Fee Review-notes | 1/3/2001 | 1/3/2001 | 5/24/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/26/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8604 issued 3-26-01 to World Travel Partners.
|
Permanent Occupancy | | 3/16/2001 | 3/16/2001 | | DONE |
|
|
|
|
BLD-Final | 3/15/2001 | 3/16/2001 | 3/16/2001 | P | PASS |
Tom Arcoraci
|
|
|
###-#### ok for perm occ after elec signs perm 3/16/2001 2:16:36 PM
|
FIRE-Final Inspection | 3/15/2001 | 3/16/2001 | 3/16/2001 | P | PASS |
Joe Tawney
|
|
|
###-#### Reinsp OK for permanant occupancy 3/19/2001 8:05:00 AM
|
FIRE-Final Inspection | 3/15/2001 | 3/15/2001 | 3/15/2001 | P | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail AHU duct detectors 3/16/2001 8:19:48 AM
|
BLD-Other | 3/6/2001 | 3/9/2001 | 3/9/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/06/2001 at 14:24:48. Contact: ###-####. pods as per manufactures specs ceiling grid, need letter from architect. 3/9/2001 11:09:04 AM
|
BLD-Framing/Rough-in | 2/14/2001 | 2/15/2001 | 2/15/2001 | A | PASS |
Russ Owen
|
|
|
JC ###-####
|
Issue PAID IN FULL permit | | | 2/6/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/2/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/2/2001 | | DONE |
|
|
|
|
Routing - FIRE | 1/30/2001 | | 2/1/2001 | | PASS |
|
|
|
delayed submittal; sprinklers & alarms
|
Plan Review Completed(1st rev) | | | 2/1/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/1/2001 | | 2/1/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2001 | | PASS |
|
|
|
|
Application received | | | 2/1/2001 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 1/4/2001 | | 2/1/2001 | | PASS |
Carl Westfall
|
|
|
2/1/01 15:56:16 CJW - activity updated through activity BLDA022 from case BLD01-00019.
|
Routing - PLAN CHECK | 1/9/2001 | | 1/30/2001 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 1/30/2001 | | PASS |
|
|
|
UBC plan review started January 30, 2001 and finished the same day. The drawings were approved with conditions. See the conditions list.
|
Plan Reviewer's activity | | | 1/22/2001 | | DONE |
|
|
|
PARTIAL PERMIT ISSUED 1/22/01 at the request of the architect.
|
Routing - PUBLIC WORKS | 1/4/2001 | | 1/9/2001 | | PASS |
|
|
|
|
Pending Assignment by MYS | 1/4/2001 | | 1/4/2001 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/4/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 1/3/2001 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/3/2001 | | DONE |
|
|
|
|