BLD-Aging Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | | PASS |
Tom Arcoraci
|
|
|
|
DOC - Permit Finaled | 8/5/2001 | 8/5/2001 | 8/5/2001 | A | PASS |
Tom Arcoraci
|
|
|
Finaled by inspector at 8/5/2001 9:07:47 PM
|
BLD-Final | 5/29/2001 | 5/29/2001 | 5/29/2001 | P | PASS |
Dave Hannah
|
|
|
###-####
|
BLD-Framing/Rough-in | 5/18/2001 | 5/21/2001 | 5/21/2001 | A | PASS |
Dave Hannah
|
|
|
Kent ###-#### 5/21/2001 11:14:09 AM suspended ceiling gride ok smoke stops ok lighting wired up ok to install panels 5/21/2001 11:20:04 AM
|
BLD-Framing/Rough-in | 5/18/2001 | 5/18/2001 | 5/18/2001 | P | FAIL |
Tom Arcoraci
|
|
|
t-bar sizemec and draft stop Kent ###-#### please call after the inspection to let him know if it passed no plans on site called left mess 5/18/2001 2:10:08 PM ge 5/18/2001 2:10:15 PM
|
Issue PAID IN FULL permit | | | 4/24/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/29/2001 | | 3/30/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/30/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/30/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/30/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/30/2001 | | DONE |
|
|
|
called Jason Butler at ###-####
|
Plan assigned to (MLO) | 2/28/2001 | | 3/30/2001 | | PASS |
Mike Otto
|
|
|
3/30/2001 10:32:26 MLO - activity updated through activity BLDA022 from case BLD01-00485.
|
Plan resubmittals received | | | 3/28/2001 | | DONE |
|
|
|
Received two copies of revised sheets - cover sheet, A1.01, A2.01, A2.02, two copies of struct. calcs. and one copy of cover letter and one coyp of addendums. Routed to Mike O. KMM
|
Plan Reviewer's activity | | | 3/15/2001 | | DONE |
|
|
|
Received request from architect to wave code requirements on fire-resistive ceiling and draft stops. Contacted architect, Jason Butler at 10:05 AM and left message that request is denied must comply with plan review corrections for rated ceiling and draft stops.
|
Plan resubmittals requested | | | 3/12/2001 | | FAIL |
|
|
|
UBC corrections
|
Routing - PLAN CHECK | 2/28/2001 | | 3/2/2001 | | FAIL |
|
|
|
corrections faxed and mailed to architect. MLO
|
Plan routing begun/TENANTS | | | 2/28/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/28/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 2/27/2001 | | DONE |
|
|
|
|
Application received | | | 2/27/2001 | | |
|
|
|
|