Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD01-00444
StatusFinaled
Name TAHOE CONSTRUCTION
Site Address 4950 E ARROW JUNCTION DR
Project Name 
Customer Number 
ePlanReviewNo
Description
This project is to build a new 1970s.f. 2-story single family dwelling with 822s.f. on the main level; 803s.f. on the 2nd level; 345s.f. unfinished future bonus room over the garage; an 840s.f. attached 2-car garage; 190s.f. covered front porch and a 78s.f. covered 2nd floor deck. Zoned R-1C/DA @CUP98-00116 setbacks ok,d by rhj All per the approved plans as marked and attachments. PC#0126 pep
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/8/20016/11/20016/11/2001APASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 06/08/2001 at 15:31:00. Contact: ###-####. 6/11/2001 8:30:08 AM C. of C. #21431 issued 6/11/2001 8:32:14 AM
DOC - Permit Finaled6/11/20016/11/20016/11/2001APASS
DetailsSteven Webb
Finaled by inspector at 6/11/2001 8:32:18 AM
BLD-Energy code compliance4/20/20014/23/20014/23/2001APART
DetailsSteven Webb
###-#### ok to cover--need energy report prior to c. of c. being issued. 4/23/2001 10:21:33 AM
BLD-Energy code compliance4/19/20014/20/20014/20/2001PPART
DetailsSteven Webb
###-#### C/n issued--prior to final an energy report is required before the c. of c. will be issued. 4/20/2001 2:42:24 PM
BLD-Framing/Rough-in4/18/20014/19/20014/19/2001PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/18/2001 at 16:54:54. Contact: ###-####. ok to insulate 4/19/2001 1:24:19 PM
BLD-Framing/Rough-in4/18/20014/19/20014/19/2001PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/18/2001 at 16:54:54. Contact: ###-####. ok to insulate 4/19/2001 1:24:19 PM
BLD-Framing/Rough-in4/16/20014/18/20014/18/2001AFAIL
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/16/2001 at 15:18:15. Contact: ###-####.C/N issued 4/18/2001 12:20:43 PM
BLD-Other4/11/20014/12/20014/12/2001APASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/11/2001 at 16:26:06. Contact: ###-####. Shear--ok to cover 4/12/2001 11:18:45 AM
BLD-Framing/Rough-in4/9/20014/10/20014/10/2001AFAIL
DetailsSteven Webb
shear\\###-#### C/N posted on site-not ready 4/10/2001 10:41:56 AM
BLD-Other4/5/20014/6/20014/6/2001ACANC
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/05/2001 at 15:48:25. Contact: ###-####.
BLD-Foundation3/13/20013/13/20013/13/2001PPART
DetailsSteven Webb
###-#### EARLY PM wip--hd not installated at time of inspection, rebar was covered with form oil, wiped with cloth to remove majority. 3/13/2001 2:50:05 PM
BLD-Footing3/12/20013/12/20013/12/2001PPART
DetailsSteven Webb
Scheduled by a contractor via Hello! on 03/12/2001 at 09:59:17. Contact: ###-####.wip-appears ok--setbacks ok 3/12/2001 3:54:41 PM
Issue PAID IN FULL permit  3/5/2001 DONE
Plan assigned to (PEP)2/27/2001 3/1/2001 PASS
DetailsPerry Paine
3/1/2001 10:59:59 PEP - activity updated through activity BLDA022 from case BLD01-00444.
Inspector's copy Bld permit  3/1/2001 DONE
Plan Review Report  3/1/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/1/2001 DONE
Inspection Record Card- Bld  3/1/2001 DONE
Telephone call  3/1/2001 DONE
left message w/reberta gave dollar amount
Pending Assignment by DJO2/23/2001 2/27/2001 DONE
DetailsDan Overy
2/27/2001 14:05:31 PEP - activity updated through activity BLDA176 from case BLD01-00444.
Routing - PUBLIC WORKS2/23/20012/23/20012/26/2001 PASS
Routing - PLANNING2/23/20012/23/20012/26/2001 PASS
Application received  2/23/2001  
Routing - PLAN CHECK2/26/20012/26/2001  PEND
Telephone Call     
called designer to confirm proposed attachment of front columns to footing/ foundation.