Case Summary (BLD) | | | 12/16/2011 | | DONE |
|
|
|
|
Fee Review-notes | 11/30/2000 | 11/30/2000 | 3/23/2001 | | DONE |
|
|
|
|
BLD-Final | 2/14/2001 | 2/14/2001 | 2/14/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/14/2001 at 07:11:19. Contact: ###-####.l/c isued in the field #20100 2/14/2001 8:57:10 AM
|
DOC - Permit Finaled | 2/14/2001 | 2/14/2001 | 2/14/2001 | A | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 2/14/2001 8:58:15 AM l/c isued in the field. ok
|
BLD-Concrete | 2/8/2001 | 2/8/2001 | 2/8/2001 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/08/2001 at 09:08:30. Contact: ###-####. Removal of CMU and install of steel angel lentel OK per Eng letter and plans. 2/8/2001 2:47:41 PM 2/8/2001 2:54:19 PM
|
Additional plans submitted | | | 2/5/2001 | | |
|
|
|
RECEIVED COPY OF LETTER FROM STRUCTURAL ENGINEER, HAROLD J. COX, FROM DOUG TAMURA, TAMURA & ASSOCIATES ARCHITECTS STATING THE ENGINEER WOULD ACCEPT THE USE OF THROUGH PENETRATIONS BOLTS IN PLACE OF THE WEDGE ANCHORS OF ORIGINAL PALN SUBMITTAL DESIGN.
THE THROUGH BOLTS ARE REQUIRED TO BE PLACED AT SAME LAYOUT AND EQUAL SIZE AS THE WEDGE ANCHORS, WITH A 3" MIN. WASHER ON THE MASONRY SIDE OF THE WALL AND A REGULAR WASHER ON THE ANGLE SIDE FACE.
THE ANGLE HAVE TO RETAIN THE 8" BEARING AT EACH END, BE SECURED IN PLACE BEFORE ANY REMOVAL OF WALL IS STARTED, BE ATTACHED TO A SOLID GROUTED BOND BEAM, ETC. ALL PER THE ORIGINAL ENGINEERING DETAILS. THE SPECIAL INSPECTION REQUIREMENTS STILL APPLY FOR VERIFICATION OF ALL METHODS & PROCESSES USED TO INSTALL THE SUPPORT SYSTEM ARE IN COMPLIANCE WITH THE STRUCUTRAL ENGINEERS DESIGN.
THE PERMIT HAS BEEN ISSUED AND SO THE REQUEST WILL BE ROUTED TO THE FIELD INSPECTOR, JIM STOREY FOR DISPERSMENT & FIELD REVIEW FOR COMPLIANCE WITH APPROVED PLANS AND THIOS MODIFICATION.
|
Issue PAID IN FULL permit | | | 1/19/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/16/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/16/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/16/2001 | | DONE |
|
|
|
called permit ready
|
Plan assigned to (DRS) | 12/5/2000 | | 1/13/2001 | | PASS |
Dan Stuart
|
|
|
1/13/2001 13:06:29 DRS - activity updated through activity BLDA022 from case BLD00-03527.
|
Routing - PLAN CHECK | 12/8/2000 | | 1/13/2001 | | PASS |
|
|
|
PLAN APPROVED PER NOTES ON PLANS & ATTACHED PLAN REVIEW COMMENTS. COPY OF PLAN REVIEW COMMENTS TO ARCHITECT WITH SUGGESTIONS OF SPECIFIC ASSEMBLIES HE CAN PROVIDE FOR BOLTED CONNECTIONS AND NOTING THAT SPACIAL INSPECTION IS REQUIRED.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2001 | | PASS |
|
|
|
TO PERMIT DESK FOR ISSUE.
|
Routing - PLANNING | 12/5/2000 | | 12/7/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/4/2000 | | DONE |
|
|
|
Mark Sanders stated that existing address is 901 La Pointe, however the permits deskaddressed it under 1004 W. Royal Blvd. That is why I did not put address on plans. Also a site plan would be nice. KMM
|
Received Certificate of Value | | | 12/4/2000 | | DONE |
|
|
|
Just a project value. No elect. ? KMM
|
Application received | | | 11/30/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/30/2000 | | DONE |
|
|
|
|