Fee Review-notes | 2/5/2001 | 2/5/2001 | 5/25/2001 | | DONE |
|
|
|
no mech
|
BLD-Final | 3/20/2001 | 3/20/2001 | 3/20/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 03/20/2001 at 07:10:04. Contact: ###-####. OK for perm Occ. 3/20/2001 2:03:11 PM
|
FIRE-Final Inspection | 3/20/2001 | 3/20/2001 | 3/20/2001 | A | PASS |
Joe Tawney
|
|
|
. 3/20/2001 12:32:34 PM Reinsp OK for permanant occupancy 3/20/2001 12:32:56 PM
|
DOC - Permit Finaled | 3/20/2001 | 3/20/2001 | 3/20/2001 | P | PASS |
Jim Sly
|
|
|
Added by Inspector: 316 On 3/20/2001 2:01:55 PM
|
Letter of compliance | | | 3/20/2001 | | DONE |
|
|
|
Letter of Compliance #21369 issued 3-21-01.
|
FIRE-Final Inspection | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail Fire ext 3/20/2001 7:53:02 AM
|
BLD-Final | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | NR |
Jim Sly
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/1/2001 | 3/2/2001 | 3/2/2001 | P | PASS |
Jim Sly
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 3/2/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/28/2001 | | 3/1/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/2001 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/1/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/1/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/1/2001 | | DONE |
|
|
|
called permit ready
|
Plan assigned to (JCB) | 2/7/2001 | | 3/1/2001 | | PASS |
Jason Blais
|
|
|
3/1/2001 14:06:49 JCB - activity updated through activity BLDA022 from case BLD01-00260.
|
Routing - PLAN CHECK | 2/23/2001 | | 2/28/2001 | | PEND |
|
|
|
One item still needs to be addressed. Waiting for item.
|
Plan resubmittals received | | | 2/28/2001 | | DONE |
|
|
|
Received two copies of reviesd sheets 1 of 2, 2 of 2, one copy of response letter. Routed to Jason B. KMM
|
Plan Review Completed(1st rev) | | | 2/23/2001 | | FAIL |
|
|
|
|
Routing - FIRE | 2/21/2001 | | 2/23/2001 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 2/21/2001 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 2/7/2001 | | 2/21/2001 | | FAIL |
|
|
|
Plan review report sent and faxed to designer. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Pending Assignment by MYS | 2/7/2001 | | 2/7/2001 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/6/2001 | | DONE |
|
|
|
|
Application received | | | 2/5/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|