BLD-Aging Inspection | 9/17/2001 | 9/17/2001 | 9/17/2001 | | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 9/17/2001 | 9/17/2001 | 9/17/2001 | P | PASS |
Jim Sly
|
|
|
Finaled by inspector at 9/17/2001 11:42:01 AM
|
BLD-Aging Inspection | 7/16/2001 | 7/16/2001 | 7/16/2001 | | PASS |
Jim Sly
|
|
|
Previously passed by 350 7/23/2001 11:32:25 AM
|
BLD-Final | 5/11/2001 | 5/14/2001 | 5/14/2001 | A | PASS |
Alan Hauser
|
|
|
c/c #19288 5/14/2001 11:34:03 AM
|
BLD-Energy code compliance | 3/8/2001 | 3/9/2001 | 3/9/2001 | A | PASS |
Jim Sly
|
|
|
Chad ###-####
|
BLD-Framing/Rough-in | 3/7/2001 | 3/7/2001 | 3/7/2001 | A | PASS |
Jim Sly
|
|
|
chad ###-####
|
BLD-Framing/Rough-in | 2/22/2001 | 2/23/2001 | 2/23/2001 | A | PART |
Jim Sly
|
|
|
Don Crocker ###-#### Shear OK. 2/23/2001 1:24:16 PM
|
BLD-Framing/Rough-in | 2/23/2001 | 2/23/2001 | 2/23/2001 | P | NR |
Russ Owen
|
|
|
###-####c/n posted still need eng approval or add new hd. 2/23/2001 2:17:02 PM
|
BLD-Framing/Rough-in | 2/20/2001 | 2/20/2001 | 2/20/2001 | P | FAIL |
Jim Sly
|
|
|
###-#### C/N Shear nailing and Eng to approve (1) strap. 2/20/2001 2:16:48 PM
|
BLD-Foundation | 1/25/2001 | 1/26/2001 | 1/26/2001 | A | PASS |
Jim Sly
|
|
|
###-####
|
BLD-Foundation | 1/24/2001 | 1/25/2001 | 1/25/2001 | P | CANC |
Jim Sly
|
|
|
###-#### Canc by Contr. 1/25/2001 2:41:27 PM
|
BLD-Foundation | 1/24/2001 | 1/24/2001 | 1/24/2001 | P | PART |
Jim Sly
|
|
|
###-####
|
BLD-Foundation | 1/24/2001 | 1/24/2001 | 1/24/2001 | P | PART |
Jim Sly
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 1/24/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/23/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/23/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/23/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/23/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PUBLIC WORKS | 1/9/2001 | 1/9/2001 | 1/17/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 1/16/2001 | 1/16/2001 | 1/16/2001 | | PASS |
|
|
|
Revised site plan.
|
Routing - PLANNING | 1/9/2001 | 1/9/2001 | 1/10/2001 | | FAIL |
|
|
|
Driveway doesn't meet ordinance. Called Chad. He will correct site plan.
|
Application received | | | 1/9/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 1/17/2001 | 1/17/2001 | | | PEND |
|
|
|
|
Plan Reviewer's activity | | | | | PEND |
|
|
|
1/18/01 Morning. I called and talked to the builder. I let him know that I need the set of plans the engineer marked up since the calculations and plans are NOT matching up. He said he would get them for me.
|
Plan Reviewer's activity | | | | | PEND |
|
|
|
1/18/01 15:30 Plan review is done untill I receive engineered plans from builder.
1/18/01 Crocker brought in the engineers marked up set. I need to call the engineer.
|
Print Pending Permit.LaserJet4 | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Plan Reviewer's activity | | | | | PEND |
|
|
|
1/19/01 9:00 I faxed den and dining wall line to Riley, engineer. He is going to re-calculate the wall line and get it back to me.
1/23/01 I received new engineering.
|
Telephone call | | | | | PEND |
|
|
|
1/19/01 13:30 Called and talked to Don. I let him know that I should receive new calculations from Riley on Monday. He said that would be fine.
|
Pending Assignment by DJO | 1/9/2001 | | | | PEND |
Dan Overy
|
|
|
|