. covered with special insp. pending report. 5/30/2001 10:08:03 AM
|
BLD-Concrete | 5/23/2001 | 5/25/2001 | 5/25/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/23/2001 at 13:04:13. Contact: (208) p.t. deck###-####...pending spec insp reports; eng'r made site visit 5/25/2001 11:41:46 AM
|
BLD-Concrete | 5/17/2001 | 5/21/2001 | 5/21/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 09:44:38. Contact: ###-####... PT slab...need eng's statement re plbg pipes, removed from col. caps 5/21/2001 2:27:59 PM
|
BLD-Conference | 5/17/2001 | 5/18/2001 | 5/17/2001 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 09:43:38. Contact: ###-####.--cancel per scott kimball
|
BLD-Conference | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/16/2001 4:58:05 PM need eng's ok for pipes in p.t. slab & column cap, verify steel laps as req'd for compression?
|
BLD-Conference | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/16/2001 4:58:05 PM need eng's ok for pipes in p.t. slab & column cap, verify steel laps as req'd for compression?
|
BLD-Concrete | 4/27/2001 | 4/27/2001 | 4/27/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/27/2001 10:20:56 AM slab at grade, NE corner; conf w/ owner: need eng'r & spec insp's affidavits for pt slab..decking/shoring wip prior to pour..req'd meeting w/ eng'r 5-7-01
|
BLD-Concrete | 4/19/2001 | 4/20/2001 | 4/20/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/19/2001 at 19:20:56. Contact: ###-####. placed with special insp.pending report. 4/20/2001 3:28:27 PM
|
BLD-Concrete | 4/17/2001 | 4/18/2001 | 4/18/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/17/2001 at 11:43:59. Contact: ###-####. placed with special insp. pending report. 4/18/2001 2:45:16 PM
|
BLD-Foundation | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/12/2001 at 08:47:57. Contact: ###-####. pend report, walls. 4/12/2001 5:11:49 PM
|
BLD-Conference | 4/2/2001 | 4/2/2001 | 4/2/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/2/2001 6:28:43 PM w/ Gary Z. re plbg c/n.
|
Plan resubmittals received | | | 4/2/2001 | | DONE |
|
|
|
Received two sets of plan resubmittals from John Price, sheets P1.0, P2.0, forwarded same to Lee Rice. 4/2/01 DAR
|
BLD-Foundation | 3/29/2001 | 3/30/2001 | 3/30/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/29/2001 at 12:31:14. Contact: ###-####. placed with special insp. pending report. 3/30/2001 1:47:22 PM
|
Plan resubmittals received | | | 3/29/2001 | | DONE |
|
|
|
Received three copies of revised sheets C1.0, P1.0, P2.0 and one copy of cover letter. Routed to Gary Ziegler. KMM
|
BLD-Footing | 3/26/2001 | 3/27/2001 | 3/27/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/26/2001 at 11:51:43. Contact: ###-####. wip mti on site 3/27/2001 9:53:17 AM
|
BLD-Footing | 3/22/2001 | 3/23/2001 | 3/23/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/22/2001 at 17:39:34. Contact: ###-####. col's; requested eng'r observe & report re p.t. deck, & overall for concrete (as designed ) deck is also 3hr occ sep. 3/23/2001 9:42:47 AM
|
BLD-Footing | 3/21/2001 | 3/22/2001 | 3/22/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/21/2001 at 17:07:53. Contact: ###-####...cols; met w/ contractor & spec insp onsite. pend report 3/22/2001 3:25:48 PM
|
Plan resubmittals received | | | 3/22/2001 | | DONE |
|
|
|
Received two copies of revised plans C1.0, A2.0, A3.0.1 and A3.0.2. Attached are a revised site plan and garage plans showing the garage floor draining to a sand and grease trap that is tied to the sanitary sewer. Routed to Carl D. KMM
|
BLD-Footing | 3/20/2001 | 3/21/2001 | 3/21/2001 | A | PART |
Jim Storey
|
|
|
###-#### placed with special insp. pending report. 3/21/2001 4:33:49 PM
|
BLD-Conference | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/19/2001 4:41:29 PM rec'd eng'g resub...called arch John Price; need insps for concrete. called bldr, has had mti onsite, need to request city insps
|
Plan resubmittals received | | | 2/27/2001 | | DONE |
|
|
|
Received two copies of revised sheets S1.1 & S1.2. Routed to Mike P. KMM
|
BLD-Footing | 2/22/2001 | 2/23/2001 | 2/23/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/22/2001 at 15:23:14. Contact: ###-####. ftgs; pend spec. insp. reports 2/23/2001 12:45:24 PM
|
(F) Reprint permit | | | 2/20/2001 | | DONE |
|
|
|
|
BLD-Footing | 2/16/2001 | 2/16/2001 | 2/16/2001 | P | PART |
Tom Arcoraci
|
|
|
pouring at 12:00 as per bob a. put in inspection for footing Scott ###-#### wip 2/20/2001 9:58:19 AM
|
Plan Reviewer's activity | | | 2/16/2001 | | PASS |
|
|
|
Approved for foundation only.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/16/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/16/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/16/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 11/30/2000 | | 2/16/2001 | | PASS |
Mike Phillips
|
|
|
2/16/2001 09:42:53 M_P - activity updated through activity BLDA022 from case BLD00-03519.
|
CHANGE ISSUED DATE | | | 2/16/2001 | | |
|
|
|
|
Telephone call | | | 2/7/2001 | | FAIL |
|
|
|
Need to discuss exits on second and thierd floors.
|
Routing Off Site - STRUCTURAL | 1/17/2001 | | 2/6/2001 | | PASS |
|
|
|
contacted PDQ to take revised plans from 1/16/01 to outside eng. John stated that there are no revised struct. calcs. at this time. KMM
|
Plan resubmittals received | | | 2/2/2001 | | DONE |
|
|
|
Received two copies of sheets A1.0 from Susan Riggs who is reviewing plans now. She put the resubs with plans.KMM
|
Plan resubmittals received | | | 2/2/2001 | | |
|
|
|
2 copys revised sheet s5 took to mike phillips/pe
|
Routing - PLANNING | 1/31/2001 | | 2/2/2001 | | PASS |
|
|
|
Approved per DRH00-161 for structure only. Revised landscape plan per DR conditions must be submitted for Staff review and approval.
|
Plan resubmittals received | | | 2/1/2001 | | DONE |
|
|
|
Received plan resubmittals from Tamura and associates, John Price, Two sets of sheets of S1.1 and S1.2, forwarded same to Mike Phillips. 2/1/01 DAR
|
Routing - PUBLIC WORKS | 1/26/2001 | | 1/31/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/26/2001 | | PEND |
|
|
|
|
Routing - FIRE | 1/22/2001 | | 1/26/2001 | | PASS |
|
|
|
Route back to PW when out of fire. KMM
|
Routing - PLAN CHECK | 1/5/2001 | | 1/22/2001 | | |
|
|
|
Routing to fire.
|
Plan Reviewer's activity | | | 1/22/2001 | | PEND |
|
|
|
Waiting for others to approve prior to issuance of permit.
|
Plan resubmittals received | | | 1/16/2001 | | DONE |
|
|
|
Received two copies of revised sheets A0.0, S1,S2, S4, S5, S6. S0.1, S1.1, S1.2. Two copies of response to structural review. Contacted John Price requesting an additional set of these revised sheets for outside eng. Mike also wanted me to inquire about revised calculations. Will route one copy of revised sheets to outside eng. after I hear from John about the calcs. The other set was routed to Mike P. When third set comes in I will route to Mike P. to complete the in-house set. 1/16/01 PM received third set of revised plans from John Price. Routed to Mike P. John also stated that struct. had not been revised. KMM
|
Routing - PUBLIC WORKS | 1/4/2001 | | 1/5/2001 | | FAIL |
|
|
|
Requires drainage plan revisions per Brian M. KMM
|
Routing - PLAN CHECK | 12/27/2000 | | 1/4/2001 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/30/2000 | | 1/4/2001 | | FAIL |
|
|
|
Sent comments to architect, additional informaiton required for further review.
|
Routing - PLUMBING | 12/21/2000 | | 12/27/2000 | | PASS |
|
|
|
|
Routing - PLANNING | 12/4/2000 | | 12/20/2000 | | FAIL |
|
|
|
Route to PW when back from planning. April ready to sign off. KMM
Plans do not comply with Design Review conditions, specifically proposed trees, and plant material not identified on site plan.
|
Routing - PUBLIC WORKS | 11/30/2000 | | 12/4/2000 | | FAIL |
|
|
|
Requires drainage plan revision and O AND M plan, Requires proof of legal land division,sewer problems. 12/4/00 DAR
|
Plan routing begun/NEW & ADDTN | | | 11/30/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/30/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 11/30/2000 | | DONE |
|
|
|
|
Application received | | | 11/30/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/30/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/5/2001 | | | | |
|
|
|
|