Fee Review-notes | 12/13/2000 | 12/13/2000 | 3/22/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 2/19/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9047 issued 2-19-02 to the Chevron Pipeline Co.
|
Permanent Occupancy | | 2/14/2002 | 2/14/2002 | | DONE |
|
|
|
|
BLD-Final | 2/12/2002 | 2/14/2002 | 2/14/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 2/12/2002 5:13:15 PM elec final ok per jack frank 2/13/2002 8:11:19 AM ok for perm occ 2/14/2002 9:34:43 AM
|
BLD-Framing/Rough-in | 2/14/2002 | 2/14/2002 | 2/14/2002 | A | PASS |
Tom Arcoraci
|
|
|
Added by Inspector: 408 On 2/14/2002 9:34:19 AM
|
FIRE-Final Inspection | 1/31/2002 | 2/1/2002 | 2/1/2002 | A | PASS |
Troy Cobbley
|
|
|
Fire life/safety finaled 2/1/2002 8:45:29 AM
|
FIRE-Final Inspection | 1/30/2002 | 1/31/2002 | 1/31/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide correct hardware on door and mount fire extinguisher at 48" above finish floor 1/30/2002 2:20:45 PM
|
BLD-Conference | 1/31/2002 | 1/31/2002 | 1/31/2002 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 1/31/2002 1:49:21 PM
|
(F) Reprint permit | | | 1/29/2002 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/29/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/29/2002 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/23/2002 | 1/23/2002 | 1/23/2002 | | PART |
Tom Arcoraci
|
|
|
talked with dan wip 1/30/2002 11:18:57 AM
|
BLD-Aging Inspection | 11/12/2001 | 11/12/2001 | 11/12/2001 | | NR |
Tom Arcoraci
|
|
|
chev pipe line 11/14/2001 8:14:20 AM
|
BLD-Aging Inspection | 9/10/2001 | 9/10/2001 | 9/10/2001 | | PART |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 7/9/2001 | 7/9/2001 | 7/9/2001 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Footing | 5/9/2001 | 5/9/2001 | 5/9/2001 | P | PASS |
Tom Arcoraci
|
|
|
Dan ###-####
|
Plan assigned to (MLO) | 12/13/2000 | | 1/18/2001 | | PASS |
Mike Otto
|
|
|
1/18/2001 11:06:56 MLO - activity updated through activity BLDA022 from case BLD00-03610.
|
Routing - PLAN CHECK | 1/17/2001 | | 1/18/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/18/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/18/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/18/2001 | | DONE |
|
|
|
called permit ready
|
Issue PAID IN FULL permit | | | 1/18/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/17/2001 | | DONE |
|
|
|
Received three copies of revised sheets 1, 1 of 10, 3 of 10, 6 of 10. One copy of response letter and three copies of information from lamtec corporation. Routed to Mike Otto. KMM
|
Plan Review Completed(1st rev) | | | 12/27/2000 | | FAIL |
|
|
|
failed BLDG review
|
Routing - FIRE | 12/21/2000 | | 12/27/2000 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 12/21/2000 | | FAIL |
|
|
|
UBC corrections
|
Routing - PLAN CHECK | 12/15/2000 | | 12/21/2000 | | FAIL |
|
|
|
corrections sent to applicant.
|
Routing - PLANNING | 12/14/2000 | | 12/15/2000 | | PASS |
|
|
|
Approve per CZC00-120.
|
Routing - PUBLIC WORKS | 12/13/2000 | | 12/14/2000 | | PASS |
|
|
|
|
Application received | | | 12/13/2000 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/13/2000 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|