Fee Review-notes | 1/30/2001 | 1/30/2001 | 12/16/2002 | | DONE |
|
|
|
3/9/01 bld01-00286 was charged a plancheck...I moved fees to this permit...lh 10/17--they totaled value on one permit, there are total of 5. applied to permits. bld01-00220,02384,02386 lh
|
BLD-Final | 1/11/2002 | 1/11/2002 | 1/11/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 1/11/2002 1:50:47 PM Ok perm oc. cards delivered tto store this day.1/11/2002 1:57:14 PM 1/11/2002 2:02:09 PM
|
Letter of compliance | | | 1/2/2002 | | DONE |
|
|
|
Letter of Compliance #22098 issued 1-2-02.
|
FIRE-Final Inspection | 1/15/2002 | 11/18/2001 | 11/18/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 1/15/2002 12:26:58 PM Fire life/safety finaled
|
BLD-Final | 11/9/2001 | 11/9/2001 | 11/9/2001 | A | FAIL |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 11/9/2001 1:59:46 PM . Needs Fire/Life Safety, Zoning, ACHD . And non- compliance items on final special inspection report approved by the project engineer. See permit #bld01-02385 for Denver mattres Tennant improvement. 11/9/2001 2:05:19 PM
|
BLD-Final | 11/9/2001 | 11/9/2001 | 11/9/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 11/9/2001 4:01:08 PM ok temp oc , see am inspection history for addn info. 11/9/2001 4:20:33 PM
|
Temporary occupancy | | | 11/9/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4636 issued 11-9-01 to Furniture Row.
|
Code Occupancy Approval | | | 11/9/2001 | | DONE |
|
|
|
SIGNED OCCUPANCY, STILL NEEDS SMALL AMOUNT OF LANDSCAPE BY COLE ROAD.
|
BLD-Final | 11/5/2001 | 11/6/2001 | 11/6/2001 | A | NR |
Russ Owen
|
|
|
###-#### ELDEN NEEDS TEMP OCCUPANCY
|
(F) Reprint permit | | | 10/31/2001 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 9/19/2001 | 9/20/2001 | 9/20/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/19/2001 at 11:44:04. Contact: ###-####. ok to cover baths in center and west bld 9/20/2001 9:43:55 AM
|
BLD-Framing/Rough-in | 8/28/2001 | 8/28/2001 | 8/28/2001 | P | PART |
Russ Owen
|
|
|
craig-- ###-####--fr insp ok to cover areas with-out plumbing. 8/28/2001 5:08:16 PM
|
Override - Parcel Holds | | | 8/28/2001 | | |
|
|
|
|
BLD-Conference | 8/20/2001 | 8/20/2001 | 8/20/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 8/20/2001 3:53:30 PM
|
BLD-Framing/Rough-in | 8/10/2001 | 8/10/2001 | 8/10/2001 | P | PART |
Russ Owen
|
|
|
FR INSP- DIRK - ###-#### . NOTE:needs a tennant improvement permit, schell only. 8/13/2001 12:21:49 PM
|
BLD-Foundation | 6/27/2001 | 6/27/2001 | 6/27/2001 | P | PART |
Russ Owen
|
|
|
###-#### subject to si. 6/27/2001 3:24:21 PM
|
BLD-Footing | 6/25/2001 | 6/26/2001 | 6/26/2001 | A | PART |
Russ Owen
|
|
|
corey ###-#### special inspection reports on site. 6/26/2001 11:56:16 AM
|
BLD-Concrete | 6/14/2001 | 6/15/2001 | 6/15/2001 | A | PART |
Russ Owen
|
|
|
###-#### subject to s-i. 1/15/2002 4:06:29 PM
|
BLD-Foundation | 6/13/2001 | 6/14/2001 | 6/14/2001 | A | PART |
Russ Owen
|
|
|
stem wall eric ###-#### ok subject to special insp. 1/14/2002 12:27:25 PM
|
BLD-Foundation | 6/13/2001 | 6/13/2001 | 6/13/2001 | P | PART |
Russ Owen
|
|
|
corey ###-####
|
BLD-Foundation | 6/11/2001 | 6/11/2001 | 6/11/2001 | P | PASS |
Dave Hannah
|
|
|
corey ###-#### MTI on site testing and inspecting 6/11/2001 1:50:12 PM
|
BLD-Footing | 6/7/2001 | 6/8/2001 | 6/8/2001 | A | PART |
Russ Owen
|
|
|
pour at 10:30= cory ###-#### subject to s-i. 1/8/2002 4:01:02 PM
|
BLD-Footing | 6/6/2001 | 6/6/2001 | 6/6/2001 | P | PART |
Russ Owen
|
|
|
cory ###-#### s-i required insp. 1/6/2002 5:14:33 PM
|
BLD-Footing | 6/1/2001 | 6/1/2001 | 6/1/2001 | P | PART |
Russ Owen
|
|
|
pouring at 1:00 corey ###-#### subject to ,mti inspection. 1/4/2002 9:38:09 AM
|
BLD-Footing | 5/30/2001 | 5/30/2001 | 5/30/2001 | P | PART |
Russ Owen
|
|
|
pouring at 2 ###-#### final pour footings. 12/30/2001 4:31:21 PM
|
BLD-Framing/Rough-in | 5/30/2001 | 5/30/2001 | 5/30/2001 | P | PART |
Russ Owen
|
|
|
fr insp --dirk ###-#### interior non bearing walls and east to west tall walls ok to cover. 12/30/2001 4:31:00 PM
|
BLD-Foundation | 5/29/2001 | 5/29/2001 | 5/29/2001 | P | PART |
Russ Owen
|
|
|
###-#### inspection will be performed by mti. 12/30/2001 10:11:57 AM
|
BLD-Footing | 5/24/2001 | 5/24/2001 | 5/24/2001 | P | PART |
Jim Storey
|
|
|
###-#### pour 3:30 pending rfi's and special insp report bach time on waiting truck in qustion. 5/24/2001 4:14:11 PM
|
BLD-Footing | 5/22/2001 | 5/22/2001 | 5/22/2001 | P | PART |
Russ Owen
|
|
|
Cory ###-#### north and east footing ok also inspections by special inspector required for design also cmu wall above went over requirements with contractor. MTI will be contracted. 12/22/2001 2:51:07 PM
|
Override - Parcel Holds | | | 5/17/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/17/2001 | | DONE |
|
|
|
|
Telephone call | | | 5/10/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (MLO) | 1/31/2001 | | 5/9/2001 | | PASS |
Mike Otto
|
|
|
5/9/2001 08:56:56 MLO - activity updated through activity BLDA022 from case BLD01-00220.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 5/9/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/9/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/9/2001 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/2/2001 | | 5/8/2001 | | PASS |
|
|
|
Sent structural resubs via PDQ , 5/2/01
|
Plan resubmittals received | | | 5/2/2001 | | DONE |
|
|
|
Received three copies of revised sheets S1.1R4, S1.4R4, S2.2R4. Two copies of line item response and two copies of additional calculations. Routed to Mike O. KMM
|
Received Certificate of Value | | | 5/1/2001 | | DONE |
|
|
|
Received final cert. of value. Project value $1,434,848.00 Routed to Mike O. KMM
|
Routing - PUBLIC WORKS | 4/20/2001 | | 4/30/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 4/17/2001 | | 4/20/2001 | | PASS |
|
|
|
Approve per DRH01-1, and per revised plans on file.
|
Plan resubmittals received | | | 4/19/2001 | | DONE |
|
|
|
Received one copy of revised sheets C1.1, C1.2, C4.1, C4.2. One copy of Ada County Highway requirment list. Routed to Richard Dailey. KMM
Richard brought plan back to me and I routed to Mike O. KMM
|
Routing Off Site - STRUCTURAL | 4/3/2001 | | 4/12/2001 | | FAIL |
|
|
|
Routed resubmitted calcs. and plans of 4/3/01 to outside eng. via PDQ. KMM Corrections faxed and mailed to architect
|
Routing - FIRE | 4/10/2001 | | 4/12/2001 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 4/12/2001 | | FAIL |
|
|
|
additional structural corrections
|
Routing - PLUMBING | 4/4/2001 | | 4/9/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/3/2001 | | 4/4/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/30/2001 | | 4/3/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/3/2001 | | DONE |
|
|
|
Received nine copies of revised sheets of plans (full sets), two copies of additional structural information in response to city review comments. Two copies of response to building department plan review comments and two copies of response to plumbing plan review dated 2/22/01. Put all with plans. Routed two copies to Mike Otto and one copy to outside eng. Put remaining six copies of plans in my hold box. KMM
|
Plan resubmittals received | | | 3/28/2001 | | DONE |
|
|
|
Received two copies of revised sheets C1.1R2, C1.2R2, C1.3R2, C2.1R2, C2.2R2, C3.1R2. Routed to Mike Otto. KMM
|
Plan Review Completed(1st rev) | | | 3/12/2001 | | FAIL |
|
|
|
|
Routing - FIRE | 3/6/2001 | | 3/12/2001 | | FAIL |
|
|
|
need response to grading permit items 1-4
|
Routing - PLAN CHECK | 3/6/2001 | | 3/6/2001 | | FAIL |
|
|
|
corrections sent to architect. MLO
|
Plan resubmittals requested | | | 3/6/2001 | | FAIL |
|
|
|
UBC and Structural corrections
|
Routing - PLAN CHECK | 2/22/2001 | | 3/5/2001 | | PEND |
|
|
|
plan review put on hold due to other priority projects.
|
Routing - PLUMBING | 2/13/2001 | | 2/22/2001 | | FAIL |
|
|
|
|
Routing - PLANNING | 2/12/2001 | | 2/13/2001 | | FAIL |
|
|
|
Plans do not comply with Design Review conditions of approval, DRH01-1, particularly the exterior elevations and some landscape areas.
|
Plan resubmittals received | | | 2/12/2001 | | DONE |
|
|
|
Received two sets of resubmittals from Eldon sheets D1.1 and D1.2, forwarded same to Mike Otto. 2/12/01 DAR
|
Routing - PUBLIC WORKS | 2/8/2001 | | 2/12/2001 | | FAIL |
|
|
|
Requires drainage plan revision per Brian Murphy. 2/12/01 DAR
|
Routing - PLAN CHECK | 2/7/2001 | | 2/8/2001 | | FAIL |
|
|
|
For demo permit. 2/7/01 DAR Need revised plans showing only non-bearing interior partitions to be removed. No other demo work is authorized at this time. Sent fax to Eldon Adams. Plans to resume circulation. MLO
|
Routing Off Site - STRUCTURAL | 1/31/2001 | | 2/8/2001 | | FAIL |
|
|
|
Sent plans and caculations to consultanting engineer via PDQ. 1/31/01 DAR corrections faxed to Eldon Adams.
|
Routing - PLANNING | 1/31/2001 | | 2/7/2001 | | FAIL |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/31/2001 | | DONE |
|
|
|
Advised Eldon Adams that a O & M manual was required for the drainage plan. He is working on it. Also waiting for an application for grading and drainage permit and a certificate of value for a Demo permit. 1/31/01 DAR
|
Plan assigned to (MYS) | 1/30/2001 | 1/30/2001 | 1/30/2001 | | DONE |
Marlene Southard
|
|
|
|
Application received | | | 1/30/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/30/2001 | | DONE |
|
|
|
|