BLD-Final | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | PASS |
Steven Webb
|
|
|
###-#### c. of c. #21597 issued 9/20/2001 10:22:21 AM
|
DOC - Permit Finaled | 9/20/2001 | 9/20/2001 | 9/20/2001 | A | PASS |
Steven Webb
|
|
|
Finaled by inspector at 9/20/2001 10:22:26 AM
|
BLD-Final | 9/19/2001 | 9/19/2001 | 9/19/2001 | P | FAIL |
Steven Webb
|
|
|
###-#### RYAN c/n issued--Elec. seal package, W. stripping on 20 min. fire door and penetrations on 1-Hr wall needs fire caulk. 9/19/2001 2:36:45 PM
|
BLD-Aging Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | | FAIL |
Steven Webb
|
|
|
permit expired 8/6/2001 8:23:47 AM
|
BLD-Aging Inspection | 6/6/2001 | 6/6/2001 | 6/6/2001 | | PASS |
Steven Webb
|
|
|
wip 6/6/2001 8:09:07 AM
|
BLD-Framing/Rough-in | 4/5/2001 | 4/6/2001 | 4/6/2001 | A | PASS |
Steven Webb
|
|
|
brian ###-#### Energy not framing 4/6/2001 12:25:51 PM
|
BLD-Framing/Rough-in | 4/4/2001 | 4/5/2001 | 4/5/2001 | A | PASS |
Steven Webb
|
|
|
###-#### ok to insulate 4/5/2001 10:26:54 AM
|
BLD-Framing/Rough-in | 4/2/2001 | 4/3/2001 | 4/3/2001 | A | FAIL |
Steven Webb
|
|
|
Bryan ###-#### C/N posted on site 4/3/2001 10:03:34 AM
|
BLD-Framing/Rough-in | 3/21/2001 | 3/22/2001 | 3/22/2001 | A | PASS |
Dave Hannah
|
|
|
###-#### 3/22/2001 11:00:59 AM ext shear panels only ok to cover ext 3/22/2001 11:01:43 AM
|
BLD-Framing/Rough-in | 3/20/2001 | 3/20/2001 | 3/20/2001 | P | FAIL |
Steven Webb
|
|
|
###-#### c/n posted-additional nailing and mst straps per plans needed, interior shear inspection needed prior to mud and tape 3/20/2001 2:16:13 PM
|
BLD-Framing/Rough-in | 3/15/2001 | 3/15/2001 | 3/15/2001 | P | FAIL |
Steven Webb
|
|
|
SHEAR ONLY\###-#### C/N posted--per plans shearwall & strap schedule needed prior to shear wall inspection. 3/15/2001 2:10:11 PM
|
Override - Parcel Holds | | | 3/15/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 3/9/2001 | | |
|
|
|
|
BLD-Foundation | 1/26/2001 | 1/26/2001 | 1/26/2001 | P | PART |
Steven Webb
|
|
|
jerry ###-#### foundation wall, hd not installed, rebar ok & forms ok. 1/26/2001 1:44:18 PM
|
Override - Parcel Holds | | | 1/26/2001 | | |
|
|
|
|
BLD-Footing | 1/24/2001 | 1/25/2001 | 1/25/2001 | A | PART |
Steven Webb
|
|
|
###-#### ready at 11setback, soil ok, reviewed rebar requirements on plans, not installed at time of inspection. 1/25/2001 11:15:26 AM
|
Override - Parcel Holds | | | 1/24/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 1/22/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/22/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 1/18/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/18/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/18/2001 | | DONE |
|
|
|
left mess that permit is ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/17/2001 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 1/12/2001 | | 1/17/2001 | | PASS |
Steve Munroe
|
|
|
1/17/2001 16:00:48 SAM - activity updated through activity BLDA022 from case BLD01-00018.
|
Override - Parcel Holds | | | 1/16/2001 | | |
|
|
|
|
Pending Assignment by DJO | 1/3/2001 | | 1/12/2001 | | DONE |
Dan Overy
|
|
|
1/12/2001 15:13:00 SAM - activity updated through activity BLDA183 from case BLD01-00018.
|
Routing - PUBLIC WORKS | 1/3/2001 | 1/3/2001 | 1/4/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 1/3/2001 | 1/3/2001 | 1/4/2001 | | PASS |
|
|
|
|
Application received | | | 1/3/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 1/4/2001 | 1/4/2001 | | | PEND |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Plan Reviewer's activity | | | | | PEND |
|
|
|
1/17/01 Called builder. He will bring down a extra site plan.
|