Case Summary (BLD) | | | 10/25/2004 | | |
|
|
|
|
Fee Review-notes | 12/18/2000 | 12/18/2000 | 11/9/2001 | | DONE |
|
|
|
|
BLD-Final | 7/30/2001 | 7/31/2001 | 7/31/2001 | A | PASS |
Dave Hannah
|
|
|
bob ###-#### all c/n items have been completed 7/31/2001 12:34:39 PM
|
Letter of compliance | | | 7/31/2001 | | DONE |
|
|
|
Letter of Compliance #21616 issued 7-13-01.
|
BLD-Conference | 7/3/2001 | 7/3/2001 | 7/3/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/3/2001 8:41:29 AM complete c/n items...will consult GS re landings, etc.
|
BLD-Conference | 6/21/2001 | 6/21/2001 | 6/21/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/21/2001 5:58:02 PM w/ contractor re c/n.
|
BLD-Final | 6/19/2001 | 6/20/2001 | 6/20/2001 | A | FAIL |
Carl Dependahl
|
|
|
bob ###-####; keep c/n 6/20/2001 10:22:09 AM
|
Code Occupancy Approval | | | 6/14/2001 | | PASS |
|
|
|
Inspected and passed today, 3:30pm
|
BLD-Conference | 6/13/2001 | 6/13/2001 | 6/13/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/13/2001 8:55:48 AM w/ Bob C...NEED p&z for final, not pub wks. keep c/n. 6/13/2001 8:56:00 AM
|
BLD-Conference | 6/4/2001 | 6/4/2001 | 6/4/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/4/2001 12:17:19 PM keep c/n; w/ refrig system installer re labelling & diagrams, etc
|
FIRE-Final Inspection | 5/31/2001 | 6/1/2001 | 6/1/2001 | A | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Final | 5/31/2001 | 6/1/2001 | 6/1/2001 | A | FAIL |
Carl Dependahl
|
|
|
c/n re mech issues, landings, door hdwe per Rick, etc. 6/4/2001 12:16:16 PM
|
BLD-Conference | 5/29/2001 | 5/30/2001 | 5/30/2001 | A | PART |
Carl Dependahl
|
|
|
Bob Cafferty, ###-#### - wants to meet with you and Rick Jackson
|
FIRE-Conference | 5/29/2001 | 5/30/2001 | 5/30/2001 | A | PART |
Rick Jackson
|
|
|
Bob Cafferty, ###-#### - wants to meet with you and Carl reviewed amonia alarm system and requirements 5/30/2001 11:25:14 AM
|
BLD-Framing/Rough-in | 5/14/2001 | 5/14/2001 | 5/14/2001 | P | PART |
Carl Dependahl
|
|
|
Bob ###-####,penthouse ok to cover. rec'd complete resub. 5/14/2001 4:55:57 PM
|
BLD-Framing/Rough-in | 5/4/2001 | 5/7/2001 | 5/7/2001 | A | CANC |
Tony Young
|
|
|
Bob ###-####
wants carl to do 5/7/2001 11:08:09 AM
|
BLD-Conference | 5/3/2001 | 5/3/2001 | 5/3/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/3/2001 9:21:44 AM w/ bldr, Bob Cafferty...awaiting appropriate resubmittal.
|
BLD-Framing/Rough-in | 4/25/2001 | 4/26/2001 | 4/26/2001 | A | CANC |
Steven Webb
|
|
|
Transfer to 340 4/26/2001 8:50:08 AM
|
BLD-Conference | 4/26/2001 | 4/26/2001 | 4/26/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/26/2001 9:35:08 AM w/ steve w...sent in error, I'll go...
|
BLD-Framing/Rough-in | 4/26/2001 | 4/26/2001 | 4/26/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/26/2001 11:50:08 AM ok to cover roof top pressure vessel enclosure...chk. firestops after completion,no elec in walls. Resubmittal on way
|
BLD-Conference | 4/24/2001 | 4/24/2001 | 4/24/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/24/2001 12:34:46 PM w arch re roof mount reqs for ammonia vessels...1hr enclosure, vented per umc
|
BLD-Conference | 4/17/2001 | 4/17/2001 | 4/17/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/17/2001 10:26:01 AM w/337, review resub. & ch. 11 UMC re refrig. piping / vessels( accumulator ) intended to be relocatd to roof...also w/ arch, Bob Howard...need add'l details for 1hr enclosure at roof & struct eng'rs review of add'l support structure, new or existing (exist masonry walls shown carrying new framing/floor/steel/ammonia vessels. Keep c/n.
|
BLD-Conference | 4/16/2001 | 4/16/2001 | 4/16/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/16/2001 10:21:25 AM w/ bldr re arch's resubmittal & c/n of 4-5-01
|
BLD-Conference | 4/13/2001 | 4/13/2001 | 4/13/2001 | P | PASS |
Carl Dependahl
|
|
|
Bob, ###-#### w/ Bob Cafferty, rec'd resub to place acumulator in separate 1hr enclosure on roof, will consult Dave L 4/13/2001 2:31:27 PM 4/13/2001 2:32:48 PM
|
BLD-Conference | 4/11/2001 | 4/11/2001 | 4/11/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/11/2001 10:58:00 AM w/ Albertsons & refrig. eng'rs, contractor, & subs...went over c/n of 4-5 re machinery room, special insp req'd, & exits. Will resubmit for change to mach. rm.
|
BLD-Conference | 4/9/2001 | 4/11/2001 | 4/11/2001 | A | PASS |
Tony Young
|
|
|
bob ###-####
carl took this 4/11/2001 10:50:34 AM
|
FIRE-Conference | 4/9/2001 | 4/11/2001 | 4/11/2001 | A | PART |
Rick Jackson
|
|
|
###-#### bob will move units to roof 4/11/2001 11:12:37 AM
|
BLD-Conference | 4/10/2001 | 4/10/2001 | 4/10/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/10/2001 11:05:40 AM w/Bob & Steve Bastian...want to meet onsite w/ refrigerator eng'r re c/n of 4-5. will contact Dave L.
|
BLD-Conference | 4/10/2001 | 4/10/2001 | 4/10/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/10/2001 12:14:08 PM keep c/n, need meet w/ reefer eng'r & Dave L
|
BLD-Conference | 4/6/2001 | 4/6/2001 | 4/6/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/6/2001 5:17:49 PM w/ Bob Cafferty re Albertsons plant; eng'r to submit proposal to remove accumulator and mount on roof and justify same per UMC, UFC.
|
BLD-Conference | 4/5/2001 | 4/5/2001 | 4/5/2001 | A | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/5/2001 11:07:49 AM c/n issued re UMC ch 11: refrigerant pressure vessels and piping to be w/i machinery room, not allowed in exit. Testing statement req'd per UMC 1122. Need spec insp/eng's ok for fabbed/welded structural assy's, etc. per UBC ch.17
|
BLD-Framing/Rough-in | 4/5/2001 | 4/5/2001 | 4/5/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/5/2001 5:22:06 PM c/n re UMC items, add studs & fasteners at shaft assys, need spec insp for struct steel welds
|
BLD-Footing | 4/2/2001 | 4/3/2001 | 4/3/2001 | A | PART |
Carl Dependahl
|
|
|
###-####; reviewed eng's resub for ftg's at existing cols, ok to pour...need spec. insp for welded/fabricated members added for structure.Arch. to address accumulator & intercooler overhead outside machinery rm. 4/3/2001 11:43:35 AM
|
BLD-Footing | 3/30/2001 | 4/2/2001 | 4/2/2001 | A | FAIL |
Carl Dependahl
|
|
|
FT INSP BURT-- ###-####; need as-built for col ftg enlargements...mti to ok epoxy dowels; add studs/fasteners at shafts 4/2/2001 12:39:31 PM
|
BLD-Footing | 3/26/2001 | 3/26/2001 | 3/26/2001 | P | PART |
Tom Arcoraci
|
|
|
Bob ###-#### ext tank footing ok 3/26/2001 2:52:11 PM
|
Issue PAID IN FULL permit | | | 3/9/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/7/2001 | | 3/8/2001 | | PASS |
|
|
|
TOOK TO CARL W
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 3/8/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/8/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/8/2001 | | DONE |
|
|
|
faxed over sheet for permit ready to be picked up - No phone number given just a fax.
|
Plan assigned to (CJW) | 12/19/2000 | | 3/8/2001 | | PASS |
Carl Westfall
|
|
|
3/8/01 09:29:16 CJW - activity updated through activity BLDA022 from case BLD00-03659.
|
Routing - FIRE | 2/27/2001 | | 3/7/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/28/2001 | | DONE |
|
|
|
Received one copy of response letter to comments from Boise City dated 2/27/01. One copy of 81/2 x11 drawing from the Structural Engineer for the detail of the revisions required of the existing footings as noted in response to item #16-3. KMM
|
Routing - PLAN CHECK | 1/18/2001 | | 2/27/2001 | | |
|
|
|
Failed 2nd UBC plan review. See conditions list.
|
Plan resubmittals received | | | 2/20/2001 | | DONE |
|
|
|
Received plan resubmitttals from Hosford, Larson, Rudeen two sets and small documents. Forwarded same to Carl Westfall. 2/19/01 DAR
|
Routing - FIRE | 1/11/2001 | | 1/17/2001 | | |
|
|
|
Failed first UFC plan review. Need more info on UFC 63 compliance.
|
Plan Review Completed(1st rev) | | | 1/17/2001 | | |
|
|
|
Failed first UBC plan review.
|
Routing - PLUMBING | 1/16/2001 | | 1/16/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/27/2000 | | 1/11/2001 | | |
|
|
|
Failed first UBC plan review.
|
Plan Reviewer's activity | | | 1/10/2001 | | |
|
|
|
Failed first UBC plan review. UBC plan review started January 10, 2001 and finished the next day. A response from the architect was required. See the conditions list.
|
Routing - PLUMBING | 12/22/2000 | | 12/27/2000 | | |
|
|
|
Failed first review.
|
Routing - PLANNING | 12/22/2000 | | 12/22/2000 | | DONE |
|
|
|
Sev Jones
|
Routing - PUBLIC WORKS | 12/19/2000 | | 12/22/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/19/2000 | | DONE |
|
|
|
|
Pending Assignment by MYS | 12/19/2000 | | 12/19/2000 | | DONE |
Marlene Southard
|
|
|
|
Application received | | | 12/18/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/18/2000 | | DONE |
|
|
|
|