Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-03659
StatusFinaled
Name ALBERTSONS (ICE CREAM PLANT)
Site Address 2700 W REGAN AVE
Project NameALBERTSON ICE CREAM PLANT
Customer Number 
ePlanReviewNo
Description
(ALBERTSON'S ICE CREAM PLANT) This building is not fire sprinklered. To construct improvements to an existing 12,363 square foot ice cream plant. New roof top mechanical units are being installed at 3 different locations on the roof. A refrigeration machinery room is being created. Work is to include structural supports for the roof top mechanical units, 1-hr separation for the refrigeration machinery room, interior metal covered insulated wall panels, and an exterior 10,000 gallon water tank all per approved drawings, engineering, and plan review conditions on file. See permit BLD01-00517 for the demolition permit. CUP00-00139 PC-1053-00 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  10/25/2004  
Fee Review-notes12/18/200012/18/200011/9/2001 DONE
BLD-Final7/30/20017/31/20017/31/2001APASS
DetailsDave Hannah
bob ###-#### all c/n items have been completed 7/31/2001 12:34:39 PM
Letter of compliance  7/31/2001 DONE
Letter of Compliance #21616 issued 7-13-01.
BLD-Conference7/3/20017/3/20017/3/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 7/3/2001 8:41:29 AM complete c/n items...will consult GS re landings, etc.
BLD-Conference6/21/20016/21/20016/21/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 6/21/2001 5:58:02 PM w/ contractor re c/n.
BLD-Final6/19/20016/20/20016/20/2001AFAIL
DetailsCarl Dependahl
bob ###-####; keep c/n 6/20/2001 10:22:09 AM
Code Occupancy Approval  6/14/2001 PASS
Inspected and passed today, 3:30pm
BLD-Conference6/13/20016/13/20016/13/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 6/13/2001 8:55:48 AM w/ Bob C...NEED p&z for final, not pub wks. keep c/n. 6/13/2001 8:56:00 AM
BLD-Conference6/4/20016/4/20016/4/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 6/4/2001 12:17:19 PM keep c/n; w/ refrig system installer re labelling & diagrams, etc
FIRE-Final Inspection5/31/20016/1/20016/1/2001APASS
DetailsRick Jackson
###-####
BLD-Final5/31/20016/1/20016/1/2001AFAIL
DetailsCarl Dependahl
c/n re mech issues, landings, door hdwe per Rick, etc. 6/4/2001 12:16:16 PM
BLD-Conference5/29/20015/30/20015/30/2001APART
DetailsCarl Dependahl
Bob Cafferty, ###-#### - wants to meet with you and Rick Jackson
FIRE-Conference5/29/20015/30/20015/30/2001APART
DetailsRick Jackson
Bob Cafferty, ###-#### - wants to meet with you and Carl reviewed amonia alarm system and requirements 5/30/2001 11:25:14 AM
BLD-Framing/Rough-in5/14/20015/14/20015/14/2001PPART
DetailsCarl Dependahl
Bob ###-####,penthouse ok to cover. rec'd complete resub. 5/14/2001 4:55:57 PM
BLD-Framing/Rough-in5/4/20015/7/20015/7/2001ACANC
DetailsTony Young
Bob ###-####
wants carl to do 5/7/2001 11:08:09 AM
BLD-Conference5/3/20015/3/20015/3/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 5/3/2001 9:21:44 AM w/ bldr, Bob Cafferty...awaiting appropriate resubmittal.
BLD-Framing/Rough-in4/25/20014/26/20014/26/2001ACANC
DetailsSteven Webb
Transfer to 340 4/26/2001 8:50:08 AM
BLD-Conference4/26/20014/26/20014/26/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 4/26/2001 9:35:08 AM w/ steve w...sent in error, I'll go...
BLD-Framing/Rough-in4/26/20014/26/20014/26/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 4/26/2001 11:50:08 AM ok to cover roof top pressure vessel enclosure...chk. firestops after completion,no elec in walls. Resubmittal on way
BLD-Conference4/24/20014/24/20014/24/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/24/2001 12:34:46 PM w arch re roof mount reqs for ammonia vessels...1hr enclosure, vented per umc
BLD-Conference4/17/20014/17/20014/17/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 4/17/2001 10:26:01 AM w/337, review resub. & ch. 11 UMC re refrig. piping / vessels( accumulator ) intended to be relocatd to roof...also w/ arch, Bob Howard...need add'l details for 1hr enclosure at roof & struct eng'rs review of add'l support structure, new or existing (exist masonry walls shown carrying new framing/floor/steel/ammonia vessels. Keep c/n.
BLD-Conference4/16/20014/16/20014/16/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/16/2001 10:21:25 AM w/ bldr re arch's resubmittal & c/n of 4-5-01
BLD-Conference4/13/20014/13/20014/13/2001PPASS
DetailsCarl Dependahl
Bob, ###-#### w/ Bob Cafferty, rec'd resub to place acumulator in separate 1hr enclosure on roof, will consult Dave L 4/13/2001 2:31:27 PM 4/13/2001 2:32:48 PM
BLD-Conference4/11/20014/11/20014/11/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/11/2001 10:58:00 AM w/ Albertsons & refrig. eng'rs, contractor, & subs...went over c/n of 4-5 re machinery room, special insp req'd, & exits. Will resubmit for change to mach. rm.
BLD-Conference4/9/20014/11/20014/11/2001APASS
DetailsTony Young
bob ###-####
carl took this 4/11/2001 10:50:34 AM
FIRE-Conference4/9/20014/11/20014/11/2001APART
DetailsRick Jackson
###-#### bob will move units to roof 4/11/2001 11:12:37 AM
BLD-Conference4/10/20014/10/20014/10/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/10/2001 11:05:40 AM w/Bob & Steve Bastian...want to meet onsite w/ refrigerator eng'r re c/n of 4-5. will contact Dave L.
BLD-Conference4/10/20014/10/20014/10/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/10/2001 12:14:08 PM keep c/n, need meet w/ reefer eng'r & Dave L
BLD-Conference4/6/20014/6/20014/6/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/6/2001 5:17:49 PM w/ Bob Cafferty re Albertsons plant; eng'r to submit proposal to remove accumulator and mount on roof and justify same per UMC, UFC.
BLD-Conference4/5/20014/5/20014/5/2001AFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 4/5/2001 11:07:49 AM c/n issued re UMC ch 11: refrigerant pressure vessels and piping to be w/i machinery room, not allowed in exit. Testing statement req'd per UMC 1122. Need spec insp/eng's ok for fabbed/welded structural assy's, etc. per UBC ch.17
BLD-Framing/Rough-in4/5/20014/5/20014/5/2001PFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 4/5/2001 5:22:06 PM c/n re UMC items, add studs & fasteners at shaft assys, need spec insp for struct steel welds
BLD-Footing4/2/20014/3/20014/3/2001APART
DetailsCarl Dependahl
###-####; reviewed eng's resub for ftg's at existing cols, ok to pour...need spec. insp for welded/fabricated members added for structure.Arch. to address accumulator & intercooler overhead outside machinery rm. 4/3/2001 11:43:35 AM
BLD-Footing3/30/20014/2/20014/2/2001AFAIL
DetailsCarl Dependahl
FT INSP BURT-- ###-####; need as-built for col ftg enlargements...mti to ok epoxy dowels; add studs/fasteners at shafts 4/2/2001 12:39:31 PM
BLD-Footing3/26/20013/26/20013/26/2001PPART
DetailsTom Arcoraci
Bob ###-#### ext tank footing ok 3/26/2001 2:52:11 PM
Issue PAID IN FULL permit  3/9/2001 DONE
Routing - PLAN CHECK3/7/2001 3/8/2001 PASS
TOOK TO CARL W
PLANS/APPL TAKEN TO FRONT DESK  3/8/2001 PASS
Inspection Record Card- Bld  3/8/2001 DONE
Print Occupancy Form  3/8/2001 DONE
Telephone call  3/8/2001 DONE
faxed over sheet for permit ready to be picked up - No phone number given just a fax.
Plan assigned to (CJW)12/19/2000 3/8/2001 PASS
DetailsCarl Westfall
3/8/01 09:29:16 CJW - activity updated through activity BLDA022 from case BLD00-03659.
Routing - FIRE2/27/2001 3/7/2001 PASS
Plan resubmittals received  2/28/2001 DONE
Received one copy of response letter to comments from Boise City dated 2/27/01. One copy of 81/2 x11 drawing from the Structural Engineer for the detail of the revisions required of the existing footings as noted in response to item #16-3. KMM
Routing - PLAN CHECK1/18/2001 2/27/2001  
Failed 2nd UBC plan review. See conditions list.
Plan resubmittals received  2/20/2001 DONE
Received plan resubmitttals from Hosford, Larson, Rudeen two sets and small documents. Forwarded same to Carl Westfall. 2/19/01 DAR
Routing - FIRE1/11/2001 1/17/2001  
Failed first UFC plan review. Need more info on UFC 63 compliance.
Plan Review Completed(1st rev)  1/17/2001  
Failed first UBC plan review.
Routing - PLUMBING1/16/2001 1/16/2001 PASS
Routing - PLAN CHECK12/27/2000 1/11/2001  
Failed first UBC plan review.
Plan Reviewer's activity  1/10/2001  
Failed first UBC plan review. UBC plan review started January 10, 2001 and finished the next day. A response from the architect was required. See the conditions list.
Routing - PLUMBING12/22/2000 12/27/2000  
Failed first review.
Routing - PLANNING12/22/2000 12/22/2000 DONE
Sev Jones
Routing - PUBLIC WORKS12/19/2000 12/22/2000 PASS
Plans ACCEPTED BY PLAN TECH  12/19/2000 DONE
Pending Assignment by MYS12/19/2000 12/19/2000 DONE
DetailsMarlene Southard
Application received  12/18/2000  
Recd Pcfee & Taken To Pln CK  12/18/2000 DONE