Test Expiration Notice | | | 8/29/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
Test Expiration Notice | | | 8/10/2001 | | DONE |
|
|
|
|
BLD-Final | 4/20/2001 | 4/20/2001 | 4/20/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 04/20/2001 at 07:04:04. Contact: ###-####. C. of C. #20414 issued. 4/20/2001 8:49:27 AM
|
DOC - Permit Finaled | 4/20/2001 | 4/20/2001 | 4/20/2001 | A | PASS |
Steven Webb
|
|
|
Added by Inspector: 420 On 4/20/2001 8:49:46 AM
|
BLD-Energy code compliance | 3/7/2001 | 3/7/2001 | 3/7/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/07/2001 at 11:17:20. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/6/2001 | 3/6/2001 | 3/6/2001 | P | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/06/2001 at 10:26:09. Contact: ###-####.c/n issued--solid bearing under 4X10 header and straps, plus eng. requested on 3/2/01 c/n stills needed on T9 truss. Ok to insulate. 3/6/2001 3:22:36 PM
|
BLD-Framing/Rough-in | 3/2/2001 | 3/2/2001 | 3/2/2001 | P | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/02/2001 at 07:24:42. Contact: ###-####. C/n issued--Grider per plans is 2 M. Lam--installed in I-joist-provide eng. or replace, Per plans at start of hallway should be 4 X 10 header, not installed, fireblock landing of stairs, G.Lam in garage need solid connections on both sides, Truss T9 per plans should be M.Lam provide eng. on truss, Truss package needed on site to complete framing inspection. 3/2/2001 2:37:07 PM
|
BLD-Other | 3/1/2001 | 3/1/2001 | 3/1/2001 | A | PASS |
Steven Webb
|
|
|
Scheduled by Inspector: 420 On 3/1/2001 10:21:24 AM SHEAR--Ok 3/1/2001 10:37:53 AM
|
BLD-Framing/Rough-in | 2/20/2001 | 2/21/2001 | 2/21/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 02/20/2001 at 16:56:33. Contact: ###-####.Shear inspection--ok to side LOWER floor only--need to verify MSTC 40 straps before siding upper section. 2/21/2001 11:41:13 AM
|
BLD-Framing/Rough-in | 2/20/2001 | 2/20/2001 | 2/20/2001 | P | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 02/20/2001 at 07:47:19. Contact: ###-####. no approved plans on site 2/20/2001 3:01:14 PM
|
BLD-Foundation | 1/23/2001 | 1/24/2001 | 1/24/2001 | A | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/23/2001 at 11:09:47. Contact: ###-####.hd not install at time of inspection 1/24/2001 11:32:27 AM
|
BLD-Footing | 1/23/2001 | 1/23/2001 | 1/23/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/23/2001 at 11:09:06. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 1/16/2001 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 1/11/2001 | 1/11/2001 | 1/12/2001 | | PASS |
Dan Overy
|
|
|
1/12/2001 08:04:45 DJO - activity updated through activity BLDA022 from case BLD01-00002.
|
Plan Reviewer's activity | | | 1/12/2001 | | DONE |
|
|
|
discussed problem areas with scott and marked plans to reflect corrections. this information will be incorporated into future plans that are being submitted at boise city.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/12/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/12/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plans ACCEPTED BY PLAN CHECK | | | 1/11/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 1/11/2001 | | PEND |
|
|
|
have called prestige homes. clarification of plans required before issuance.
|
Print Pending Permit.LaserJet4 | | | 1/11/2001 | | PEND |
|
|
|
|
Plan Review Report | | | 1/11/2001 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 1/2/2001 | 1/2/2001 | 1/2/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 1/2/2001 | 1/2/2001 | 1/2/2001 | | PASS |
|
|
|
|
Application received | | | 1/2/2001 | | |
|
|
|
came in 12/29/2000/pe
|
Routing - PLAN CHECK | 1/2/2001 | 1/2/2001 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 1/2/2001 | | | | PEND |
Dan Overy
|
|
|
|