Permit Information
Permit NumberBLD00-03631
StatusFinaled
Name MCARTER-MOORHOUSE CO INC
Site Address 10754 W EXECUTIVE DR
Project NameIND RES CNTR-BLDG #4
Customer Number 
ePlanReviewNo
Description
To remodel the tenant in the north end of the building consisting of a 10,000 sq.ft. first floor and 5,000 sq.ft. second floor per approved plans on file. Occupancies to be retail showroom/fabrication wood working shop/office and storage. Work to include, construction of a one-hour occupancy separation between the F1 wood working shop and the offices and retail areas, removal of gaudrail on the second floor and construct one-hour occupancy separation wall, installation of an approved dust removal system, construction of a circular stairway between First and Second floor office spaces, installation of new glazing storefront glazing and door, construction of interior partitions to create additional office spaces on the second floor, Miscelaneous related interior finishes. NOTE: This building is fully fire sprinklered for area increase. Any alterations or modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department. This building was constructed in Ada County and annexed into Boise City. Original plans for this building (Industrial Resource Center Bldg. #4) and adjacent building (Industrical Resource Center Bldg. #3) are scanned with this plan. (P.C. #1043-00) *RMH*
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes12/14/200012/14/20001/28/2004 DONE
BLD-Aging Inspection8/15/20038/15/20038/15/2003 CANC
DetailsRuss Owen
BLD-Aging Inspection1/14/20021/14/20021/14/2002 PART
DetailsRuss Owen
no insp called for . 1/14/2002 10:19:21 AM
BLD-Conference11/13/200111/13/200111/13/2001 DONE
permit extension
BLD-Aging Inspection10/16/200110/16/200110/16/2001 PART
DetailsRuss Owen
2nd phase not started yet. 10/16/2001 10:59:34 AM
BLD-Aging Inspection8/16/20018/16/20018/16/2001 PART
DetailsRuss Owen
2nd faze not yet started. 8/22/2001 1:10:16 PM
BLD-Final6/5/20016/5/20016/5/2001PPART
DetailsRuss Owen
John Taylor ###-#### need to install the new stair case and upper floor offfice area work has not been completed, need penetrations on firewall, caulked and removed 6 in exhaust duct out of firewall. 1/5/2002 4:31:04 PM
FIRE-Final Inspection5/23/20015/30/20015/30/2001APASS
DetailsJoe Tawney
Reinsp Pass on phase II of permit 5/30/2001 8:49:00 AM
BLD-Final5/18/20015/18/20015/18/2001PFAIL
DetailsJoe Tawney
Added by Inspector: 406 On 5/18/2001 2:12:10 PM Reinsp Fail Fire door and batteries in FACP, Knox Box, breaker lock for FACP
BLD-Framing/Rough-in4/23/20014/23/20014/23/2001PPART
DetailsRuss Owen
tom ###-#### ok to sheetrock lower floor walls only ,upper floor not done.also ceiling not done. 11/23/2001 3:49:21 PM
FIRE-Final Inspection2/28/20013/1/20013/1/2001AFAIL
DetailsJoe Tawney
Final Fail C/N issued. 3/2/2001 8:16:30 AM
BLD-Framing/Rough-in2/27/20012/28/20012/28/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/27/2001 at 10:03:00. Contact: .went over req for final. 2/28/2001 1:36:14 PM
BLD-Framing/Rough-in2/20/20012/21/20012/21/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/20/2001 at 12:45:20. Contact: .1st layer drywall at lid over office. 2/21/2001 1:52:18 PM
BLD-Framing/Rough-in2/14/20012/15/20012/15/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/14/2001 at 16:40:44. Contact: .Ok to cover new tall wall ,now constructed ok, architect has revised line of separation wall, ok as revised only i have requested a detail for the 1 hr horizontal portion of the wall over the office area. 2/15/2001 12:48:58 PM
BLD-Framing/Rough-in2/8/20012/9/20012/9/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/08/2001 at 11:43:47. Contact: ###-####.Need to have architect reveiw the existing construction and submit any neccessary revisions as the firewall at north of existing rest room is not being cont as plans. south of this is ok. also architect needs to provide a detail for support of the new tall firewall in the shop. went over these items with building tenant/contractor. 2/9/2001 10:56:48 AM
Plan assigned to (R_H)12/18/2000 2/5/2001 PASS
Details
2/5/2001 10:14:51 RMH - activity updated through activity BLDA022 from case BLD00-03631.
Routing - PLAN CHECK1/17/2001 2/5/2001 PASS
DetailsRon Hill
Case Summary (BLD)  2/5/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  2/5/2001 PASS
DetailsRon Hill
Telephone call  2/5/2001 DONE
talked to Tom gave dollar amount
Inspection Record Card- Bld  2/5/2001 DONE
Print Occupancy Form  2/5/2001 DONE
Issue PAID IN FULL permit  2/5/2001 DONE
Plan resubmittals received  2/1/2001 DONE
Received two copies of revised sheets A-3.0, and new detail sheet A-4.0 revision dated 1/30/01. One copy of cover letter to Ron from JGT Architecture. Routed to Ron Hill. KMM
Routing - FIRE1/23/2001 1/26/2001 PASS
APPROVED AS NOTED
Plan resubmittals received  1/23/2001 DONE
Received plan resubmittals from JGT Architects, two sets of sheet A-2.0 and A-3.0 plus two sets of small documents, forwarded same to Ron Hill. 1/23/01 DAR
Plan Review Completed(1st rev)  1/16/2001 FAIL
Routing - FIRE1/10/2001 1/16/2001 FAIL
inadequate info. Comments faxed to architect.
Plan Reviewer's activity  1/10/2001 FAIL
DetailsRon Hill
Routing - PLAN CHECK12/20/2000 1/10/2001 FAIL
DetailsRon Hill
Faxed and Mailed requirements to Gregg Toolson, at JGT architecture. On 01-10-00, Routed to fire same day.
Routing - PUBLIC WORKS12/18/2000 12/20/2000 PASS
Plans ACCEPTED BY PLAN TECH  12/14/2000 DONE
Received Certificate of Value  12/14/2000 DONE
Application received  12/14/2000  
Recd Pcfee & Taken To Pln CK  12/14/2000 DONE
Routing - PLAN CHECK1/26/2001