Fee Review-notes | 11/30/2000 | 11/30/2000 | 3/23/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 2/20/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8574 issued 2-20-01 to Mark Bottles.
|
Permanent Occupancy | | 2/16/2001 | 2/16/2001 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/16/2001 | 2/16/2001 | 2/16/2001 | P | PASS |
Joe Tawney
|
|
|
###-#### Reinsp OK for permanant occupancy 2/16/2001 5:14:20 PM
|
BLD-Final | 2/16/2001 | 2/16/2001 | 2/16/2001 | P | PASS |
Jim Sly
|
|
|
###-#### LATE PM OK for Perm Occ. 2/16/2001 3:51:52 PM
|
FIRE-Final Inspection | 2/14/2001 | 2/15/2001 | 2/15/2001 | A | FAIL |
Joe Tawney
|
|
|
richard ###-#### fire fn Final Fail C/N issued 2/16/2001 8:13:28 AM
|
BLD-Final | 2/15/2001 | 2/15/2001 | 2/15/2001 | P | CANC |
Jim Sly
|
|
|
###-####
|
BLD-Framing/Rough-in | 1/19/2001 | 1/22/2001 | 1/22/2001 | P | PASS |
Jim Sly
|
|
|
Jeanine- ###-####
|
Issue PAID IN FULL permit | | | 1/18/2001 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 12/1/2000 | | 1/17/2001 | | PASS |
Jason Blais
|
|
|
1/17/2001 13:12:44 JCB - activity updated through activity BLDA022 from case BLD00-03526.
|
Routing - PLAN CHECK | 1/12/2001 | | 1/17/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/17/2001 | | PASS |
|
|
|
|
Print Occupancy Form | | | 1/17/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/17/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/17/2001 | | DONE |
|
|
|
called permit ready
|
Routing - FIRE | 1/8/2001 | 1/11/2001 | 1/12/2001 | | PASS |
Richard Dailey
|
|
|
Field Verify. No written comments.
|
Plan resubmittals received | | | 1/12/2001 | | DONE |
|
|
|
Received two copies of revised sheetTI-1.2 Routed to Jason Blais
|
Plan Review Completed(1st rev) | | | 1/12/2001 | | FAIL |
|
|
|
failed bldg review
|
Routing - PLAN CHECK | 12/4/2000 | | 1/8/2001 | | FAIL |
|
|
|
Plan review report sent to architect and tenant. Resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Early Start Permit | | | 12/12/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 12/1/2000 | | 12/4/2000 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 12/1/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/1/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 12/1/2000 | | DONE |
|
|
|
|
Application received | | | 11/30/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/30/2000 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/8/2000 | | |
|
|
|
Plan resubmittals and response required for further review.
|