Fee Review-notes | 12/13/2000 | 12/13/2000 | 3/23/2001 | | DONE |
|
|
|
additional value from subs
|
Permanent occupancy UNPAID FEE | | | 2/15/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8570 issued 2-15-01 to Capital One.
|
Permanent Occupancy | | 2/14/2001 | 2/14/2001 | | DONE |
|
|
|
|
BLD-Final | 2/14/2001 | 2/14/2001 | 2/14/2001 | P | PASS |
Russ Owen
|
|
|
Added by Inspector: 407 On 2/14/2001 3:17:14 PM
|
DOC - Permit Finaled | 2/14/2001 | 2/14/2001 | 2/14/2001 | P | PASS |
Russ Owen
|
|
|
Added by Inspector: 407 On 2/14/2001 3:17:28 PM
|
FIRE-Final Inspection | 2/12/2001 | 2/13/2001 | 2/13/2001 | A | PASS |
Joe Tawney
|
|
|
Final OK for permanant occupancy 2/13/2001 6:49:30 PM
|
BLD-Framing/Rough-in | 1/26/2001 | 1/26/2001 | 1/26/2001 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/26/2001 at 10:01:32. Contact: ###-####. 1/26/2001 5:07:09 PM
|
Issue PAID IN FULL permit | | | 1/26/2001 | | DONE |
|
|
|
|
Routing - FIRE | 1/22/2001 | 1/25/2001 | 1/25/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 1/25/2001 | | 1/25/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 1/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/25/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/25/2001 | | DONE |
|
|
|
talked to marv meyer to verify plans are ready
|
Plan assigned to (JCB) | 1/2/2001 | | 1/25/2001 | | PASS |
Jason Blais
|
|
|
1/25/2001 13:14:03 JCB - activity updated through activity BLDA022 from case BLD00-03622.
|
Routing - PLAN CHECK | 1/18/2001 | | 1/22/2001 | | PEND |
|
|
|
Permit approval is dependent on Fire Dept. approval of plans. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 1/18/2001 | | DONE |
|
|
|
Received plan resubmittals from MPE Architects, David Marsee, forwarded same to Jason Blais. 1/18/01 DAR
|
Routing - FIRE | 1/11/2001 | 1/17/2001 | 1/17/2001 | | FAIL |
Bill Alexander
|
|
|
Lack correlating UFC UBC issues.
|
Plan Review Completed(1st rev) | | | 1/17/2001 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 1/11/2001 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLAN CHECK | 1/2/2001 | | 1/11/2001 | | FAIL |
|
|
|
Plan review report faxed to architect and contractor. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Pending Assignment by MYS | 1/2/2001 | | 1/2/2001 | | DONE |
Marlene Southard
|
|
|
Could not assign until resubmittals came in which could be processed.
|
Plan resubmittals received | | | 12/29/2000 | | DONE |
|
|
|
Received Sheets A1.0, A1.1, A1.2 and A1.3
|
Plan resubmittals received | | | 12/26/2000 | | DONE |
|
|
|
Received resubmittals. Still have problems with location of exit doors, swing of doors, no exit signage, etc. Sent FAX along with copy of plan with notes of what items need to be addressed to David Marsee (MPI Architect).
|
Telephone call | | | 12/19/2000 | | DONE |
|
|
|
Talked to David Marsee at MPI Architects in Dallas, Texas. We discussed code options and he faxed me a proposal. I approved proposal and sent it back with FAX telling him what he needed to resubmit. I informed him that once the resubmittal was sent in that I would assign the job to a plan reviewer. Plans on HOLD until resubmittals are sent in.
|
Telephone call | | | 12/15/2000 | | DONE |
|
|
|
Called Marv Meyer at Russell Corp. Told him that the plans could NOT be processed as yet because the conference rooms were located in the middle of the open office area and did not have the second exit to exterior or rated corridor. He said he would pass this one to the architect.
|
Plans ACCEPTED BY PLAN TECH | | | 12/14/2000 | | DONE |
|
|
|
|
Application received | | | 12/13/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/13/2000 | | DONE |
|
|
|
|