BLD-Final | 4/11/2001 | 4/12/2001 | 4/12/2001 | A | PASS |
Jim Sly
|
|
|
###-#### C/C issued. 4/12/2001 10:23:14 AM
|
DOC - Permit Finaled | 4/12/2001 | 4/12/2001 | 4/12/2001 | A | PASS |
Jim Sly
|
|
|
Added by Inspector: 316 On 4/12/2001 10:22:52 AM
|
BLD-Final | 4/10/2001 | 4/11/2001 | 4/11/2001 | A | FAIL |
Dave Hannah
|
|
|
jp ###-#### need to seal all the boxes on ext walls 4/11/2001 10:55:47 AM
|
BLD-Energy code compliance | 3/5/2001 | 3/5/2001 | 3/5/2001 | P | PASS |
Jim Sly
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/2/2001 | 3/2/2001 | 3/2/2001 | P | PASS |
Jim Sly
|
|
|
fr insp--j p ###-####
|
BLD-Framing/Rough-in | 2/27/2001 | 2/28/2001 | 2/28/2001 | A | PART |
Jim Sly
|
|
|
###-#### Shear OK. 2/28/2001 12:10:05 PM
|
BLD-Footing | 2/15/2001 | 2/15/2001 | 2/15/2001 | P | NR |
Dave Hannah
|
|
|
FT INSP -- ###-####- TONY no one on site ftgs have been excavated but no forms on site 2/15/2001 3:53:06 PM
|
Issue PAID IN FULL permit | | | 2/15/2001 | | DONE |
|
|
|
|
Plan assigned to (DJO) | 2/12/2001 | 2/12/2001 | 2/14/2001 | | PASS |
Dan Overy
|
|
|
2/14/2001 16:05:47 DJO - activity updated through activity BLDA022 from case BLD01-00289.
|
Plan Reviewer's activity | | | 2/14/2001 | | DONE |
|
|
|
received revised plans which still did not clarify roof framing. have red-lined.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2001 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/14/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 2/14/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/14/2001 | | DONE |
|
|
|
|
Telephone call | | | 2/14/2001 | | DONE |
|
|
|
talked to chuck ###-####
|
Plan Reviewer's activity | | | 2/12/2001 | | PEND |
|
|
|
elevations do not match each other, roof framing is not clear, shear cone notes to be deleated, brace wall panel need relocated, square footages incorrect, plans are not to scale. initial review started 2-9-2001. called tom withworth with hubble homes and left message friday about problems with plans.. received return phone call 2-12-2001 around 9:00 a.m. and discussed situation with tom witworth. new plans will be submitted, with all corrections, and will not be submitted for a master.
|
Plans ACCEPTED BY PLAN CHECK | | | 2/12/2001 | | |
|
|
|
|
Routing - PUBLIC WORKS | 2/7/2001 | 2/7/2001 | 2/8/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 2/7/2001 | 2/7/2001 | 2/8/2001 | | PASS |
|
|
|
|
Application received | | | 2/7/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 2/8/2001 | 2/8/2001 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 2/7/2001 | | | | PEND |
Dan Overy
|
|
|
|