BLD-Final | 4/26/2001 | 4/26/2001 | 4/26/2001 | P | PASS |
Dave Hannah
|
|
|
###-####
|
DOC - Permit Finaled | 4/26/2001 | 4/26/2001 | 4/26/2001 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 4/26/2001 2:19:24 PM
|
BLD-Final | 4/24/2001 | 4/24/2001 | 4/24/2001 | P | FAIL |
Dave Hannah
|
|
|
###-#### c/n on site 4/24/2001 2:54:08 PM
|
BLD-Framing/Rough-in | 4/2/2001 | 4/3/2001 | 4/3/2001 | A | NR |
Dave Hannah
|
|
|
###-#### need pluming roughin finished 4/3/2001 10:53:05 AM
|
BLD-Energy code compliance | 4/2/2001 | 4/3/2001 | 4/3/2001 | P | CANC |
Dave Hannah
|
|
|
###-####
|
BLD-Framing/Rough-in | 4/3/2001 | 4/3/2001 | 4/3/2001 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 4/3/2001 2:55:05 PM
|
BLD-Energy code compliance | 4/3/2001 | 4/3/2001 | 4/3/2001 | P | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 4/3/2001 4:49:49 PM
|
BLD-Framing/Rough-in | 3/30/2001 | 4/2/2001 | 4/2/2001 | P | PASS |
Dave Hannah
|
|
|
###-#### shear wall ext ok to cover 4/2/2001 2:45:37 PM
|
BLD-Foundation | 3/22/2001 | 3/22/2001 | 3/22/2001 | P | PASS |
Dave Hannah
|
|
|
Ryan ###-####
|
BLD-Footing | 3/21/2001 | 3/21/2001 | 3/21/2001 | P | PASS |
Dave Hannah
|
|
|
ft ins--ryan ###-####
|
Issue PAID IN FULL permit | | | 3/16/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/12/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/12/2001 | | DONE |
|
|
|
TALKED TO VERNA TO VERIFY PLANS ARE READY
|
Plan assigned to (PEP) | 3/9/2001 | 3/9/2001 | 3/9/2001 | | PASS |
Perry Paine
|
|
|
3/9/2001 17:29:46 PEP - activity updated through activity BLDA022 from case BLD01-00352.
|
Inspector's copy Bld permit | | | 3/9/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 3/9/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2001 | | DONE |
|
|
|
|
Pending Assignment by DJO | 2/15/2001 | | 3/9/2001 | | DONE |
Dan Overy
|
|
|
3/9/2001 08:12:06 PME - activity updated through activity BLDA176 from case BLD01-00352.
|
Office Staff conference/action | | | 3/8/2001 | | HOLD |
|
|
|
michael called 3/7/20001 wants plans on hold, bringing in new house plans 3/9/2001/pe
|
Routing - PLANNING | 2/15/2001 | 2/15/2001 | 3/7/2001 | | PASS |
|
|
|
JIM RICH HAS ON HOLD REQUESTING A DEED/PE
|
Routing - PUBLIC WORKS | 2/15/2001 | 2/15/2001 | 3/7/2001 | | PASS |
|
|
|
fees paid to west boise sewer dist. lw/pe
|
Application received | | | 2/15/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 3/7/2001 | 3/7/2001 | | | PEND |
|
|
|
|