Fee Review-notes | 2/7/2001 | 2/7/2001 | 1/18/2002 | | DONE |
|
|
|
|
Letter of compliance | | | 8/23/2001 | | DONE |
|
|
|
Letter of Compliance #21728 issued 8-23-01.
|
BLD-Final | 8/22/2001 | 8/22/2001 | 8/22/2001 | P | PASS |
Tom Arcoraci
|
|
|
###-#### dale please call first ok for perm occ 8/22/2001 2:24:25 AM
|
BLD-Aging Inspection | 8/20/2001 | 8/20/2001 | 8/20/2001 | | PASS |
Tom Arcoraci
|
|
|
outstanding c/notice on landing 8/19/2001 8:20:26 PM
|
FIRE-Final Inspection | 6/15/2001 | 6/19/2001 | 6/19/2001 | A | PASS |
Joe Tawney
|
|
|
Final Pass Ok for cert of completion 6/19/2001 2:22:37 PM
|
BLD-Final | 6/15/2001 | 6/19/2001 | 6/19/2001 | P | FAIL |
Tom Arcoraci
|
|
|
Jared ###-#### need new landing 6/19/2001 2:00:42 AM
|
BLD-Final | 6/13/2001 | 6/14/2001 | 6/14/2001 | A | NR |
Tom Arcoraci
|
|
|
Jerard ###-####
|
BLD-Conference | 5/16/2001 | 5/16/2001 | 5/16/2001 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 5/16/2001 10:06:28 AM
|
BLD-Framing/Rough-in | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | PASS |
Tom Arcoraci
|
|
|
Added by Inspector: 408 On 5/16/2001 3:30:55 PM ok to cover shaft
|
BLD-Framing/Rough-in | 5/15/2001 | 5/15/2001 | 5/15/2001 | P | FAIL |
Tom Arcoraci
|
|
|
mike ###-#### cn posted for shaft 5/15/2001 3:40:23 PM
|
BLD-Framing/Rough-in | 5/9/2001 | 5/9/2001 | 5/9/2001 | P | NR |
Tom Arcoraci
|
|
|
###-#### no plans 5/9/2001 3:06:44 PM
|
BLD-Framing/Rough-in | 5/4/2001 | 5/4/2001 | 5/4/2001 | P | PART |
Tom Arcoraci
|
|
|
###-#### wip 5/4/2001 1:32:55 PM
|
Issue PAID IN FULL permit | | | 4/30/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/16/2001 | | 3/19/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/19/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/19/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/19/2001 | | DONE |
|
|
|
CALLED PERMIT READY
|
Plan assigned to (MLO) | 2/12/2001 | | 3/19/2001 | | PASS |
Mike Otto
|
|
|
3/19/2001 10:07:58 MLO - activity updated through activity BLDA022 from case BLD01-00292.
|
Plan resubmittals received | | | 3/15/2001 | | DONE |
|
|
|
Received plan resubmittals from HSA Architects, two sets and small documents, forwarded same to Mike Otto after 4:30 PM. 3/15/03 DAR
|
Plan Review Completed(1st rev) | | | 3/2/2001 | | FAIL |
|
|
|
failed bldg review
|
Routing - FIRE | 2/27/2001 | | 3/2/2001 | | PASS |
|
|
|
Approved without comments
|
Plan resubmittals requested | | | 2/27/2001 | | FAIL |
|
|
|
UBC corrections
|
Routing - PLAN CHECK | 2/12/2001 | | 2/27/2001 | | FAIL |
|
|
|
corrections mailed and faxed to architect
|
Pending Assignment by MYS | 2/12/2001 | | 2/12/2001 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/8/2001 | | DONE |
|
|
|
Requested resubmittal of new application form by fax from Joe Presher. 2/8/01 DAR
|
Application received | | | 2/7/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/7/2001 | | DONE |
|
|
|
|