Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD01-00186
StatusFinaled
Name ELLSWORTH ROY J & FRANCES
Site Address 1425 W RIVER ST
Project NameORTHOPEDIC SURGERY
Customer Number 
ePlanReviewNo
Description
ORTHOPEDIC SURGERY CENTER OF IDAHO -TO CONSTRUCT A NEW 9,765 SQUARE FOOT, ONE STORY, OUTPATIENT ORTHOPEDIC SURGERY CENTER BUILDING AND RELATED SITE IMPROVEMENTS. THIS BUILDING IS CONSTRUCTED OF EXTERIOR MASONRY WALLS, INTERIOR STEEL FRAME AND ROOF JOISTS, THIS BUILDING IS FULLY FIRE SPRINKLED. THE SPRINKLERS ALLOW THIS OCCUPANCY WITHIN A II-N BUILDING (UBC SEC. 308.2.1, EXC. 3) ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. THIS BUILDING IS LOCATED WITHIN A FLOODPLAIN AREA AND A COMPLETED FLOODPLAIN CERTIFICATE IS REQUIRED TO BE SUBMITTED TO THE STRUCTURAL INSPECTOR AS SOON AS POSSIBLE AFTER COMPLETION OF THE FOUNDATION AND SLAB FLOOR PLACEMENT. (FLOODPLAIN) DRH00-00196/PC#066-01/JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes1/24/20011/24/20014/11/2002 DONE
Permanent occupancy  2/19/2002 DONE
Perm. Occ. Cert. #9048 issued 2-19-02 to the Orthopedic Surgery Center.
Permanent Occupancy 2/14/20022/14/2002 DONE
Details
BLD-Final2/13/20022/14/20022/14/2002APASS
DetailsCarl Dependahl
mike ###-#### fn , card to Cathy 2/14/2002 1:42:29 PM
Temporary occupancy  2/14/2002 PART
Temp. Occ. Cert. #4725 issued 2-14-02 to the Orthopedic Surgery Center.
BLD-Conference2/1/20022/1/20022/1/2002APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 2/1/2002 8:59:53 AM rec'd proper flood cert, ok
BLD-Conference1/31/20021/31/20021/31/2002APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/31/2002 10:51:51 AM need proper flood cert...from actual const floor levels; called bldr.
BLD-Final1/29/20021/30/20021/30/2002AFAIL
DetailsCarl Dependahl
DAVE ###-####, c/n handrail at main entry; rec'd spec insps'affidavit & flood cert 1/30/2002 11:42:47 AM
BLD-Final1/22/20021/23/20021/23/2002ANR
DetailsTom Arcoraci
###-#### will recall for insp 1/23/2002 10:58:26 AM
Code Occupancy Approval1/22/20021/22/20021/22/2002PCANC
DetailsWm. Michael Meloy
Scheduled by Inspector: WMM On 1/22/2002 3:31:51 PM
Code Occupancy Approval1/22/20021/22/20021/22/2002PPASS
DetailsWm. Michael Meloy
Scheduled by Inspector: WMM On 1/22/2002 1:46:50 PM Passed 1/22/2002 1:47:53 PM
FIRE-Final Inspection1/16/20021/17/20021/17/2002APASS
DetailsRick Jackson
###-####
FIRE-Final Inspection1/8/20021/11/20021/11/2002PFAIL
DetailsRick Jackson
JOHN ###-#### FIRE ALARM AND SAFTY c/n issued 1/11/2002 4:49:36 PM
FIRE-Final Inspection1/8/20021/11/20021/11/2002ACANC
DetailsRick Jackson
JOHN ###-#### FIRE ALARM AND SAFTY rescheduled for pm 1/11/2002 6:24:08 AM
FIRE-Sprinkler Rough-in1/7/20021/8/20021/8/2002PFAIL
DetailsRick Jackson
per rick around 1:30-- john-- ###-#### r/i- with GC - penetrations; need to test alarms; scheduled for 1/11 pm for final inspection 1/8/2002 3:08:27 PM
BLD-Conference1/8/20021/8/20021/8/2002PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/8/2002 12:41:53 PM w/ contractor & site eng'r re ramp: provide min 36 " wide x approx. 6' level at bottom
BLD-Conference1/3/20021/3/20021/3/2002APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/3/2002 8:11:04 AM w/ supt & framer...complete seal at smoke barriers; ok to chk at final
BLD-Other12/31/200112/31/200112/31/2001PPASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/31/2001 at 08:45:24. Contact: ###-####... ok for staff only to stock bldg & train, exits are maintained. 12/31/2001 1:50:20 PM
BLD-Framing/Rough-in12/31/200112/31/200112/31/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 12/31/2001 1:48:21 PM smoke walls ok; ok to place tiles.
BLD-Other12/28/200112/28/200112/28/2001PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 12/28/2001 at 09:20:57. Contact: ###-####....seal smoke barrier walls per 904, keep c/n 12/28/2001 5:10:42 PM
BLD-Conference12/28/200112/28/200112/28/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 12/28/2001 12:15:23 PM elec ok for grid; complete firestops at 1hr & smoke walls, prior to tiles ...many missed
BLD-Framing/Rough-in12/27/200112/27/200112/27/2001PFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 12/27/2001 3:27:44 PM add wires, spreaders, as need ... get elec r/i ok'd.
BLD-Conference12/18/200112/18/200112/18/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 12/18/2001 12:09:52 PM w/ bldr re ADA ramp
BLD-Framing/Rough-in12/13/200112/13/200112/13/2001PPART
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 12/13/2001 12:16:15 PM grid clg ok exc. add spreaders at loose ends...obtain hvac & elec oks, seal penetrations at rated smoke barriers
12/13/2001 3:12:46 PM
BLD-Conference12/12/200112/12/200112/12/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 12/12/2001 6:00:47 PM w/ supt...rec'd Mti's soils approval as requested... stamped by eng'r
BLD-Conference10/23/200110/23/200110/23/2001PPASS
DetailsCarl Dependahl
Scheduled by Inspector: 340 On 10/23/2001 12:09:53 PM w/ Dave re mech room issues...keep c/n. 10/23/2001 4:27:13 PM
BLD-Conference10/22/200110/22/200110/22/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 10/22/2001 9:25:26 AM w/ Kevin Of Roylance Eng's re soils report...need statement per c/n of 10-19, keep c/n.
BLD-Framing/Rough-in10/19/200110/19/200110/19/2001PFAIL
DetailsCarl Dependahl
###-#### dave..add'l c/n...clarify "occ. separations", dampers, eng's geo-tech & flood cert to be submitted. ok to begin cover, except at hvac areas. 10/19/2001 5:08:08 PM
BLD-Framing/Rough-in10/18/200110/18/200110/18/2001PFAIL
DetailsCarl Dependahl
###-#### DAVE c/n re smoke walls, dampers, other ok's...recall 10/18/2001 12:51:50 PM
Plan resubmittals received  10/11/2001 DONE
Received two copies of revised sheets P1.2. Routed to Bill V. kmm Bill took one set to the field, one set taken to records. dkl
BLD-Framing/Rough-in10/3/200110/3/200110/3/2001APART
DetailsCarl Dependahl
Added by Inspector: 340 On 10/3/2001 11:12:07 AM keep c/n(s)...ext ok to place veneer
BLD-Conference9/20/20019/20/20019/20/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 9/20/2001 5:17:35 PM keep c/n re joist burn thru, reviewed mti report, soils ok
BLD-Conference9/4/20019/4/20019/4/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 9/4/2001 11:07:25 AM w/ Dave & proj mgr onsite...need eng's fix for steel burn thru at roof deck welds
BLD-Framing/Rough-in8/30/20018/30/20018/30/2001AFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 8/30/2001 10:17:30 AM c/n, burn thru at top chords bar joists, need "fix"; discussed smoke barrierconst w/ framer
BLD-Conference8/14/20018/14/20018/14/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 8/14/2001 11:37:27 AM w/ Dave...still need steel certs, masonry & apprropriate concrete reports
BLD-Conference8/7/20018/7/20018/7/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 8/7/2001 9:11:56 AM w/ bldr re c/n of 8-6
BLD-Conference8/7/20018/7/20018/7/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 8/7/2001 10:58:26 AM w/ Sonia of Outland Steel re c/n: will forward steel certs & "approved fabricator" staus for joist/truss manuf. (Vulcraft?) per UBC ch.17
BLD-Conference8/6/20018/6/20018/6/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 8/6/2001 3:44:03 PM w/ supt & mason foreman: need all lifts called for insp to city as req'd: need verify approved fab. status for steel roof framing; show flood cert.
BLD-Footing7/19/20017/20/20017/20/2001APASS
DetailsJim Storey
###-#### north floor slab ok 7/20/2001 8:25:59 AM
BLD-Foundation7/19/20017/20/20017/20/2001PPASS
DetailsJim Storey
###-#### slab on grade ok with foam and vapor barrior. 7/20/2001 3:38:42 PM
BLD-Footing7/20/20017/20/20017/20/2001APASS
DetailsJim Storey
Added by Inspector: 301 On 7/20/2001 8:38:34 AM pad ft and wing walls for screen wall south ok pending mti report.
BLD-Footing7/18/20017/19/20017/19/2001PCANC
DetailsJim Storey
Robert ###-#### called and canclled 7/19/2001 4:22:59 PM
(F) Reprint permit  6/25/2001 DONE
BLD-Footing6/21/20016/22/20016/22/2001APART
DetailsCarl Dependahl
Robert ###-####; perim ftgs; ok pend MTI report. met w/ super onsite 6/22/2001 11:31:50 AM
BLD-Conference6/22/20016/22/20016/22/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 6/22/2001 11:35:33 AM met w/ bldr onsite, surgery suite project, pre-con partial
Inspection Record Card- Bld  6/20/2001  
Print Occupancy Form  6/20/2001 DONE
Print Occupancy Form  6/20/2001 DONE
Telephone call  6/20/2001 DONE
talked to dave to verify plans are ready
Issue PAID IN FULL permit  6/20/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/19/2001 PASS
Routing - PLAN CHECK6/12/2001 6/19/2001 PASS
Plan assigned to (JCM)1/25/2001 6/19/2001 PASS
DetailsJohn Menard
6/19/01 16:31:17 JCM - activity updated through activity BLDA022 from case BLD01-00186.
Plan resubmittals received  6/18/2001 DONE
Received three sets of plan resubmittals from MD architects, forwarded same to John Menard with small documents. 6/18/01 DAR
Routing - PUBLIC WORKS6/12/2001 6/12/2001 PASS
Routing - PLAN CHECK6/8/2001 6/12/2001  
Plan resubmittals received  6/11/2001 DONE
Received three sets of plan resubmittals , sheet A3.0 from MD Architects, forwarded same to John Menard. 6/11/01. DAR
Routing - PLUMBING6/7/2001 6/8/2001 PASS
per resubmitted plans dated 6/4/01 and 97 upc
Plan resubmittals received  6/7/2001 DONE
received six copies of revised A1.0, A1.1, A5.0. Routed to John M. KMM
Routing - PUBLIC WORKS6/6/2001 6/7/2001 FAIL
Requires street light plan per Bill Colson. 6/7/01
Plan resubmittals requested  6/6/2001  
FAxed the architect of record a request for additional revisions and plans reflecting the changes required by the floor elevation change. JCM
Plan resubmittals received  6/6/2001 DONE
Received five copies of revised civil sheets 1 of 2, 2 of 2. Routed to John M. KMM
Plan Reviewer's activity  6/5/2001 FAIL
Reviewed resubmitted plan sheets and require additional revisions. JCM
Plan resubmittals received  6/4/2001  
2 sets each T-1--A1.0--A1.1--A1.2--A1.3--A1.4--A3.0--A6.0--A8.0--F1.1--F2.1--S1.1--S2.2--S2.1--E0.0--E1.0--E2.0--E3.0--E4.0--E5.0--TOOK TO JOHN M 6/4/2001/PE
Plan resubmittals received  5/31/2001 DONE
Plan resubmittals received from Structural Design Inc, two sets of sheets F1.1 and F2.1, forwarded same to John Menard. 5/31/01 DAR
Routing - PUBLIC WORKS4/20/2001 4/25/2001 FAIL
Requires street light plan per Bill Colson. 4/25/01 DAR
Plan Review Completed(1st rev)  4/20/2001 FAIL
Routing - FIRE4/17/2001 4/20/2001 PASS
Routing - PLUMBING4/13/2001 4/17/2001 FAIL
provide floor sinks for ice mechine and refer. in toe kick of the cabinet. move fd's under autoclaves to exposed location and provide funnels. venting in south end is undersized. verify thermol expantion protection sizing with field inspector. water system branch sizing looks too small, resize or provide sizing calculations for review. if an automatic soap dispensor is installed provide a water supply for it. additional cross connection protection may be required.
Plan resubmittals requested  4/13/2001 FAIL
Mailed the architect of record a copy of the comment list requesting revisions. JCM
Plan resubmittals received  4/11/2001 DONE
received three copies of revised sheets F2.1, S2.1, S2.2. routed to john m. kmm
Additional plans submitted  4/11/2001 DONE
Received three copies of plumb., mech. , elec., sheets and three copies of project manual. routed to john. kmm
Plan Reviewer's activity  3/15/2001 HOLD
Partially reviewed submitted plans and application. Plans sets do not contain the required mechanical, electrical or plumbing plans. These items were requested by the Plan Tech on 1/25/01. The plans are on hold in the plan reviewer's area until all required plan sheets have been submitted for review. JCM
Routing Off Site - STRUCTURAL3/8/2001 3/12/2001 PASS
Received a fax from the consulting engineer approving structural resubmittals. JCM
Routing - PLUMBING3/9/2001 3/12/2001 FAIL
please provide a complete set of plumbing drawings, fixture schedule, med gas system, equipment intake and exhaust locations, etc.
Routing - PLANNING3/6/2001 3/9/2001 PASS
Approved per DRH00-196.
Plan resubmittals received  3/7/2001 DONE
three copies of calculations and revision 1 sheets F2.1-S2.1-S2.2 TAKEN TO JOHN M. 3/37/2001
Routing - PUBLIC WORKS2/22/2001 3/6/2001 FAIL
brian failed eng information sent to eng. in feb waiting on final plans. bgm/pe
Plan routing begun/NEW & ADDTN  2/22/2001 DONE
Will route to PW, PZ. Still waiting for Plumb. and Mech. Plans. KMM
Plan resubmittals requested  2/22/2001  
Faxed a copy of the structural comment list to the architect of record requesting structural plan revisions. JCM
Routing Off Site - STRUCTURAL2/2/2001 2/19/2001 FAIL
Contacted PDQ to take plans to outside eng. KMM Received a comment list from the consulting structural engineer requesting revisions. JCM
Plan resubmittals received  2/2/2001 DONE
Received two copies of Struct. calcs. Two copies of land scape plan.
Requires 1. Operations & Maintenance Manual for grading permit.
Requires 1. Two copies of plumb. plans.
2. Two copies of mech. plans. KMM

2/08-01 received one copy of O & M manual. can now start grading and drainage permit. Still waiting for the mech. and plumb. plans. KMM
Plan resubmittals received  1/31/2001 DONE
Received
1. Revised cert. of value for building minus the grading.
2. Received five copies of civil sheets for grading permit which will be started as soon as I receive O&M manual and two copies of landscape plans.
3. Received five copies of site plan. Put three with building and two with grading and drainage plans.
Contacted Al to let him know that I still need.
For building permit. 1. Two copies of mech. and plumb. plans
2. Structural calcs
For Grading permit. 1. O&M manual
2. two copies of landscape plans.
3. Cover sheet of application with project description.
Telephone call  1/29/2001 DONE
Spoke with Rick of MD Architects at ###-####. He is working on the above submittals and will fedex them when complete. Plumb. and Mech are being worked on as well and will be sent asap. KMM
Received Certificate of Value  1/29/2001 DONE
Received revised cert. of value minus the grading. KMM
Telephone call  1/26/2001 DONE
Received a telephone call from Al Turner *** They are going to apply for a grading and drainage permit. I faxed Al requirements for grading and drainage. I also repeated what was necessary to complete his plan submittal
1. Two copies of Structural calcs.
2. Two copies of stamped and signed mech. plans.
3. Two copies of stamped and signed plumb. plans.
4. Three copies of stamped and signed site plan.
5. Requirements for grading and drainage permit.
6. Revised cert. of value for building minus the grading.
I informed Al that I cannot start routing plans until above items are received.
KMM
Plan routing begun/NEW & ADDTN  1/25/2001 HOLD
Plans ACCEPTED BY PLAN TECH  1/25/2001 HOLD
See action for telephone call cated 1/26/01
Requires. 1. O & M manual
2. Two copies of struct. calcs.
3. Two copies of stamped and signed mechanical plans.
4. Two copies of stamped and signed plumbing plans.
5. Three copies of site plan stamped and signed.
Faxed and called Arden Johnson and faxed Richard Renshen. KMM
Received Certificate of Value  1/24/2001 DONE
Application received  1/24/2001  
Recd Pcfee & Taken To Pln CK     
Routing - PLAN CHECK4/25/2001