Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-03550
StatusFinaled
Name SOUTHSHORE OFFICES
Site Address 1175 E PARKCENTER BLVD
Project NameSOUTHSHORE OFFICES
Customer Number 
ePlanReviewNo
Description
To construct a new 7,840 sq. ft. single story, wood frame, multi-tenant office building shell and core with one 350 sq.ft. finished office space for mini-storage. All construction per the approved plans, attached comment list and CABO/ANSI A117.1. Work to include on site land scaping, utilities and parking lots. NOTE: This building is a shell only except for the 350 sq.ft. office at the souther end of the building. Separate permits and Certificate of Occupancies must be obtainted for each additional tenant space to be finished and occupied. DRH00-00160 PC#1017-00 MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes12/4/200012/4/200011/9/2001 DONE
Letter of compliance  8/30/2001 DONE
Letter of Compliance #21946 issued 8-30-01 to Scott Hedrick Construction.
BLD-Final8/28/20018/29/20018/29/2001APASS
DetailsSteven Webb
###-#### GEORGE
BLD-Final8/24/20018/27/20018/27/2001AFAIL
DetailsSteven Webb
Scheduled by a contractor via Hello! on 08/24/2001 at 13:14:52. Contact: ###-####. Not all required signatures completed. 8/27/2001 11:39:42 AM
FIRE-Final Inspection8/23/20018/23/20018/23/2001PPASS
DetailsRick Jackson
###-#### george
Code Occupancy Approval  8/22/2001 PASS
Inspected and approved. Area on corner had been disturbed. DRH had this area as a do not disturb. George Maxwell, ###-####, said that Idaho Power and improperly located their underground power line 30' outside their easement. In relocating the line, Idaho Power disturbed this area and did not refurbish. Property owners are dealing with this issue.
FIRE-Final Inspection8/21/20018/21/20018/21/2001PFAIL
DetailsRick Jackson
george ###-#### fire fn --will be on site until 3:30 address; exit sign or door hardware in office 8/22/2001 10:43:42 AM
BLD-Aging Inspection7/16/20017/16/20017/16/2001 PART
DetailsSteven Webb
wip 7/16/2001 7:56:44 AM
BLD-Framing/Rough-in5/11/20015/14/20015/14/2001APASS
DetailsSteven Webb
reinspection George ###-#### Prior c/n items corrected. 5/14/2001 11:08:30 AM
Override - Parcel Holds  5/11/2001  
BLD-Framing/Rough-in5/10/20015/10/20015/10/2001PPART
DetailsSteven Webb
George Maxwell ###-#### C/N issued--Shear and frame of office building. 5/10/2001 3:27:27 PM
Override - Parcel Holds  5/10/2001  
BLD-Concrete4/19/20014/19/20014/19/2001PPASS
DetailsSteven Webb
###-#### flat work for floor--4" 4/19/2001 2:13:40 PM
Override - Parcel Holds  4/19/2001  
BLD-Foundation4/3/20014/4/20014/4/2001PPART
DetailsSteven Webb
###-####wip-rebar set except drive through in south wall-will verify hd's at next inspection. 4/4/2001 2:58:31 PM
Override - Parcel Holds  4/3/2001  
BLD-Footing3/28/20013/30/20013/30/2001APART
DetailsSteven Webb
George ###-####Requested engineering or removal of 4 " electrical condiut at nw corner of building. ok to pour remainer of formed footing. 3/30/2001 11:59:07 AM
Override - Parcel Holds  3/28/2001  
(F) Reprint permit  3/15/2001 DONE
Issue PAID IN FULL permit  3/14/2001 DONE
Routing - PLAN CHECK2/20/2001 3/1/2001 DONE
Plan Reviewer's activity  3/1/2001 PASS
Print Pending Permit.LaserJet4  3/1/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/1/2001 DONE
Case Summary (BLD)  3/1/2001 DONE
Inspection Record Card- Bld  3/1/2001 DONE
Print Occupancy Form  3/1/2001 DONE
Telephone call  3/1/2001 DONE
called talked to Sally gave dollar amount and told her she need to let mike burden know that achd is also needed.
Plan assigned to (M_P)12/5/2000 3/1/2001 PASS
DetailsMike Phillips
3/1/2001 13:59:26 M_P - activity updated through activity BLDA022 from case BLD00-03550.
Routing - PLANNING2/16/2001 2/20/2001 PASS
Approved per DRH00-160, and as noted on the plans requiring extension of the sidewalk into the site and construction of masonry screen walls (instead of wood fences) around the HVAC units on the east side of the building.
Routing - PLAN CHECK1/17/2001 2/16/2001  
Routing - PLAN CHECK1/12/2001 1/17/2001  
Routing - FIRE1/17/2001 1/17/2001 PASS
Satisfactory water flow received. Faxed to architect.
Plan Review Completed(1st rev)  1/12/2001 FAIL
Routing - FIRE1/8/2001 1/12/2001 FAIL
need water flow info
Plan resubmittals received  1/12/2001 DONE
Received small documents and two sets of sheets A-1 and A-7. Forwarded same to Mike Phillips. 1/12/01 DAR
Routing - PLAN CHECK12/27/2000 1/8/2001  
Routing to fire
Plan Reviewer's activity  1/8/2001 FAIL
Additional information required for follow up review.
Routing - PLUMBING12/20/2000 12/26/2000 PASS
Routing - PUBLIC WORKS12/22/2000 12/22/2000 PASS
Routing - PLANNING12/8/2000 12/20/2000 FAIL
Need approval from City Attorney in order to sign off plans.
Routing - PUBLIC WORKS12/6/2000 12/8/2000 FAIL
Requires drainage plan revisions per Brian Murphy. 12/8/00 DAR
Plan routing begun/NEW & ADDTN  12/6/2000 DONE
Plans ACCEPTED BY PLAN TECH  12/5/2000 DONE
Received Certificate of Value  12/4/2000 DONE
Application received  12/4/2000  
Recd Pcfee & Taken To Pln CK  12/4/2000 DONE