Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD01-00138
StatusFinaled
Name C J BANKS
Site Address 350 N MILWAUKEE ST Unit: 2323
Project NameBTS - #2323
Customer Number 
ePlanReviewNo
Description
To construct a 4,497 sq.ft. retail tenant space on the upper level of the mall per approved plans on file. Work to include, demolition of existing interior finishes, partitions, and storefront. Construction of new noncombustible partitions to create storage area, dressing rooms, sales area, and an access hallway to the exit passage way. Construction of a new storefront glazing and bulkhead system and installation of a new rolldown security grill. Installation of a new suspended ceiling system, new flooring and miscelaneous related interior finishes. Separate permits required for Electrical, mechanical, plumbing and sign installation. NOTE: This building is fully fire sprinklered and has a smoke control system. Any alterations or modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department. The smoke evacuation system shall be maintained as installed under the 1985 UBC. (P.C.#0052-01)*RMH*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes1/19/20011/19/20015/24/2001 DONE
Permanent occupancy UNPAID FEE  4/9/2001 DONE
Perm. Occ. Cert. #8624 issued 4-6-01 to C J Bank on the upper level of Boise Towne Square.
FIRE-Final Inspection4/4/20014/5/20014/5/2001ACANC
DetailsJoe Tawney
reinspection Kirk ###-#### #2323
BLD-Final4/4/20014/5/20014/5/2001PPASS
DetailsCarl Dependahl
Kirk ###-#### #2323
FIRE-Final Inspection4/5/20014/5/20014/5/2001APASS
DetailsJoe Tawney
Kirk ###-#### Reinsp OK for permanant occupancy 4/5/2001 6:09:14 PM
FIRE-Final Inspection4/2/20014/3/20014/3/2001AFAIL
DetailsJoe Tawney
4/3/2001 5:35:01 PM Final Fail C/N issued 4/3/2001 5:35:17 PM
FIRE-Alarm Testing4/2/20014/3/20014/3/2001AFAIL
DetailsJoe Tawney
4/3/2001 5:35:40 PM Final Fail C/N issued 4/3/2001 5:36:02 PM
BLD-Final4/2/20014/3/20014/3/2001PCANC
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/02/2001 at 13:47:31. Contact: ###-####. cancelled by kirk
FIRE-Final Inspection3/27/20013/28/20013/28/2001APART
DetailsJoe Tawney
###-#### pager OK on spklr rough in 3/28/2001 1:18:23 PM
BLD-Other3/28/20013/28/20013/28/2001PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 03/28/2001 at 08:34:34. Contact: ###-####. t-bar grid ok dressing room complete 1 pod. 3/28/2001 4:52:51 PM
BLD-Framing/Rough-in3/15/20013/16/20013/16/2001APART
DetailsCarl Dependahl
Kirk ###-####, storefront & sidewalls ok ;bracing modified, ok as built3/16/2001 6:34:41 PM 3/16/2001 6:36:25 PM
BLD-Framing/Rough-in3/9/20013/9/20013/9/2001PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 03/09/2001 at 07:46:14. Contact: .ok to cover all but ,bulk head ,const not started at this time. 3/9/2001 1:44:13 PM
Plan assigned to (R_H)1/24/2001 2/26/2001 PASS
Details
2/26/2001 09:51:43 RMH - activity updated through activity BLDA022 from case BLD01-00138.
Routing - PLAN CHECK2/13/2001 2/26/2001 PASS
DetailsRon Hill
PLANS/APPL TAKEN TO FRONT DESK  2/26/2001 PASS
DetailsRon Hill
Case Summary (BLD)  2/26/2001 DONE
Inspection Record Card- Bld  2/26/2001 DONE
Print Occupancy Form  2/26/2001 DONE
Telephone call  2/26/2001 DONE
permit ready
Issue PAID IN FULL permit  2/26/2001 DONE
Plan resubmittals received  2/23/2001 DONE
Received 3 sets of resubmittals from Finn Daniels Architect, plus design caculations, forwarded same to Ron Hill 2/23/01 DAR
Routing - FIRE2/8/2001 2/13/2001 PASS
DetailsRon Hill
Plan Review Completed(1st rev)  2/13/2001 FAIL
Case Summary (BLD)  2/8/2001 DONE
Plan Reviewer's activity  2/8/2001 FAIL
DetailsRon Hill
Faxed and mailed requirements to the Architect, Greg Dahling, and Mark Finnemanns office. On 2-8-01 at 3:00 pm. Routed plans to Fire department for reveiw.
Routing - PLAN CHECK1/25/2001 2/8/2001 FAIL
DetailsRon Hill
Routing - PUBLIC WORKS1/24/2001 1/25/2001 PASS
Pending Assignment by MYS1/24/2001 1/24/2001 DONE
DetailsMarlene Southard
Plans ACCEPTED BY PLAN TECH  1/22/2001 DONE
Application received  1/19/2001  
Recd Pcfee & Taken To Pln CK  1/19/2001 DONE