Fee Review-notes | 7/7/2003 | 7/7/2003 | 7/7/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/26/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9082 issued 3-26-02 to St. Luke's Hospital for the 10th floor physical therapy & respiratory therapy.
|
BLD-Final | 3/7/2002 | 3/7/2002 | 3/7/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/07/2002 at 07:53:26. Contact: ###-####. struct ok for perm...awaiting plbg perm final, need to install therapy tubs. 3/7/2002 1:57:07 PM
|
BLD-Final | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/06/2002 at 08:21:54. Contact: ###-####. need plans to site. 3/6/2002 3:17:14 PM
|
BLD-Final | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | CANC |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 3/6/2002 1:26:43 PM
|
FIRE-Final Inspection | 3/5/2002 | 3/5/2002 | 3/5/2002 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/05/2002 at 09:09:16. Contact: ###-####.
|
BLD-Final | 3/5/2002 | 3/5/2002 | 3/5/2002 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/05/2002 at 09:12:43. Contact: ###-####...need fire. 3/6/2002 1:29:19 PM
|
FIRE-Final Inspection | 3/1/2002 | 3/4/2002 | 3/4/2002 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/01/2002 at 15:16:17. Contact: ###-####. voice fire alarm not working; damper access doors and damper not closing 3/4/2002 9:53:10 AM
|
BLD-Aging Inspection | 1/29/2002 | 1/29/2002 | 1/31/2002 | | NR |
Carl Dependahl
|
|
|
wip, 10th fl 1/31/2002 5:59:25 PM
|
Permanent Occupancy | | 1/28/2002 | 1/28/2002 | | DONE |
|
|
|
|
Fee Review-notes | 3/1/2001 | 3/1/2001 | 12/12/2001 | | DONE |
|
|
|
waiting for final
|
BLD-Framing/Rough-in | 11/28/2001 | 11/29/2001 | 11/29/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/28/2001 at 09:34:03. Contact: ###-####...seal/firestop hvac, etc. above grid ;ok to tile exc as noted. 11/29/2001 5:03:50 PM
|
BLD-Framing/Rough-in | 10/29/2001 | 10/30/2001 | 10/30/2001 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/29/2001 at 10:13:56. Contact: ###-####. Report from MTI for column fire proofing ok. Ok to sheetrock walls Smoke barrier not completelt constructed at this time ,need to recall, also no ceiling tile in at this time and penetration of firewalls not completed at this time. 10/31/2001 9:20:48 AM
|
BLD-Framing/Rough-in | 10/18/2001 | 10/18/2001 | 10/18/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-####, c/n, recxall. 10/18/2001 5:14:38 PM
|
BLD-Framing/Rough-in | 10/17/2001 | 10/17/2001 | 10/17/2001 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/17/2001 at 08:31:22. Contact: ###-####...still need arch's clarification. 10/17/2001 4:32:37 PM
|
BLD-Framing/Rough-in | 10/15/2001 | 10/16/2001 | 10/16/2001 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/15/2001 at 10:31:51. Contact: ###-####. incorrect permit #...recall. 10/16/2001 4:51:45 PM
|
BLD-Conference | 9/12/2001 | 9/12/2001 | 9/12/2001 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/12/2001 at 11:03:47. Contact: ###-####....w/ Jason, need drawings 9/12/2001 1:55:00 PM, verify req'd firerating at cols...main or secondary? 9/12/2001 2:39:35 PM
|
Issue & PRINT to be Invoiced | | | 8/1/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/30/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/30/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/30/2001 | | DONE |
|
|
|
|
Telephone call | | | 7/30/2001 | | DONE |
|
|
|
email curtis
|
Routing - FIRE | 7/24/2001 | 7/24/2001 | 7/27/2001 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 7/27/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/27/2001 | | 7/27/2001 | | PASS |
|
|
|
Approved as noted and attached plan review conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/27/2001 | | PASS |
|
|
|
To permit desk.
|
Plan assigned to (DRS) | 3/15/2001 | | 7/27/2001 | | PASS |
Dan Stuart
|
|
|
7/27/2001 16:19:26 DRS - activity updated through activity BLDA022 from case BLD01-00512.
|
Routing - PLAN CHECK | 3/21/2001 | | 7/24/2001 | | PEND |
|
|
|
Have completed other plan reviews placed ahead of this one per SLRMC. No response necessary for this project. Forwarding plans to fire code analyst for review.
|
Plan resubmittals received | | | 4/20/2001 | | DONE |
|
|
|
Received Plan resubmittals from Tamura & associates, John Price,forwarded same to Dan Stuart. 4/20/01 DAR
|
Routing - PLUMBING | 3/19/2001 | | 3/21/2001 | | PASS |
|
|
|
per plans and 97 upc
|
Routing - PUBLIC WORKS | 3/15/2001 | | 3/16/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/1/2001 | | DONE |
|
|
|
|
Received Certificate of Value | | | 3/1/2001 | | DONE |
|
|
|
|
Application received | | | 3/1/2001 | | |
|
|
|
|