Case Summary (BLD) | | | 12/29/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/19/2008 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/31/2002 | | |
|
|
|
|
Fee Review-notes | 1/24/2001 | 1/24/2001 | 1/29/2002 | | DONE |
|
|
|
|
Permanent Occupancy | | 12/3/2001 | 12/3/2001 | | DONE |
|
|
|
|
BLD-Final | 11/30/2001 | 12/3/2001 | 12/3/2001 | A | PASS |
Tony Young
|
|
|
walter ###-####
ok for perm. occ. as long as others are ok 12/3/2001 11:43:36 AM
|
Permanent occupancy | | | 12/3/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8927 issued 12/3/01 to Rash, LLC aml
|
BLD-Final | 11/29/2001 | 11/29/2001 | 11/29/2001 | P | FAIL |
Tony Young
|
|
|
WALTER ###-####
waiting on elevator final from the state and electrical 11/29/2001 2:15:47 PM
|
FIRE-Final Inspection | 11/27/2001 | 11/28/2001 | 11/28/2001 | P | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Final | 11/20/2001 | 11/20/2001 | 11/19/2001 | P | PART |
Tony Young
|
|
|
Ok for temp occ.. CN issued for temp. glass, ada compliance on ramps, special inspection final letter and other agency signoffs.
|
FIRE-Final Inspection | 11/15/2001 | 11/15/2001 | 11/15/2001 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 11/15/2001 4:31:58 PM disregard the PASS on this date; temp occ approved pending fire control panel for detectors and elevator recall
|
BLD-Final | 11/14/2001 | 11/15/2001 | 11/15/2001 | P | FAIL |
Tony Young
|
|
|
WALTER ###-####
c/n posted 11/15/2001 4:36:14 PM
|
FIRE-Final Inspection | 11/14/2001 | 11/15/2001 | 11/15/2001 | A | PASS |
Rick Jackson
|
|
|
###-####
|
FIRE-Final Inspection | 11/14/2001 | 11/14/2001 | 11/14/2001 | P | FAIL |
Rick Jackson
|
|
|
Added by Inspector: 409 On 11/14/2001 4:05:41 PM elevator recall panel needed; need detector at smoke damper at stair enclosure
|
Code Occupancy Approval | 11/9/2001 | 11/8/2001 | 11/8/2001 | A | PASS |
Michael Garner
|
|
|
Added by Inspector: MSG On 11/9/2001 11:49:33 AM
|
BLD-Aging Inspection | 11/6/2001 | 11/6/2001 | 11/6/2001 | | PART |
Tony Young
|
|
|
wip 11/8/2001 9:25:47 AM
|
BLD-Framing/Rough-in | 9/5/2001 | 9/6/2001 | 9/6/2001 | P | PASS |
Tony Young
|
|
|
walter- ###-#### r/i
|
BLD-Energy code compliance | 8/28/2001 | 8/29/2001 | 8/29/2001 | P | PART |
Tony Young
|
|
|
###-####
ok to cover main level outside walls after tightening bolts, and ok to cover main level int. non bearing walls away from any mechanical work, (no mech. permit for ducting yet) 8/29/2001 3:17:40 PM
|
BLD-Framing/Rough-in | 8/27/2001 | 8/28/2001 | 8/28/2001 | P | PART |
Tony Young
|
|
|
###-####////c/n posted, ok to insulate unaffected areas, pending letter from eng. 8/28/2001 3:35:49 PM
|
BLD-Conference | 8/24/2001 | 8/27/2001 | 8/27/2001 | A | PASS |
Tony Young
|
|
|
for conf walter###-#### -per tony 10:00
met w/ greg w/ hummel, need structural to provide letter of compliance on as built, and talked about plan change drawings and alt. finish work, stairs, draft stopping, fire stops, etc 8/27/2001 11:03:36 AM
|
BLD-Framing/Rough-in | 8/23/2001 | 8/24/2001 | 8/24/2001 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/23/2001 at 17:32:14. Contact: ###-####.no mech. sign off, and need to meet arch. or strutural on job, go over special construction design 8/24/2001 2:50:35 PM
|
BLD-Framing/Rough-in | 8/20/2001 | 8/21/2001 | 8/21/2001 | A | PART |
Tony Young
|
|
|
###-#### PARTIAL
ok to drywall lid below vault area and elevator shaft and mech . room next to elevator, pending elec. sign off 8/21/2001 11:51:30 AM
|
BLD-Framing/Rough-in | 8/7/2001 | 8/8/2001 | 8/8/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 08/07/2001 at 16:50:00. Contact: ###-####. 8/8/2001 11:01:13 AM shear nialing on upper level ok to cover 8/8/2001 11:12:53 AM
|
BLD-Framing/Rough-in | 7/31/2001 | 8/1/2001 | 8/1/2001 | A | PART |
Tony Young
|
|
|
SHEAR WALL WALTER ###-####
shear ok on front areas, lower and some of upper 8/1/2001 11:32:45 AM
|
BLD-Concrete | 7/3/2001 | 7/5/2001 | 7/5/2001 | A | PART |
Tony Young
|
|
|
slab and a concrete wall Walter ###-####
poured already, s. i. was on site per walter 7/5/2001 10:51:40 AM
|
BLD-Foundation | 6/27/2001 | 6/28/2001 | 6/28/2001 | A | PART |
Tony Young
|
|
|
WAlter ###-####
pending special inspector report, already poured 6/28/2001 12:00:21 PM
|
BLD-Foundation | 6/25/2001 | 6/26/2001 | 6/26/2001 | P | PART |
Tony Young
|
|
|
Walter ###-####
already poured, confirmed w/ mti that they where there///pending report 6/26/2001 1:20:32 PM
|
BLD-Foundation | 6/20/2001 | 6/22/2001 | 6/22/2001 | A | PART |
Tony Young
|
|
|
###-####
already poured, pending s i report 6/22/2001 10:53:56 AM
|
BLD-Foundation | 6/20/2001 | 6/21/2001 | 6/21/2001 | A | PART |
Tony Young
|
|
|
slab and vertical walls ###-####
pending s. i. report 6/21/2001 10:50:16 AM
|
BLD-Foundation | 6/14/2001 | 6/15/2001 | 6/15/2001 | A | PASS |
Tony Young
|
|
|
###-####
pending s. i. report 6/15/2001 10:12:33 AM
|
BLD-Footing | 6/8/2001 | 6/11/2001 | 6/11/2001 | A | PART |
Dave Hannah
|
|
|
###-#### 6/11/2001 10:43:46 AM MTI is testing and inspecting 6/11/2001 10:44:37 AM
|
BLD-Foundation | 6/8/2001 | 6/11/2001 | 6/11/2001 | A | PART |
Dave Hannah
|
|
|
MTI inspected and tested 6/11/2001 10:45:13 AM
|
BLD-Other | 6/9/2001 | 6/11/2001 | 6/11/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 06/09/2001 at 19:02:30. Contact: ###-####.
|
FIRE-Supply Line Cover | 6/7/2001 | 6/8/2001 | 6/8/2001 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/07/2001 at 14:48:16. Contact: ###-####. work code entered by caller - no fire requested 6/8/2001 7:54:32 AM
|
BLD-Concrete | 6/4/2001 | 6/5/2001 | 6/5/2001 | A | PART |
Tom Arcoraci
|
|
|
###-#### wall PENDING SPEC INSP REPORTS 6/5/2001 11:02:21 AM
|
BLD-Concrete | 5/29/2001 | 5/30/2001 | 5/30/2001 | A | PART |
Tony Young
|
|
|
###-####
pend. report from s. i. 5/30/2001 11:49:20 AM
|
BLD-Concrete | 5/23/2001 | 5/24/2001 | 5/24/2001 | P | FAIL |
Tony Young
|
|
|
concrete wall walter ###-####
rebar above windows not per plan, pending s. i. report on fix 5/24/2001 1:47:50 PM
|
BLD-Concrete | 5/17/2001 | 5/18/2001 | 5/18/2001 | A | PART |
Tony Young
|
|
|
pouring at 8:00 Walter ###-####
pending s. i. report 5/18/2001 9:13:19 AM
|
BLD-Concrete | 5/11/2001 | 5/14/2001 | 5/14/2001 | A | PART |
Tony Young
|
|
|
###-#### wall
upper south retaining wall, ok pending s. i. report 5/14/2001 1:32:51 PM
|
BLD-Concrete | 5/7/2001 | 5/8/2001 | 5/8/2001 | P | PART |
Tony Young
|
|
|
pouring at 12:00 Walter ###-####
pending s.i. report 5/8/2001 1:58:30 PM
|
BLD-Concrete | 5/7/2001 | 5/8/2001 | 5/8/2001 | A | PART |
Tony Young
|
|
|
found. wall on top of retaining wall north 1/2, and found. wall around dumpster ok pending S. I. report 5/8/2001 10:49:24 AM
|
BLD-Foundation | 5/2/2001 | 5/3/2001 | 5/3/2001 | A | PART |
Tony Young
|
|
|
found-- walter- ###-####
looks ok, w/ verbal corrections, pending s. i. report 5/3/2001 10:34:37 AM
|
BLD-Concrete | 4/19/2001 | 4/19/2001 | 4/19/2001 | P | PART |
Tony Young
|
|
|
special inspectors on site walter ###-####
|
BLD-Concrete | 4/13/2001 | 4/16/2001 | 4/16/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/13/2001 at 14:02:38. Contact: ###-####.
Special on site, ftgs for dumpster area, and retaining wall 2nd half 4/16/2001 12:09:53 PM
|
BLD-Footing | 4/11/2001 | 4/12/2001 | 4/12/2001 | A | PART |
Tony Young
|
|
|
special inspector on site Walter ###-#### pouring at 10:30
pending s. i. report, retaining wall ftgs 4/12/2001 10:41:04 AM
|
BLD-Concrete | 4/5/2001 | 4/5/2001 | 4/5/2001 | P | PART |
Tony Young
|
|
|
walter-- ###-#### concrete
wall rebar inspection while panels are off, looks good so far, pending s. i. report 4/5/2001 3:12:04 PM
|
BLD-Footing | 4/3/2001 | 4/3/2001 | 4/3/2001 | P | PART |
Tony Young
|
|
|
pending s.i. report 4/3/2001 2:16:57 PM
|
BLD-Footing | 3/27/2001 | 3/28/2001 | 3/28/2001 | A | PART |
Tony Young
|
|
|
work in progress, talked w/ S. I. about corrections that need to be addressed also t/w job foreman. 1/2 of footing were poured when I got here and some corrections where not done yet, s.i. and I talked, corrections are being made now, general conformance should be met 3/28/2001 11:44:00 AM
|
BLD-Grading Inspection | 3/28/2001 | 3/28/2001 | 3/28/2001 | | PASS |
Rita DeYoung
|
|
|
Footing subgrade has been approved by the geotechnical engineer.
|
BLD-Footing | 3/27/2001 | 3/27/2001 | 3/27/2001 | P | PART |
Tony Young
|
|
|
###-#### late pm
pending special inspector report, work in progress, verbal corrections, need to go back and verify 3/27/2001 2:56:30 PM
|
(F) Reprint permit | | | 3/19/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/16/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/13/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/13/2001 | | DONE |
|
|
|
Scott Straubhar ###-####
|
Inspection Record Card- Bld | | | 3/13/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/13/2001 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 1/25/2001 | | 3/13/2001 | | PASS |
Mike Otto
|
|
|
3/13/2001 10:41:07 MLO - activity updated through activity BLDA022 from case BLD01-00187.
|
Routing Off Site - STRUCTURAL | 3/9/2001 | | 3/12/2001 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/9/2001 | | DONE |
|
|
|
called Tom Poremba at AHJ regarding any possible corrected plan sheets from dicussion with consulting engineer. He has corrected one sheet. AHJ to provide two copies of the corrected plan sheet to the Building Dept. to be inserted into the approved plans. MLO
|
Plan resubmittals received | | | 3/9/2001 | | DONE |
|
|
|
Received two copies of revised sheet S2.1 and one copy of additional calculations for plan review comment #3. Routed to Mike O. KMM PLANS RECEIVED BY M. OTTO ON MONDAY 3-12-01.
|
Routing - PUBLIC WORKS | 3/7/2001 | | 3/8/2001 | | PASS |
|
|
|
|
Telephone call | | | 3/8/2001 | | DONE |
|
|
|
TALKED TO JESSICA TO VERIFY PLANS ARE READY & NEED ACHD
|
Routing - FIRE | 3/6/2001 | | 3/7/2001 | | PASS |
|
|
|
Route to PW when out of fire. KMM
|
Routing - PUBLIC WORKS | 3/1/2001 | | 3/6/2001 | | FAIL |
|
|
|
Requires additional drainage information per Brian Murphy. KMM
|
Routing Off Site - STRUCTURAL | 2/28/2001 | | 3/5/2001 | | FAIL |
|
|
|
sent to outside eng. plans resubmitted. on 2/23/01 KMM received email from consulting engineer that still had problem with wall studs at stair spanning 32.5 feet. Consulting engineer has directly contacted EOR regarding correction. MLO
|
Plan resubmittals received | | | 2/23/2001 | | DONE |
|
|
|
Received plan resubmittals from Hummel Architects, plus small documents, forwarded same to Mike Otto. 2/23/01 DAR
|
Routing Off Site - STRUCTURAL | 1/25/2001 | | 2/20/2001 | | FAIL |
|
|
|
Sent plans to consultanting Engineer via PDQ. 1/25/01 DAR Corrections mailed and faxed to architect.
|
Plan resubmittals requested | | | 2/20/2001 | | FAIL |
|
|
|
structural corrections
|
Routing - PLAN CHECK | 2/20/2001 | | 2/20/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/16/2001 | | DONE |
|
|
|
RECEIVED 2 COPIES OF REVISED DRAWING SHEETS AZ.01-A2.03-A6.01 AND A8.0 TOOK TO MIKE OTTO 2/16/2001/PE
|
Plan Review Completed(1st rev) | | | 2/12/2001 | | FAIL |
|
|
|
|
Routing - FIRE | 2/7/2001 | | 2/12/2001 | | FAIL |
|
|
|
fireflow vs sprinklers?
|
Additional plans submitted | | | 2/8/2001 | | DONE |
|
|
|
Received additional plans from ROMAR Electric, all electrical plans three sets of sheets E1.0, E2.0, E2.1, E2.2, E2.3 and E2.4 , forwarded same to Mike Otto. 2/8/01 DAR
|
Plan resubmittals requested | | | 2/7/2001 | | FAIL |
|
|
|
UBC corrections
|
Routing - PLAN CHECK | 2/1/2001 | | 2/7/2001 | | FAIL |
|
|
|
corrections faxed and mailed to architect. MLO
|
Routing - PLUMBING | 1/31/2001 | | 2/1/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 1/25/2001 | | 1/31/2001 | | FAIL |
|
|
|
Requires more information for the drainage plan per Brian Murphy. 1/31/01 DAR
|
Routing - PLANNING | 1/31/2001 | | 1/31/2001 | | PASS |
|
|
|
Approve per DRH00-156 & DRH01-13
|
Plans ACCEPTED BY PLAN TECH | | | 1/25/2001 | | DONE |
|
|
|
|
Application received | | | 1/24/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/25/2001 | | | | DONE |
|
|
|
Mailed drainage caculations to consultanting engineer via U.S. MAIL 1/25/01
|