Fee Review-notes | 2/23/2001 | 2/23/2001 | 3/15/2004 | | DONE |
|
|
|
|
Expired/Cancelled | | | 8/18/2003 | | DONE |
|
|
|
|
BLD-Final | 6/6/2002 | 6/7/2002 | 6/7/2002 | A | PASS |
Dave Hannah
|
|
|
SCOTT ###-#### PLEASE CALL 1/2 HOUR BRFORE SO THAT SCOTT CAN MEET YOU THERE ....
|
FIRE-Final Inspection | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled. earth quake and any hanger deficiencies to be corrected under tenant permit 6/6/2002 2:29:39 PM
|
FIRE-Final Inspection | 6/4/2002 | 6/5/2002 | 6/5/2002 | A | CANC |
Troy Cobbley
|
|
|
duplicate inspection 6/5/2002 11:42:44 AM
|
FIRE-Final Inspection | 6/4/2002 | 6/5/2002 | 6/5/2002 | P | FAIL |
Troy Cobbley
|
|
|
ceiling tile was in so I could not verify earth quake bracing or hangers on sprinkler lines to be per plan review notes, insulation in warehouse is sagging and needs to be reattached to roof deck 6/5/2002 2:40:55 PM
|
FIRE-Final Inspection | 5/31/2002 | 6/3/2002 | 6/3/2002 | A | FAIL |
Rick Jackson
|
|
|
###-#### SCOTT need BLD permit plans and FIR sprinkler plans 6/3/2002 9:12:18 AM
|
BLD-Aging Inspection | 12/7/2001 | 12/7/2001 | 12/7/2001 | | PART |
Russ Owen
|
|
|
|
BLD-Aging Inspection | 9/24/2001 | 9/24/2001 | 9/24/2001 | | PART |
Russ Owen
|
|
|
wip 9/26/2001 4:02:23 PM
|
BLD-Aging Inspection | 7/24/2001 | 7/24/2001 | 7/24/2001 | | PART |
Russ Owen
|
|
|
wip. 7/26/2001 1:56:55 PM
|
BLD-Framing/Rough-in | 5/23/2001 | 5/24/2001 | 5/24/2001 | A | PASS |
Dave Hannah
|
|
|
Dennis ###-#### front wall and restroom walls 5/24/2001 10:28:15 AM
|
BLD-Foundation | 5/14/2001 | 5/15/2001 | 5/15/2001 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/14/2001 at 18:34:02. Contact: ###-####.
|
BLD-Footing | 4/12/2001 | 4/13/2001 | 4/13/2001 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/12/2001 at 19:18:17. Contact: ###-####. footings at the front wall for new columns. 4/13/2001 11:00:16 AM
|
Issue PAID IN FULL permit | | | 4/11/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/6/2001 | | 4/9/2001 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 4/9/2001 | | DONE |
|
|
|
|
Telephone call | | | 4/9/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (JCB) | 3/2/2001 | | 4/9/2001 | | PASS |
Jason Blais
|
|
|
4/9/2001 09:52:07 JCB - activity updated through activity BLDA022 from case BLD01-00435.
|
Routing - FIRE | 4/2/2001 | | 4/6/2001 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 4/6/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 3/29/2001 | | 4/2/2001 | | |
|
|
|
Route to Fire Dept.
|
Routing - PLANNING | 3/28/2001 | | 3/29/2001 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/28/2001 | | |
|
|
|
Resubmittal documents and response required for further review.
|
Routing - PLAN CHECK | 3/6/2001 | | 3/28/2001 | | FAIL |
|
|
|
Plan review report faxed to architect, engineer, and property manager. Resubmittal documents and response required. Plans to route to Planning and the Fire Dept. for review.
|
Routing - PUBLIC WORKS | 3/2/2001 | | 3/6/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/26/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 2/23/2001 | | PASS |
|
|
|
|
Application received | | | 2/23/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|