(F) Reprint permit | | | 3/11/2002 | | DONE |
|
|
|
|
Fee Review-notes | 2/23/2001 | 2/23/2001 | 11/9/2001 | | DONE |
|
|
|
final cert. 3,331,135.00 ele 496,441.00 plm 385,790.00 mec 48,738.00 mec
o/s 394,000.00 fire 70,706.00 from Dan Loerke Const. ###-####
|
Letter of compliance | | | 8/28/2001 | | DONE |
|
|
|
Letter of Compliance #21934 issued 8-28-01.
|
BLD-Final | 8/22/2001 | 8/23/2001 | 8/23/2001 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/22/2001 at 14:22:41. Contact: ###-####. needs plumb sign off 8/22/2001 10:35:24 PM
|
BLD-Final | 8/23/2001 | 8/23/2001 | 8/23/2001 | A | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 8/23/2001 9:29:30 AM Reinsp OK for permanant occupancy
|
FIRE-Final Inspection | 8/17/2001 | 8/20/2001 | 8/20/2001 | P | FAIL |
Joe Tawney
|
|
|
Final Fail thumb turns and move one strobe in hallway 8/20/2001 6:38:20 PM
|
FIRE-Conference | 8/8/2001 | 8/9/2001 | 8/9/2001 | A | PASS |
Joe Tawney
|
|
|
|
BLD-Framing/Rough-in | 7/31/2001 | 8/1/2001 | 8/1/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 7/31/2001 10:03:27 PM
|
BLD-Aging Inspection | 7/24/2001 | 7/24/2001 | 7/24/2001 | | PASS |
Tom Arcoraci
|
|
|
WIP 7/23/2001 8:22:58 PM
|
Plan resubmittals received | | | 5/11/2001 | | |
|
|
|
2 COPIES OF REVISED SHEET S1.1/ 2 COPIES RIVISED STRUCTURAL CALCS. TOOK TO TOM A. STRUC INSPECTOR
|
Issue PAID IN FULL permit | | | 4/24/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/23/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/23/2001 | | DONE |
|
|
|
|
Telephone call | | | 4/23/2001 | | DONE |
|
|
|
called permit ready
|
Routing - PLAN CHECK | 4/18/2001 | 4/18/2001 | 4/20/2001 | | PASS |
|
|
|
New structural details received, Sheet S1.1 & New engineering calcs. Reviewed and discussed with strucutral engineer, Jan Welch. Incerted into plans. Approved for issue of permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2001 | | PASS |
|
|
|
Routing to permit desk for issue.
|
Plan assigned to (DRS) | 3/5/2001 | | 4/20/2001 | | PASS |
Dan Stuart
|
|
|
4/20/2001 12:15:31 DRS - activity updated through activity BLDA022 from case BLD01-00440.
|
Plan resubmittals received | | | 4/18/2001 | | DONE |
|
|
|
Received plan resubmittals from HP , and CSHQA two sheets and small documents, forwarded same to Dan Stuart. 4/18/01 DAR
|
Plan Review Completed(1st rev) | | | 4/12/2001 | | FAIL |
|
|
|
|
Routing - FIRE | 4/9/2001 | | 4/12/2001 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 4/9/2001 | | FAIL |
|
|
|
Discussion of structural details for clarification with Jan Wech, 4/4/01, revealed that the plans submitted were not the plans to be used for the structural support system to install the new Dry Coolers on the existing roof structure. Call from Mr Maulin, 4/5/01, project architect of record disclosed, that Jan had been instructed to prepare new design details & submit for approval.
|
Routing - PLAN CHECK | 4/2/2001 | | 4/9/2001 | | FAIL |
|
|
|
Waiting for new Structural Plans & Design Calcs from Stapley Eng., Janene Welch.
Routing plans to Fire code analyst.
|
Routing - PUBLIC WORKS | 3/5/2001 | | 3/7/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/26/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 2/23/2001 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/23/2001 | | DONE |
|
|
|
|
Application received | | | 2/23/2001 | | |
|
|
|
|