(F) Reprint permit | | | 12/27/2002 | | |
|
|
|
|
(F) Reprint permit | | | 7/17/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/12/2002 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/9/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/11/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8861 issued 10-11-01 to McDonald's Restaurant.
|
Permanent Occupancy | | 10/9/2001 | 10/9/2001 | | DONE |
|
|
|
|
BLD-Final | 9/28/2001 | 9/28/2001 | 9/28/2001 | P | NR |
Russ Owen
|
|
|
Cathy has the card - if there are any questions call Chris @ ###-#### Appears to need s-i reports. 9/28/2001 3:58:47 PM
|
PubWorks Occupancy Approval | | | 9/6/2001 | | DONE |
|
|
|
Complete as of 9/6/01. No card to sign. G.Fitts
|
BLD-Aging Inspection | 9/3/2001 | 9/3/2001 | 9/3/2001 | | PART |
Tom Arcoraci
|
|
|
wip till 9-28 9/3/2001 9:20:23 PM
|
Fee Review-notes | 12/8/2000 | 12/8/2000 | 7/12/2001 | | DONE |
|
|
|
called GC for final cert & owner supplied
|
BLD-Framing/Rough-in | 7/2/2001 | 7/2/2001 | 7/2/2001 | P | PASS |
Tom Arcoraci
|
|
|
###-####- bob r/i ok to back fill basement on demo 7/2/2001 1:31:57 AM
|
Code Occupancy Approval | | | 6/29/2001 | | DONE |
|
|
|
Bonded for rest of parking, paving, stripping, removal of demo materials and finish of landscaping $$40,043.
|
FIRE-Final Inspection | 6/27/2001 | 6/28/2001 | 6/28/2001 | A | PASS |
Joe Tawney
|
|
|
###-#### Reinsp OK for permanant occupancy 6/28/2001 10:24:42 AM
|
BLD-Final | 6/27/2001 | 6/28/2001 | 6/28/2001 | A | PART |
Tom Arcoraci
|
|
|
###-#### late am ok for temp occ need lettters from spec inspector and eng of record 6/27/2001 11:01:08 PM
|
Temporary occupancy | | | 6/28/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4564 issued 6-28-01 to McDonald's.
|
FIRE-Final Inspection | 6/26/2001 | 6/26/2001 | 6/26/2001 | P | FAIL |
Rick Jackson
|
|
|
joe is on vacation carl ###-#### c/n issued 6/26/2001 4:08:20 PM
|
Code Occupancy Approval | | | 6/26/2001 | | FAIL |
|
|
|
Bonded for landscaping, demo of bldg. and parking ($40,043.00)
|
FIRE-Sprinkler Rough-in | 6/18/2001 | 6/19/2001 | 6/19/2001 | A | PASS |
Joe Tawney
|
|
|
Conf with Carl, contr reg Life/safety issues 6/19/2001 3:35:37 PM
|
BLD-Framing/Rough-in | 6/12/2001 | 6/13/2001 | 6/13/2001 | A | PASS |
Tom Arcoraci
|
|
|
ceiling grid carl- ###-####
|
BLD-Framing/Rough-in | 6/5/2001 | 6/6/2001 | 6/6/2001 | A | PART |
Tom Arcoraci
|
|
|
shafts and ceiling grid CArl ###-#### ok for ul-496 on shaft 6/6/2001 3:56:49 PM
|
BLD-Framing/Rough-in | 6/1/2001 | 6/4/2001 | 6/4/2001 | A | FAIL |
Tom Arcoraci
|
|
|
soffits outside of building ###-#### cn posted for draft stops 6/4/2001 1:32:54 PM
|
BLD-Framing/Rough-in | 6/4/2001 | 6/4/2001 | 6/4/2001 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 6/4/2001 11:18:19 AM wip draft stop ok 6/4/2001 3:33:46 PM
|
BLD-Framing/Rough-in | 5/23/2001 | 5/24/2001 | 5/24/2001 | A | NR |
Dave Hannah
|
|
|
shafts Carl ###-####
|
BLD-Framing/Rough-in | 5/11/2001 | 5/15/2001 | 5/15/2001 | P | PART |
Tom Arcoraci
|
|
|
r/i ###-####- carl -cover ok to cover kit 5/15/2001 4:15:32 PM
|
BLD-Conference | 5/3/2001 | 5/3/2001 | 5/3/2001 | P | PASS |
Tom Arcoraci
|
|
|
Added by Inspector: 408 On 5/3/2001 4:24:40 PM resubmittel conf
|
BLD-Framing/Rough-in | 4/18/2001 | 4/18/2001 | 4/18/2001 | P | PART |
Tom Arcoraci
|
|
|
steel\\###-#### wip strata on site 4/18/2001 1:55:58 PM
|
BLD-Footing | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | PART |
Tom Arcoraci
|
|
|
INTERIOR COLUMN PAD MIKE ###-#### WOULD LIKE TO POUR AT 2 THEY HAVE STRATA ON SITE spec on site 4/12/2001 3:23:36 PM
|
BLD-Foundation | 4/5/2001 | 4/6/2001 | 4/6/2001 | P | PART |
Tom Arcoraci
|
|
|
tony ###-#### stem wall ok pending stratas reports 4/6/2001 12:42:04 PM
|
BLD-Footing | 4/4/2001 | 4/5/2001 | 4/5/2001 | A | PART |
Russ Owen
|
|
|
Tony ###-#### ok subject to s-i 4/5/2001 12:14:42 PM
|
BLD-Footing | 4/3/2001 | 4/4/2001 | 4/4/2001 | P | CANC |
Tom Arcoraci
|
|
|
Mike ###-#### pouring at 2:00
|
(F) Reprint permit | | | 3/28/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/23/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/23/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/23/2001 | | DONE |
|
|
|
talked to david holm to verify plans are ready
|
Issue PAID IN FULL permit | | | 3/23/2001 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/13/2001 | | 3/22/2001 | | DONE |
|
|
|
Sent plans to consultanting engineer via PDQ. 3/13/01 DAR
|
Plan Reviewer's activity | | | 3/22/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/22/2001 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/22/2001 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/22/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 12/8/2000 | | 3/22/2001 | | PASS |
Mike Phillips
|
|
|
3/22/2001 15:14:30 M_P - activity updated through activity BLDA022 from case BLD00-03593.
|
Plan Reviewer's activity | | | 3/15/2001 | | PEND |
|
|
|
Waiting for out side engineering to complete review prior to issuing permit.
|
Plan resubmittals received | | | 3/12/2001 | | DONE |
|
|
|
Received three copies of revised structural drawings, structural calculations and revised structural calculations. In response to your January 23, 2001 preliminary plan review. Routed to Mike P. KMM
|
Routing - PLANNING | 2/16/2001 | | 2/22/2001 | | PASS |
|
|
|
Approved per CUP00-96 (Susan Riggs) and per DRH00-166 (Marty Santoyo).
|
Routing - PLAN CHECK | 1/26/2001 | | 2/16/2001 | | |
|
|
|
|
Plan resubmittals received | | | 2/14/2001 | | DONE |
|
|
|
Received two copies of Special Inspections Program. Routed to Mike P. KMM
|
Plan resubmittals received | | | 2/12/2001 | | DONE |
|
|
|
Received two sets of plan resubmittals from McDonalds Corporation, forwarded same to Mike Phillips. 2/12/01 DAR
|
Routing - FIRE | 1/23/2001 | | 1/26/2001 | | PASS |
|
|
|
Fax to architect was not successful
|
Plan Review Completed(1st rev) | | | 1/26/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/27/2000 | | 1/23/2001 | | |
|
|
|
Routing to fire.
|
Plan Reviewer's activity | | | 1/23/2001 | | FAIL |
|
|
|
Additional information required for further review.
|
Override - Parcel Holds | | | 1/23/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 1/22/2001 | | HOLD |
|
|
|
Need density reduction completed.
|
Routing Off Site - STRUCTURAL | 12/12/2000 | | 1/4/2001 | | FAIL |
|
|
|
12/12/00 Received stamped and signed calcs cover sheet. Put with plans and contacted pdq to take to outside eng. KMM
Additional information required by outside engineering firm.
|
Routing - PLUMBING | 12/22/2000 | | 12/27/2000 | | PASS |
|
|
|
use boise city approved grease interceptor detail, attached, provide a 3" vent downstream ok grease interceptor discharge diptube, roof drainage from building to connection to site drainage to be tested. inspection to be by the plumbing inspector.
|
Routing - PUBLIC WORKS | 12/11/2000 | | 12/20/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/12/2000 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 12/11/2000 | | DONE |
|
|
|
Will route to outside eng. after I received stamped struc.cover sheet. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 12/8/2000 | | PEND |
|
|
|
Requires stamped cover sheet for struct. calcs. Will route in house but will hold for outside eng. until I received stamped cover sheet. Contacted Loy Taylor of this need. KMM
|
Received Certificate of Value | | | 12/8/2000 | | DONE |
|
|
|
|
Application received | | | 12/8/2000 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Routing - PLAN CHECK | 2/22/2001 | | | | |
|
|
|
|