BLD-Final | 6/27/2001 | 6/29/2001 | 6/29/2001 | P | PASS |
Tony Young
|
|
|
###-####
|
BLD-Grading Inspection | 6/29/2001 | 6/29/2001 | 6/29/2001 | | BOND |
Rita DeYoung
|
|
|
Rough grading and drainage are complete. Fine grading and revegetation are not. For this the engineer has recommended a $500.00 bond. When this is submitted the grading and drainage are conditionally approved.
|
DOC - Permit Finaled | 6/29/2001 | 6/29/2001 | 6/29/2001 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 6/29/2001 1:41:50 PM
|
BLD-Framing/Rough-in | 5/3/2001 | 5/4/2001 | 5/4/2001 | A | PASS |
Tony Young
|
|
|
shear nail insp Buster ###-####
|
CHANGE STATUS TO (ISS) | | | 5/4/2001 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 4/30/2001 | 5/1/2001 | 5/1/2001 | A | PASS |
Tony Young
|
|
|
FR -RE-INSP -- ###-#### BUSTER OFFICE ###-####
ok to cover 5/1/2001 1:57:18 PM
|
BLD-Energy code compliance | 4/27/2001 | 4/30/2001 | 4/30/2001 | P | PART |
Tony Young
|
|
|
buster ###-#### office ###-####
c/n posted, ok to rock unaffected areas 4/30/2001 1:28:48 PM
|
BLD-Energy code compliance | 4/25/2001 | 4/26/2001 | 4/26/2001 | P | PART |
Tony Young
|
|
|
BUSTER ###-####
energy seal ok only 4/26/2001 2:48:25 PM
|
BLD-Framing/Rough-in | 4/25/2001 | 4/26/2001 | 4/26/2001 | P | PART |
Tony Young
|
|
|
BUSTER ###-####
c/n posted, ok to insulate 4/26/2001 2:47:58 PM
|
BLD-Framing/Rough-in | 4/18/2001 | 4/18/2001 | 4/18/2001 | P | PART |
Tony Young
|
|
|
###-#### or ###-#### shear wall
ext. shear ok 4/18/2001 3:09:07 PM
|
BLD-Foundation | 3/13/2001 | 3/14/2001 | 3/14/2001 | A | PART |
Tony Young
|
|
|
###-####
|
BLD-Foundation | 3/13/2001 | 3/13/2001 | 3/13/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/13/2001 3:48:20 PM hold downs subject to insp at frame...
|
BLD-Footing | 3/9/2001 | 3/12/2001 | 3/12/2001 | P | PASS |
Carl Dependahl
|
|
|
###-#### cell ###-#### office Buster; ok, bar in place 3/12/2001 3:31:21 PM
|
Override - Parcel Holds | | | 3/9/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/9/2001 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 2/15/2001 | 2/15/2001 | 3/8/2001 | | PASS |
Dan Overy
|
|
|
3/8/2001 10:36:22 DJO - activity updated through activity BLDA022 from case BLD01-00272.
|
Plan Reviewer's activity | | | 3/8/2001 | | DONE |
|
|
|
received stamped memo from AHJ indicating loads accumulated at garage wing wall will be distributed through stem wall and into continuous footing. have red-lined and attached other information to plans. due to the excessive amount of red-lining and that only one stamped foundation plan was submitted, only one approved set of plans will be issued. future submittals will be screened closer for compliance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/8/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/8/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/8/2001 | | DONE |
|
|
|
called permit ready
|
Plan Reviewer's activity | | | 2/28/2001 | | PEND |
|
|
|
02-27-2001 received engineering for overheight walls. spoke with ram-tech about other areas of concern. will submit addendums when done.
|
Plans ACCEPTED BY PLAN CHECK | | | 2/15/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 2/15/2001 | | PEND |
|
|
|
started initial review late afternoon on 02-14-2001
|
Plan Reviewer's activity | | | 2/15/2001 | | PEND |
|
|
|
called ram-tech. problem areas. missing beam over furnace compartment, need engineering for over height bearing walls, garage stem walls/footings undersized, interior shear to be specified, roof frame detail for eave overhang at side of garage and calcs on exterior post footings. will issue permit when issues are resolved.
|
Case Summary (BLD) | | | 2/15/2001 | | PEND |
|
|
|
|
Plan Review Report | | | 2/15/2001 | | PEND |
|
|
|
|
Routing - PLANNING | 2/8/2001 | 2/8/2001 | 2/12/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 2/6/2001 | 2/6/2001 | 2/8/2001 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3 on 2/8/01. TOOK TO TERRY RECORDS 2/6/2001/PE
|
Routing - PUBLIC WORKS | 2/6/2001 | 2/6/2001 | 2/8/2001 | | PASS |
|
|
|
|
Application received | | | 2/6/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 2/12/2001 | 2/12/2001 | | | PEND |
|
|
|
|