Fee Review-notes | 2/22/2001 | 2/22/2001 | 5/25/2001 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/22/2001 | 5/24/2001 | 5/24/2001 | A | PASS |
Joe Tawney
|
|
|
Final OK for permanant occupancy 5/24/2001 10:52:43 AM
|
BLD-Final | 5/22/2001 | 5/24/2001 | 5/24/2001 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/22/2001 at 14:15:17. Contact: ###-####. 5/24/2001 1:04:28 PM ok for perm occ 5/24/2001 1:56:30 PM
|
FIRE-Alarm Testing | 5/22/2001 | 5/24/2001 | 5/24/2001 | A | PASS |
Joe Tawney
|
|
|
Reinsp OK on alarm system 5/24/2001 10:53:15 AM
|
Permanent Occupancy | | 5/24/2001 | 5/24/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/24/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8702 issued 5-24-01 to North American Mortgage.
|
FIRE-Final Inspection | 5/10/2001 | 5/11/2001 | 5/11/2001 | A | FAIL |
Joe Tawney
|
|
|
fire sprinkler and fire alarm ###-#### Test duct det Fail improperly installed. Emerg and exit lights OK 5/11/2001 11:20:25 AM
|
BLD-Other | 5/8/2001 | 5/9/2001 | 5/9/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/08/2001 at 15:47:51. Contact: ###-####. grid ceiling. 12/9/2001 12:29:18 PM
|
FIRE-Final Inspection | 5/4/2001 | 5/4/2001 | 5/4/2001 | P | PART |
Joe Tawney
|
|
|
John ###-#### Spklr rough in OK to cover exc SE co0rner office. 2heads off same drop in same room. 5/4/2001 3:11:25 PM
|
BLD-Framing/Rough-in | 4/10/2001 | 4/10/2001 | 4/10/2001 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/10/2001 at 10:31:40. Contact: ###-####. l 4/11/2001 10:18:36 AMleft side offices ok to cover. 4/11/2001 10:18:52 AM
|
BLD-Framing/Rough-in | 3/29/2001 | 3/30/2001 | 3/30/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/29/2001 at 14:49:15. Contact: ###-####.ok to sheet rock 3/30/2001 3:48:18 PM
|
Issue PAID IN FULL permit | | | 3/29/2001 | | DONE |
|
|
|
|
Plan Review Completed(1st rev) | | | 3/27/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/27/2001 | | 3/27/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2001 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/27/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/27/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/27/2001 | | DONE |
|
|
|
called permit ready
|
Plan assigned to (JCB) | 2/23/2001 | | 3/27/2001 | | PASS |
Jason Blais
|
|
|
3/27/2001 10:00:34 JCB - activity updated through activity BLDA022 from case BLD01-00417.
|
Routing - FIRE | 3/22/2001 | | 3/27/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/26/2001 | | 3/22/2001 | | PEND |
|
|
|
Plan review report sent and faxed to architect. No response required. Permit can be issued when plans approved by Fire Dept. Plans routed to Fire Dept.
|
Early Start Permit | | | 2/28/2001 | | DONE |
|
|
|
|
Telephone call | | | 2/26/2001 | | DONE |
|
|
|
left mess with marv meyer that permit is ready
|
Routing - PUBLIC WORKS | 2/23/2001 | | 2/26/2001 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 2/23/2001 | | DONE |
|
|
|
PARTIAL PERMIT ISSUED at the request of the contractor.
|
Plans ACCEPTED BY PLAN TECH | | | 2/22/2001 | | DONE |
|
|
|
|
Application received | | | 2/22/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/22/2001 | | DONE |
|
|
|
|