Fee Review-notes | 12/7/2000 | | 11/9/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/18/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8874 issued 10-18-01 to Dr. Robert Agnetta.
|
Permanent Occupancy | | 6/29/2001 | 6/29/2001 | | DONE |
|
|
|
|
BLD-Final | 6/28/2001 | 6/29/2001 | 6/29/2001 | A | PASS |
Jim Sly
|
|
|
###-#### OK for Perm Occ. 6/29/2001 12:06:11 PM
|
DOC - Permit Finaled | 6/29/2001 | 6/29/2001 | 6/29/2001 | P | PASS |
Jim Sly
|
|
|
Added by Inspector: 316 On 6/29/2001 12:05:22 PM
|
BLD-Final | 6/21/2001 | 6/21/2001 | 6/21/2001 | P | PART |
Jim Sly
|
|
|
Added by Inspector: 316 On 6/21/2001 2:50:08 PM OK for Temp Occ.
|
FIRE-Final Inspection | 6/18/2001 | 6/19/2001 | 6/19/2001 | A | FAIL |
Joe Tawney
|
|
|
Final Fail C/N issued 6/19/2001 11:45:34 AM
|
FIRE-Final Inspection | 6/19/2001 | 6/19/2001 | 6/19/2001 | P | PASS |
Joe Tawney
|
|
|
Reinsp Pass OK for permanant occupancy 6/19/2001 3:33:38 PM
|
BLD-Final | 6/19/2001 | 6/19/2001 | 6/19/2001 | P | NR |
Russ Owen
|
|
|
fire is also going out tim ###-#### please call 1/2 hour before going to job site-fire is also going out pm today need zoning and public works. no inspection done this day. 1/19/2002 4:34:37 PM
|
BLD-Aging Inspection | 6/13/2001 | 6/13/2001 | 6/13/2001 | | PART |
Jim Sly
|
|
|
Work in progress. 6/13/2001 12:34:20 PM
|
BLD-Framing/Rough-in | 4/12/2001 | 4/13/2001 | 4/13/2001 | A | PASS |
Jim Sly
|
|
|
###-####
|
BLD-Framing/Rough-in | 4/10/2001 | 4/11/2001 | 4/11/2001 | A | PASS |
Jim Sly
|
|
|
###-####
|
Routing - PLAN CHECK | 2/12/2001 | | 2/13/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2001 | | PASS |
|
|
|
Plumbing drawings were submitted after this permit was cleared for issuance the first time. The drawings were pulled from the Permits Desk, sheets were inserted, and the drawings routed to the Plumbing Division for review. This is the 2nd time this project has been cleared for issuance.
|
Override - Parcel Holds | | | 2/13/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/13/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/13/2001 | | DONE |
|
|
|
|
Telephone call | | | 2/13/2001 | | DONE |
|
|
|
###-#### brian wilson
|
Override - Parcel Holds | | | 2/13/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/13/2001 | | DONE |
|
|
|
|
Routing - PLUMBING | 2/9/2001 | | 2/12/2001 | | PASS |
|
|
|
intake an exhaust from compressor and vacuum pump must comply with upc, verify with field inspector
|
CHANGE STATUS TO (PND) | | | 2/9/2001 | | DONE |
|
|
|
|
Telephone call | | | 2/9/2001 | | DONE |
|
|
|
Called the contractor, Brian Wilson, to tell him that the permit is NOT ready. Told him that it will not be ready until we have reviewed the resubmitted plumbing drawings. Vacuum and compressed air lines are being provided. There does not appear to be any "medical gas" system.
|
Additional plans submitted | | | 2/9/2001 | | DONE |
|
|
|
Received Plumbing plans from BRS Architects, two sets of sheets P-1, P-2, P-3 and P-4, forwarded same to Carl Westfall. 2/9/01 DAR
|
Override - Parcel Holds | | | 2/6/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/6/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/6/2001 | | DONE |
|
|
|
|
Telephone call | | | 2/6/2001 | | DONE |
|
|
|
TALKED TO BRIAN TO VERIFY PLANS ARE READY
|
Routing - PLUMBING | 2/1/2001 | | 2/5/2001 | | PASS |
|
|
|
misc. fixture relocation ok, additional cross connection prrotection may be required. no med gas system if installed resubmit
|
Routing - PLAN CHECK | 2/5/2001 | | 2/5/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2001 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 12/8/2000 | | 2/5/2001 | | PASS |
Carl Westfall
|
|
|
2/5/01 15:05:29 CJW - activity updated through activity BLDA022 from case BLD00-03582.
|
Routing - PLAN CHECK | 1/2/2001 | | 2/1/2001 | | PASS |
|
|
|
Passed 2nd UBC review. Drawings approved, with conditions, after resubmittal review.
|
Plan resubmittals received | | | 1/31/2001 | | DONE |
|
|
|
Received plan resubmittals from BRS two sets each , forwarded same to Carl Westfall. 1/31/01 DAR
|
Routing - PLUMBING | 12/29/2000 | | 1/2/2001 | | PASS |
|
|
|
note 11 page p2,future tenants water supply must be independant of this tenants water supply, additional cross connection protection may be required
|
Routing - FIRE | 12/26/2000 | | 12/29/2000 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 12/29/2000 | | |
|
|
|
Failed first UBC plan review.
|
Routing - PLAN CHECK | 12/12/2000 | | 12/26/2000 | | |
|
|
|
Failed first UBC plan review.
|
Plan Reviewer's activity | | | 12/21/2000 | | |
|
|
|
Failed first UBC plan review. UBC plan review started December 21, 2000 and finished December 26, 2000. A response from the architect was required. See the conditions list.
|
Early Start Permit | | | 12/15/2000 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 12/8/2000 | | 12/12/2000 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 12/11/2000 | | DONE |
|
|
|
PARTIAL PERMIT ISSUED AT THE REQUEST OF THE ARCHITECT. GAVE TO PERMIT DESK ON THIS DATE TO ISSUE.
|
Telephone call | | | 12/11/2000 | | DONE |
|
|
|
called early start ready
|
Pending Assignment by MYS | 12/7/2000 | | 12/8/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/8/2000 | | |
|
|
|
Requires Mech. Plans. Contacted Andrew Davis of this need. KMM
|
Received Certificate of Value | | | 12/7/2000 | | DONE |
|
|
|
|
Application received | | | 12/7/2000 | | |
|
|
|
|