(F) Reprint permit | | | 5/23/2001 | | DONE |
|
|
|
|
Fee Review-notes | | | 3/23/2001 | | DONE |
|
|
|
need final cert
|
Permanent Occupancy | | 2/16/2001 | 2/16/2001 | | DONE |
|
|
|
|
BLD-Final | 2/15/2001 | 2/16/2001 | 2/16/2001 | P | PASS |
Jim Storey
|
|
|
###-####
|
Permanent occupancy UNPAID FEE | | | 2/16/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8573 issued 2-16-01 to Washington Mutual Bank.
|
FIRE-Final Inspection | 2/15/2001 | 2/15/2001 | 2/15/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 2/15/2001 4:07:17 PM
|
BLD-Framing/Rough-in | 2/8/2001 | 2/9/2001 | 2/9/2001 | A | PART |
Jim Storey
|
|
|
###-#### CEILING GRID ceilling ok pending mech and ele approval. 2/9/2001 9:41:53 AM
|
BLD-Framing/Rough-in | 1/30/2001 | 1/31/2001 | 1/31/2001 | P | PASS |
Steven Webb
|
|
|
###-####. 1/31/2001 3:30:39 PM
|
BLD-Framing/Rough-in | 1/29/2001 | 1/30/2001 | 1/30/2001 | A | NR |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/29/2001 at 12:05:59. Contact: .Needs electrical and plumbing inspections. 1/30/2001 11:16:10 AM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2001 | | PASS |
|
|
|
|
Print Occupancy Form | | | 1/26/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/26/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/26/2001 | | DONE |
|
|
|
he will be in only a blk away
|
Issue PAID IN FULL permit | | | 1/26/2001 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 12/28/2000 | | 1/26/2001 | | PASS |
Jason Blais
|
|
|
1/26/2001 13:05:08 JCB - activity updated through activity BLDA022 from case BLD00-03716.
|
Routing - PLAN CHECK | 1/22/2001 | | 1/26/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan resubmittals received | | | 1/25/2001 | | DONE |
|
|
|
Received one set of resubmittals from Kelly Witt, Kendrick Brothers, forwarded same to Jason Blaise. 1/25/01 DAR
Received second set of plan resubmittals and some structural caculations from Kelly Witt. 1/26/01 DAR
|
Routing - FIRE | 1/19/2001 | | 1/22/2001 | | PASS |
|
|
|
Approved as noted. Faxed to architect
|
Plan Review Completed(1st rev) | | | 1/22/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/29/2000 | | 1/19/2001 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plans resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Plan resubmittals requested | | | 1/19/2001 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Early Start Permit | | | 1/9/2001 | | DONE |
|
|
|
|
Telephone call | | | 12/29/2000 | | DONE |
|
|
|
left message for tom kendrick that partial permit is ready 1-###-####
|
Routing - PUBLIC WORKS | 12/28/2000 | | 12/29/2000 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 12/28/2000 | | DONE |
|
|
|
PARTIAL PERMIT ISSUED AT THE REQUEST OF TOM KENDRICK - CONTRACTOR.
|
Pending Assignment by MYS | 12/28/2000 | | 12/28/2000 | | DONE |
Marlene Southard
|
|
|
|
Received partial PAYMENT | | | 12/27/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/27/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 12/27/2000 | | DONE |
|
|
|
|
Application received | | | 12/27/2000 | | |
|
|
|
|