BLD-Final | 5/23/2001 | 5/23/2001 | 5/23/2001 | P | PASS |
Jim Sly
|
|
|
Chuck ###-#### C/C issued. 5/23/2001 2:33:31 PM
|
DOC - Permit Finaled | 5/23/2001 | 5/23/2001 | 5/23/2001 | P | PASS |
Jim Sly
|
|
|
Added by Inspector: 316 On 5/23/2001 2:33:10 PM
|
BLD-Energy code compliance | 3/28/2001 | 3/28/2001 | 3/28/2001 | P | PASS |
Jim Sly
|
|
|
###-#### Frame pass. 3/28/2001 3:15:57 PM
|
BLD-Framing/Rough-in | 3/27/2001 | 3/27/2001 | 3/27/2001 | P | FAIL |
Jim Sly
|
|
|
###-#### fram and shear C/N truss bracing.....Shear OK. 3/27/2001 2:15:28 PM
|
BLD-Foundation | 3/6/2001 | 3/6/2001 | 3/6/2001 | A | FAIL |
Jim Sly
|
|
|
wall dirk ###-#### Bldr changed mind....Going to tear out. 3/6/2001 1:09:32 PM
|
Issue PAID IN FULL permit | | | 2/28/2001 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 2/22/2001 | 2/22/2001 | 2/26/2001 | | PASS |
Perry Paine
|
|
|
2/26/2001 08:19:10 PEP - activity updated through activity BLDA022 from case BLD01-00422.
|
Inspector's copy Bld permit | | | 2/26/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 2/26/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/26/2001 | | DONE |
|
|
|
|
Telephone call | | | 2/26/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PUBLIC WORKS | 2/22/2001 | 2/22/2001 | 2/23/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 2/22/2001 | 2/22/2001 | 2/23/2001 | | PASS |
|
|
|
|
Application received | | | 2/22/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 2/23/2001 | 2/23/2001 | | | PEND |
|
|
|
|