Fee Review-notes | 7/2/2003 | 7/2/2003 | 7/2/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent occupancy | | | 7/27/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8776 issued 7-27-01 to Domino's Pizza.
|
Permanent Occupancy | | 7/25/2001 | 7/25/2001 | | DONE |
|
|
|
|
BLD-Final | 7/24/2001 | 7/25/2001 | 7/25/2001 | A | PASS |
Russ Owen
|
|
|
only running on temp needs final occ\###-####. ok for a permanent occupancy. 7/25/2001 10:28:58 AM
|
BLD-Final | 7/23/2001 | 7/23/2001 | 7/23/2001 | P | NR |
Russ Owen
|
|
|
###-####. contractor called me said he bathroom grab bar in place but does not have lateral ceiling pods in yet. 7/23/2001 3:39:01 PM
|
BLD-Aging Inspection | 7/4/2001 | 7/4/2001 | 7/4/2001 | | PART |
Russ Owen
|
|
|
went out to job .corrections were to add 42 in grab bar at rest room and ceiling pods,and i checked , but this has not been done i left buiseness card with worker and asked if they could have store manager call me. 7/6/2001 12:35:01 PM
|
Telephone call | | | 6/25/2001 | | DONE |
|
|
|
Called Ben @ ###-#### & left msg. re: status of temp. occ.
|
Fee Review-notes | 1/12/2001 | 1/12/2001 | 4/25/2001 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/23/2001 | 4/24/2001 | 4/24/2001 | A | PASS |
Joe Tawney
|
|
|
Ben ###-#### REinsp OK for permanant occupancy 4/23/2001 5:11:38 PM
|
BLD-Final | 4/23/2001 | 4/24/2001 | 4/24/2001 | A | PART |
Russ Owen
|
|
|
fn occ ben-- ###-#### Ok for temp oc ,only c/n is for ceiling grid pods,and left side grab bar in H/C rest room. posted with plans. 11/24/2001 10:59:20 AM
|
Temporary occupancy | | | 4/24/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4539 issued 4-24-01 to Domino's Pizza in the Calderwood Center.
|
FIRE-Final Inspection | 4/20/2001 | 4/23/2001 | 4/23/2001 | A | FAIL |
Joe Tawney
|
|
|
Reinsp Fail Door Hdwre 4/23/2001 12:24:03 PM
|
FIRE-Final Inspection | 4/19/2001 | 4/20/2001 | 4/20/2001 | A | FAIL |
Joe Tawney
|
|
|
###-####. 4/20/2001 1:33:41 PM Final Fail C/N issued 4/20/2001 2:27:02 PM
|
BLD-Final | 4/19/2001 | 4/19/2001 | 4/19/2001 | P | CANC |
Russ Owen
|
|
|
late pm scott ###-#### Called contractor told him he would need all required signatures on occupancy card , also told him that a grid ceiling inspection had not been done, need to check this adn 1 brace at front sofit was left on a c/n for frame insp. will recall when ready. 11/19/2001 3:50:53 PM
|
BLD-Framing/Rough-in | 3/29/2001 | 3/29/2001 | 3/29/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/29/2001 at 09:06:22. Contact: .ok to cover need 1 brace at 45 added to the soffit over counter, verifiy at next insp, ceiling not yet in place. 3/29/2001 2:38:29 PM
|
BLD-Framing/Rough-in | 3/26/2001 | 3/27/2001 | 3/27/2001 | A | FAIL |
Russ Owen
|
|
|
asap if possible\\###-#### soffit not per plans mec insp req. 3/27/2001 1:02:36 PM
|
BLD-Framing/Rough-in | 3/12/2001 | 3/12/2001 | 3/12/2001 | P | FAIL |
Russ Owen
|
|
|
after 2 ###-####.no approved plans on site. 3/12/2001 1:47:00 PM
|
Issue PAID IN FULL permit | | | 2/27/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/21/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/21/2001 | | DONE |
|
|
|
|
Telephone call | | | 2/21/2001 | | DONE |
|
|
|
left message gave dollar amount
|
Routing - PLAN CHECK | 2/14/2001 | | 2/20/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2001 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 1/24/2001 | | 2/20/2001 | | PASS |
Jason Blais
|
|
|
2/20/2001 14:52:03 JCB - activity updated through activity BLDA022 from case BLD01-00079.
|
Plan resubmittals received | | | 2/16/2001 | | |
|
|
|
2 copies CS-A-1-A-2-A-3/BOISE PLAN CHECK WRITTEN RESPONCE. TOOK TO JASON BLAIS 2/16/2001/PE
|
Routing - FIRE | 2/9/2001 | | 2/14/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 2/14/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 1/29/2001 | | 2/9/2001 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Plan resubmittals requested | | | 2/9/2001 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLUMBING | 1/26/2001 | | 1/29/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 1/24/2001 | | 1/26/2001 | | PASS |
|
|
|
|
Pending Assignment by MYS | 1/24/2001 | | 1/24/2001 | | DONE |
Marlene Southard
|
|
|
|
Routing Off Site - C.D.H | 1/16/2001 | | 1/23/2001 | | PASS |
|
|
|
Rick George came and took plans out to CDH. Plans were submitted without CDH approval. KMM
|
Plans ACCEPTED BY PLAN CHECK | | | 1/23/2001 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 1/16/2001 | | FAIL |
|
|
|
Plans not signed off by CDH. Rick George came in to take plans out to CDH
|
Plans ACCEPTED BY PLAN TECH | | | 1/12/2001 | | HOLD |
|
|
|
Plans on hold. They were not signed off by CDH. Contacted Richard George of this need and gave him Deb's cell phone number. I also requested that he come in and pick up plans to take to Deb to sign off. KMM
|
Received Certificate of Value | | | 1/12/2001 | | DONE |
|
|
|
|
Application received | | | 1/12/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/12/2001 | | DONE |
|
|
|
|