Information based on query as of Saturday, August 17, 2024.
Permit Information
Permit NumberBLD01-00255
StatusFinaled
Name VIKEN OFFICE BLDG
Site Address 15 N ORCHARD
Project NameVIKEN OFFICE BUILDING
Customer Number 
ePlanReviewNo
Description
To install ceiling and finish 1,200 sq.ft. of the interior of this building for occupancy. All constructionper the approved plans and attached comments in permit BLD 01-00254. MJP
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  3/12/2002 DONE
Fee Review-notes2/12/20012/12/20011/29/2002 DONE
BLD-Final10/12/200110/12/200110/12/2001PPASS
DetailsTom Arcoraci
###-#### ROY ok for perm occ 10/12/2001 3:13:46 PM
Letter of compliance  10/12/2001 DONE
Letter of Compliance #20918 issued 10-12-01.
BLD-Final9/17/20019/18/20019/18/2001APART
DetailsTom Arcoraci
###-####
FIRE-Final Inspection8/31/20018/31/20018/31/2001APASS
DetailsRick Jackson
Added by Inspector: 409 On 8/31/2001 9:15:58 AM
BLD-Conference8/23/20018/24/20018/24/2001APASS
DetailsTom Arcoraci
###-#### FOR CONF
BLD-Aging Inspection8/23/20018/23/20018/23/2001 PART
DetailsTom Arcoraci
wip 8/23/2001 1:52:16 AM
Issue PAID IN FULL permit  5/24/2001 DONE
Routing - PLAN CHECK5/22/2001 5/23/2001 DONE
Plan Reviewer's activity  5/23/2001  
Print Pending Permit.LaserJet4  5/23/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/23/2001 DONE
Case Summary (BLD)  5/23/2001 DONE
Inspection Record Card- Bld  5/23/2001 DONE
Print Occupancy Form  5/23/2001 DONE
Telephone call  5/23/2001 DONE
Plan assigned to (M_P)2/13/2001 5/23/2001 PASS
DetailsMike Phillips
5/23/2001 13:40:41 M_P - activity updated through activity BLDA022 from case BLD01-00255.
Routing - PUBLIC WORKS5/17/2001 5/22/2001 PASS
Routing - PLAN CHECK4/25/2001 5/17/2001  
Plan resubmittals received  4/24/2001 DONE
Received three sets of resubmittals from Jerrie Wolfe and Associates forwarded same to Richard Dailey. 4/24/01 DAR
Routing - FIRE4/20/2001 4/24/2001 PASS
Routing - PUBLIC WORKS4/16/2001 4/18/2001 FAIL
Requires drainage plan revision per Brian Murphy. 4/18/01 DAR
Plan Review Completed(1st rev)  3/21/2001 FAIL
Routing - FIRE3/19/2001 3/21/2001 FAIL
pending decision on hydrant location. Existing Fire Hydrant location and access looks acceptable on plans per the UFC/05/31/01, (JWA)
Plan Reviewer's activity  3/19/2001 FAIL
Additional information required for further review.
Print Pending Permit.LaserJet4  3/19/2001  
Routing - PLAN CHECK2/28/2001 3/19/2001 FAIL
Routing - PLUMBING2/26/2001 2/28/2001 FAIL
Routing - PLANNING2/20/2001 2/23/2001 PASS
Approved per DRH00-100.
Routing - PUBLIC WORKS2/13/2001 2/16/2001 FAIL
Plans ACCEPTED BY PLAN TECH  2/13/2001 DONE
Plan assigned to (MYS)2/12/20012/12/20012/12/2001 DONE
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  2/12/2001 DONE
Application received  2/5/2001  
Routing - PLAN CHECK3/21/2001    
Routing - PLAN CHECK4/18/2001