Permit Information
Permit NumberBLD01-00375
StatusFinaled
Name TOBACCO CONNECTION
Site Address 9543 W EMERALD Unit: SUITE C
Project NameSAILFISH PLACE
Customer Number 
ePlanReviewNo
Description
Remodeling to expand and existing 1,656 sq. ft. office/warehouse/storage tenant on first floor by constructing an additional 740 sq. ft new portion on second floor for additional warehouse use per approved plans on file. New total for tenant will be 2,396 sq. ft. Work to include new framed floor area with supporting bearing walls, new interior partitions with doors, new interior stairway with handrails, dumbwaiter, interior finish, new gypsum board ceiling for first floor warehouse, fire sprinkler work, mechanical work, and electrical work. NOTE: This building is fully fire sprinklered for area increase. NOTE: NEW CERTIFICATE OF OCCUPANCY TO BE ISSUED. (P.C.#0132-01) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  1/31/2002 DONE
Fee Review-notes2/16/20012/16/200111/9/2001 DONE
Permanent occupancy  8/14/2001 DONE
Perm. Occ. Cert. #8789 issued 8-14-01 to the Tobacco Connection.
Permanent Occupancy 8/13/20018/13/2001 DONE
Details
FIRE-Final Inspection8/10/20018/13/20018/13/2001APASS
DetailsJoe Tawney
Reinsp Ok for certificate of completion 8/13/2001 10:22:28 AM
BLD-Final8/10/20018/13/20018/13/2001PPASS
DetailsRuss Owen
DWAYNE ###-#### FN OCC--CALL 1/2 BEFORE INSP. ok for perm oc. 8/13/2001 4:05:11 PM
FIRE-Final Inspection7/24/20017/26/20017/26/2001AFAIL
DetailsJoe Tawney
Final Fail C/N issued 7/26/2001 11:00:22 AM
BLD-Final7/24/20017/26/20017/26/2001PFAIL
DetailsRuss Owen
###-#### please call 30 minutes out so he can meet you there. needs signatures on card and handrails on . 7/26/2001 1:40:13 PM. i have approval for ledger connection revisions from engineer. 7/26/2001 1:40:50 PM
BLD-Aging Inspection7/23/20017/23/20017/23/2001 PART
DetailsRuss Owen
wip. 7/26/2001 11:50:38 AM
BLD-Framing/Rough-in5/18/20015/21/20015/21/2001APART
DetailsRuss Owen
Duane ###-#### please call so that he can meet you there. engineer to address ledger at south wall not anchored per plans,also needs ele insp,c/n posted. 12/21/2001 12:05:26 PM
Issue PAID IN FULL permit  4/24/2001 DONE
Inspection Record Card- Bld  4/12/2001 DONE
Print Occupancy Form  4/12/2001 DONE
Telephone call  4/12/2001 DONE
talked to dwayne to verify plans are ready
Routing - PLAN CHECK3/16/2001 4/11/2001 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  4/11/2001 PASS
Plan assigned to (JCB)2/23/2001 4/11/2001 PASS
DetailsJason Blais
4/11/2001 13:34:16 JCB - activity updated through activity BLDA022 from case BLD01-00375.
Plan resubmittals received  4/6/2001 DONE
Received three copies of revised sheets A-1, A-2, A-3. One copy of cover letter and one copy of geo. tech report. Routed to Jason B. KMM
Plan resubmittals received  3/20/2001 DONE
Received three copies of revised sheets A-2, A-3, A-4. One copy of response review letter and one copy of the calculations to support the connection details for the new mezzanine framing. Routed to Jason. KMM
Routing - FIRE3/13/2001 3/16/2001 PASS
Plan Review Completed(1st rev)  3/16/2001 FAIL
Plan resubmittals requested  3/13/2001  
Plan resubmittals and response required for further review.
Routing - PLAN CHECK2/23/2001 3/13/2001 FAIL
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
Plan Reviewer's activity  2/23/2001 DONE
This doesn't qualify for a partial permit as it has new floor framing creating additional 2nd story area. Sent a fax to Cornel Larson notifying him of this.
Application received  2/16/2001  
Recd Pcfee & Taken To Pln CK  2/16/2001 DONE