BLD-Aging Inspection | 4/11/2003 | 4/11/2003 | 4/11/2003 | | DONE |
Carl Dependahl
|
|
|
work abandoned...apply for new permit. 4/11/2003 4:51:51 PM
|
BLD-Conference | 4/11/2003 | 4/11/2003 | 4/11/2003 | P | PASS |
Carl Dependahl
|
|
|
w/ Jason re permit, arch to submit new app.
|
DOC - Permit Expired | 4/11/2003 | 4/11/2003 | 4/11/2003 | P | PASS |
Carl Dependahl
|
|
|
Expired by inspector at 4/11/2003 4:54:01 PM
|
BLD-Conference | 2/7/2003 | 2/7/2003 | 2/7/2003 | P | PASS |
Carl Dependahl
|
|
|
w/ 2/7/2003 3:00:58 PM arch....referred 2/7/2003 3:04:14 PM...to plan chk. 2/7/2003 3:07:25 PM
|
BLD-Aging Inspection | 1/27/2003 | 1/27/2003 | 1/27/2003 | | PASS |
Carl Dependahl
|
|
|
project appears delayed...unable to contact. 1/27/2003 12:12:50 PM
|
BLD-Aging Inspection | 12/10/2001 | 12/10/2001 | 12/11/2001 | | NR |
Carl Dependahl
|
|
|
no call by contractor....wip 12/11/2001 6:34:14 PM
|
BLD-Conference | 10/8/2001 | 10/8/2001 | 10/8/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/8/2001 10:40:13 AM w/ owner re 1hr const.
|
BLD-Concrete | 8/27/2001 | 8/28/2001 | 8/28/2001 | A | PASS |
Carl Dependahl
|
|
|
###-#### CELL RUSS 8/28/2001 12:22:39 PM int slab ok; consult fire re sprinklers at raised floor areas 8/28/2001 12:23:11 PM
|
BLD-Conference | 8/21/2001 | 8/21/2001 | 8/21/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/21/2001 9:16:26 AM w/ bldr...call in for insps as req'd
|
Issue PAID IN FULL permit | | | 7/27/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/26/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/26/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/24/2001 | | 7/25/2001 | | PASS |
|
|
|
Addendum info. provided. Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2001 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 3/21/2001 | | 7/25/2001 | | PASS |
Jason Blais
|
|
|
7/25/2001 13:52:59 JCB - activity updated through activity BLDA022 from case BLD01-00513.
|
Plan resubmittals requested | | | 7/24/2001 | | |
|
|
|
Addendum information and new structural calculations required again.
|
Routing - PLAN CHECK | 7/5/2001 | | 7/24/2001 | | FAIL |
|
|
|
Addendum info. provided is still not in compliance with code. Architect and structural engineer need to address an approved adhesive anchor system for use in CMU units. Faxed and sent 13 pages of info. to help resolve issue. New addedum information and new strucural calculations required to be submitted.
|
Plan resubmittals received | | | 7/23/2001 | | DONE |
|
|
|
Received two sets of small documents from AP&D group, forwarded same to Jason Blais. 7/23/01 DAR
|
Plan resubmittals received | | | 7/11/2001 | | DONE |
|
|
|
Received small documents from AP&D Group, forwarded same to Jason Blais. 7/11/01 DAR
|
Routing - FIRE | 7/3/2001 | | 7/5/2001 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 7/3/2001 | | |
|
|
|
Addendum sheets needed to clarify four items.
|
Routing - PLAN CHECK | 5/11/2001 | | 7/3/2001 | | FAIL |
|
|
|
Four items still need to be adequately addressed and clarified. Called architect and let him know deficient items. He acknowledged and said addendum sheets would be coming. Plans routed to Fire Dept. again for review.
|
Plan resubmittals received | | | 6/28/2001 | | DONE |
|
|
|
Received two sets of plan resubmittals from Jim Struckman of AP&D Group plus small documents. A, Fand P sheets, forwarded all to Jason Blais. 6/28/01 DAR
|
Routing - FIRE | 5/9/2001 | 5/14/2001 | 5/11/2001 | | FAIL |
Bill Alexander
|
|
|
Lack UFC issues/requirements.
|
Routing - PLAN CHECK | 4/19/2001 | | 5/9/2001 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Numerous problems identified. Plan resubmittal and response required for further review. Plans routed to Fire Dept. for review.
|
Plan resubmittals requested | | | 5/9/2001 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Plan resubmittals received | | | 5/9/2001 | | DONE |
|
|
|
Received two copies of floor plan. KMM
|
Routing - PLANNING | 4/3/2001 | | 4/19/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/16/2001 | | DONE |
|
|
|
Received one copy of addendum no. 1. Routed to Jason B. KMM
|
Routing - PLAN CHECK | 3/26/2001 | | 4/3/2001 | | |
|
|
|
Needs to route to Planning prior to Jason's review. Outside work being done.
|
Routing - PLUMBING | 3/23/2001 | | 3/26/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/21/2001 | | 3/23/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/20/2001 | | DONE |
|
|
|
Received stamped and signed plumb. sheets and plans back from Mr. Struckman. Put with plans and put back on Marlenes desk. KMM
|
Telephone call | | | 3/16/2001 | | DONE |
|
|
|
Received a call from Jim Structman (arch.) for this project. He will be in this afternoon to complete plumb. requirements for this project. I took plans from Marlenes desk to give to him when he comes in. KMM
|
Plan resubmittals received | | | 3/5/2001 | | DONE |
|
|
|
Received one line plumb. plans. However they were not stamped or signed. KMM
|
Received Certificate of Value | | | 3/2/2001 | | |
|
|
|
|
Application received | | | 3/1/2001 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/1/2001 | | FAIL |
|
|
|
Requires plumb. plans.
3/05/01 Received plumb. plans but they were not stamped or signed. Contacted Russell
Purcell to let him know. He stated that Arch. would not be in town until 3/13 or 3/14. to stamp and sign. KMM
|
Fee Review-notes | 3/1/2001 | 3/1/2001 | | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|