To remodel the northwest portion, add two accessible restrooms, four office spaces and corridor within the existing multi-tenant building. Install a suspended ceiling in an existing meeting room. Work to include relocating the fire sprinklers, HVAC system, up grading electrical service, reroofing structure adding new exterior windows and doors. Additional work being done on the exterior is relocating two gazebos to the property at 1125 S. Capitol, landscaping pool area and front entry. All construction per the approved plans, attached comment list. (P.C.#0008-01) MJP * PLAN MODIFICATION 6/1/01 * Enlarge storage area in group meeting room, south of dininr room and reduce occupant load of this meeting room and make corridor a norated hallway. All construction of this area per the approved plans dated 6/1/01. MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  3/23/2006  
BLD-Aging Inspection2/10/20042/10/20042/10/2004 PASS
DetailsJim Storey
First Notice 2/10/20042/10/2004 DONE
FIRE-Final Inspection12/8/200312/8/200312/8/2003APASS
DetailsRick Jackson
BLD-Final12/8/200312/8/200312/8/2003APASS
DetailsJim Storey
407 finaled pending fire fire passed ok 12/8/2003 3:39:19 PM
BLD-Aging Inspection12/5/200312/5/200312/5/2003 PASS
DetailsRick Jackson
Permanent occupancy  5/1/2003 DONE
Perm. Occ. Cert. #9638 issued 5-1-03 to Boise City Housing and Community Development for offices.
Permanent occupancy  5/1/2003 DONE
Perm. Occ. Cert. # 9638 issued to Boise City Housing and Community Development offices.
Permanent Occupancy 4/25/20034/25/2003 DONE
Details
BLD-Aging Inspection4/23/20034/23/20034/23/2003 PART
DetailsJim Storey
final ok pendig fire alarm approval insp. 4/23/2003 2:19:03 PM
Plan Modification Accepted  3/28/2003 DONE
Fire Alarm plan modification approved - see FIR03-00053
BLD-Aging Inspection2/21/20032/21/20032/21/2003 PART
DetailsJim Storey
fire planreview recieved plans today for approval 2/24/03. 2/24/2003 11:19:52 AM
BLD-Aging Inspection12/17/200212/17/200212/17/2002 PART
DetailsJim Storey
12/17/2002 8:41:50 AM mike hoppkins to have work complet 30 days. 12/17/2002 8:42:34 AM
Print Pending Permit.LaserJet4  7/2/2002 DONE
BLD-Aging Inspection10/15/200110/15/200110/15/2001 PART
DetailsJim Storey
mike hoppkins to call for plm and bld for sign off. 10/15/2001 9:04:38 AM
BLD-Aging Inspection8/13/20018/13/20018/13/2001 PART
DetailsJim Storey
cathy will notafy mike hoopkins to finsh up project. 8/13/2001 8:20:58 AM
Telephone call  8/13/2001 DONE
Talked to Mike Hopkins re: status of temp. occ. - will follow up re: fire alarm requirements w/Rick Jackson
Code Occupancy Approval  7/20/2001 PASS
Inspected & passed.
Fee Review-notes1/4/20011/4/20017/12/2001 DONE
Temporary occupancy  6/13/2001 PART
Temp. Occ. Cert. #4559 issued 6-13-01 to Boise City Housing & C.D.
BLD-Final6/12/20016/12/20016/12/2001PPART
DetailsRuss Owen
###-#### ok temp oc , appears to still need info for 1 hr corridor deletion. see note from last insp. 1/12/2002 3:47:30 PM
FIRE-Final Inspection6/12/20016/12/20016/12/2001APART
DetailsRick Jackson
Added by Inspector: 409 On 6/12/2001 10:29:27 AM temp occ approved pending resolution of fire sprinkler monitoring
Override - Parcel Holds  6/8/2001  
Code Occupancy Approval  6/8/2001 TEMP
Staffed with Scott Spjute and Tempora Wilson. No DR on plan. Money is being held by Planning Development, therefore no need to bond. Temp Occupancy Approved.
Override - Parcel Holds  6/7/2001  
Code Occupancy Approval  6/7/2001 FAIL
Request form Joe, ###-####, for "temporary occupancy sign off." Inspected pool area and found landscaping was still in progress. Joe said that sprinklers, and plants lawn still needed to be done and estimated that it would be about $12,000.00 to do. Additionally, the front piece is not done, asphalt needs to be added to the space between the new bricks and the old asphalt. A large rock, to show address, is not yet in place. I provided him information on how to do a bond for temporary occupancy. Joe said that he is under a deadline of June 16, 2001.
Plan Reviewer's activity  6/1/2001 PASS
Override - Parcel Holds  6/1/2001  
Print Pending Permit.LaserJet4  6/1/2001  
Case Summary (BLD)  6/1/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/1/2001 DONE
Print Occupancy Form  6/1/2001 DONE
Plan assigned to (M_P)5/2/2001 6/1/2001 PASS
DetailsMike Phillips
6/1/2001 09:35:10 M_P - activity updated through activity BLDA022 from case BLD01-00027.
Routing - PLAN CHECK5/2/2001 6/1/2001 DONE
Plan modification of 4/30/01
Need additional informaiton prioor to issuing plan modification. 5/15/01
Plan Modification complete. 6/1/01 MJP
BLD-Foundation5/18/20015/21/20015/21/2001APASS
DetailsJim Storey
rebar Joe ###-#### sign wall out front ok for rebar per plan. 5/21/2001 9:26:40 AM
Override - Parcel Holds  5/18/2001  
Plan Reviewer's activity  5/15/2001 FAIL
Plan modification problems 2 exits required from meeting room.Called and spoke with Larry Sundell and explained what needed to be done. Waiting for new plans to be submitted.
BLD-Framing/Rough-in5/10/20015/11/20015/11/2001APART
DetailsCarl Dependahl
ceiling grid joe ###-####, ceiling ok...plan check has resub. according to Mike Hopkins. OK to continue pending verification of deletion of 1hr corridor from conference rm. 5/11/2001 10:17:25 AM
Override - Parcel Holds  5/10/2001  
BLD-Framing/Rough-in5/9/20015/9/20015/9/2001PCANC
DetailsJim Storey
ceiling grid Joe ###-#### reinspection plan modifacation not approved thru plan review hold on job until approved. 5/9/2001 5:02:21 PM
Override - Parcel Holds  5/9/2001  
BLD-Framing/Rough-in5/7/20015/8/20015/8/2001AFAIL
DetailsCarl Dependahl
ceiling grid \\###-#### this has nothing to do with plan mod....add wires,submit clarification as req'd, make fire c/n ok. 5/8/2001 10:08:09 AM
Override - Parcel Holds  5/7/2001  
Plan routing begun/TENANTS  5/2/2001 DONE
Plan modification of 4/30/01
Plans ACCEPTED BY PLAN TECH  5/2/2001 DONE
Plan modification of 4/30/01
Received Certificate of Value  4/30/2001 DONE
Plan modification of 4/30/01
Plan resubmittals received  4/30/2001 PASS
Received two copies of revised sheet one of one. Routed to Lee Rice. KMM provide cleanout at note B
CHANGE STATUS TO (PND)  4/30/2001 DONE
Plan Modification
BLD-Framing/Rough-in3/30/20014/2/20014/2/2001PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/30/2001 at 08:58:51. Contact: ###-####. walls only c/n need arch. to submit ceilling assemblie/ no ra in coridor/protect supply. putty pad boxes back to back next to rest a room. 4/2/2001 5:09:08 PM
Routing - PLAN CHECK3/19/2001 3/23/2001 DONE
Plan Reviewer's activity  3/23/2001 PASS
Print Pending Permit.LaserJet4  3/23/2001 DONE
Print Pending Permit.LaserJet4  3/23/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/23/2001 DONE
Print Occupancy Form  3/23/2001 DONE
Inspection Record Card- Bld  3/23/2001 DONE
Issue PAID IN FULL permit  3/23/2001 DONE
Plan assigned to (M_P)1/17/2001 3/23/2001 PASS
DetailsMike Phillips
3/23/2001 09:30:36 M_P - activity updated through activity BLDA022 from case BLD01-00027.
CHANGE ISSUED DATE  3/23/2001 DONE
Plan resubmittals received  3/21/2001 DONE
Plan resubmittals received from Larry Sundell, two sets of sheets one and eleven. Forwarded same to Mike Phillips. 3/21/01 DAR
Plan resubmittals received  3/20/2001 DONE
Received two copies of revised sheets one and eleven. Routed to Mike P. KMM
Plan Reviewer's activity  3/20/2001 FAIL
Not all comments have been answered.
Routing - PLANNING3/16/2001 3/19/2001 PASS
approved per CZC01-00014
Plan Reviewer's activity  3/16/2001 FAIL
additional information required for further review.
Routing - PLAN CHECK2/27/2001 3/16/2001 FAIL
sending to Planning.
BLD-Conference3/7/20013/7/20013/7/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 3/7/2001 6:49:24 PM w/ Dan Stuart re possible add'l permit
Plan resubmittals received  3/5/2001 DONE
Received Plan resubmittals, small documents, structural caculationsand two sets of plans with sheets 1, 2, 5 and 11. 3/5/01 DAR
Routing - FIRE2/23/2001 2/27/2001 PASS
Plan Review Completed(1st rev)  2/27/2001 FAIL
Routing - PLAN CHECK1/26/2001 2/23/2001  
Routing to fire.
Plan Reviewer's activity  2/23/2001 FAIL
Additional information required for further review.
Routing - PUBLIC WORKS1/17/2001 1/25/2001 PASS
Routing - PLANNING1/25/2001 1/25/2001 FAIL
Need a zoning certificate for the exterior changes. Called Larry Sundell.
Pending Assignment by MYS1/17/2001 1/17/2001 DONE
DetailsMarlene Southard
Additional plans submitted  1/16/2001 DONE
Received two copies of stamped and signed sheet 12 ( electrical) Put with plans. KMM
Plans ACCEPTED BY PLAN TECH  1/5/2001 PEND
Received Certificate of Value  1/4/2001 DONE
Application received  1/4/2001