BLD-Final | 4/17/2001 | 4/18/2001 | 4/18/2001 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 04/17/2001 at 17:17:24. Contact: ###-####.
|
DOC - Permit Finaled | 4/18/2001 | 4/18/2001 | 4/18/2001 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 4/18/2001 2:24:07 PM
|
BLD-Final | 4/17/2001 | 4/17/2001 | 4/17/2001 | P | FAIL |
Dave Hannah
|
|
|
JP ###-#### c/n on site 4/17/2001 2:04:17 PM
|
BLD-Energy code compliance | 3/15/2001 | 3/15/2001 | 3/15/2001 | P | PASS |
Jim Sly
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/14/2001 | 3/14/2001 | 3/14/2001 | P | PASS |
Jim Sly
|
|
|
jp ###-#### fr
|
BLD-Framing/Rough-in | 3/12/2001 | 3/12/2001 | 3/12/2001 | P | PART |
Jim Sly
|
|
|
SHEAR Shear wall OK. 3/12/2001 5:37:11 PM
|
BLD-Foundation | 2/22/2001 | 2/22/2001 | 2/22/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/22/2001 at 06:50:39. Contact: .
|
BLD-Footing | 2/21/2001 | 2/21/2001 | 2/21/2001 | P | PART |
Jim Sly
|
|
|
###-####
|
Inspection Record Card- Bld | | | 2/20/2001 | | DONE |
|
|
|
|
Telephone call | | | 2/20/2001 | | DONE |
|
|
|
called left message w/shawn gave dollar amount
|
Issue PAID IN FULL permit | | | 2/20/2001 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 2/15/2001 | | 2/16/2001 | | PASS |
Perry Paine
|
|
|
2/16/2001 16:18:37 PEP - activity updated through activity BLDA022 from case BLD01-00314.
|
Inspector's copy Bld permit | | | 2/16/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 2/16/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/2001 | | DONE |
|
|
|
|
Pending Assignment by DJO | 2/9/2001 | | 2/15/2001 | | DONE |
Dan Overy
|
|
|
2/15/2001 11:55:32 PEP - activity updated through activity BLDA176 from case BLD01-00314.
|
Routing - PUBLIC WORKS | 2/9/2001 | 2/9/2001 | 2/12/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 2/9/2001 | 2/9/2001 | 2/12/2001 | | PASS |
|
|
|
|
Application received | | | 2/9/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 2/12/2001 | 2/12/2001 | | | PEND |
|
|
|
|