Case Summary (BLD) | | | 11/4/2005 | | |
|
|
|
|
Fee Review-notes | 7/7/2003 | 7/7/2003 | 7/7/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Fee Review-notes | 3/2/2001 | 3/2/2001 | 1/29/2002 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/20/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8770 issued 7-20-01 to perkins Coie LLP.
|
FIRE-Final Inspection | 7/19/2001 | 7/19/2001 | 7/19/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 7/19/2001 8:04:12 AM
|
Permanent Occupancy | | 7/19/2001 | 7/19/2001 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/17/2001 | 7/18/2001 | 7/18/2001 | A | FAIL |
Rick Jackson
|
|
|
AT 8:30 ??? BUCK-- ###-#### FN FIRE
|
FIRE-Alarm Testing | 7/17/2001 | 7/18/2001 | 7/18/2001 | A | FAIL |
Rick Jackson
|
|
|
BUCK ###-#### FIRE ALM TEST c/n issued 7/18/2001 9:41:54 AM
|
BLD-Final | 7/17/2001 | 7/18/2001 | 7/18/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/17/2001 at 08:41:24. Contact: ###-####. final ok pending fire sign off. 7/18/2001 5:04:48 PM
|
BLD-Final | 7/17/2001 | 7/18/2001 | 7/18/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 07/17/2001 at 08:41:24. Contact: ###-####. final ok pending fire sign off. 7/18/2001 5:04:48 PM
|
FIRE-Alarm Testing | 7/16/2001 | 7/17/2001 | 7/17/2001 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/16/2001 at 11:11:36. Contact: ###-####. CANCEL PER BUCK
|
FIRE-Final Inspection | 7/16/2001 | 7/17/2001 | 7/17/2001 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/16/2001 at 11:12:47. Contact: ###-####.--CANCEL PER BUCK/MLS
|
BLD-Conference | 7/12/2001 | 7/12/2001 | 7/12/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/12/2001 11:40:41 AM w/ bldr...need fire & elec for t/o; verified 3hr doors at bsmt elev shaft entry
|
FIRE-Hydro test above ground | 7/2/2001 | 7/2/2001 | 7/2/2001 | P | PASS |
Joe Tawney
|
|
|
###-#### OK on 4th flr hydro test 7/2/2001 1:01:02 PM
|
FIRE-Sprinkler Rough-in | 6/26/2001 | 6/26/2001 | 6/26/2001 | P | PASS |
Rick Jackson
|
|
|
Doug ###-#### r/i okay to cover 6/26/2001 10:48:06 AM
|
BLD-Other | 6/22/2001 | 6/22/2001 | 6/22/2001 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/22/2001 at 07:27:07. Contact: ###-####. need wires pods, firecaulk corridor 6/22/2001 12:11:11 PM
|
BLD-Other | 6/20/2001 | 6/21/2001 | 6/21/2001 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/20/2001 at 14:55:28. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/9/2001 | 5/9/2001 | 5/9/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/9/2001 10:58:25 AM ok to usr frt wood at door/window openings w/i assy
|
BLD-Conference | 5/1/2001 | 5/1/2001 | 5/1/2001 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/01/2001 at 08:38:52. Contact: ###-####. w/ contractor, ok to use frt wood within walls 5/1/2001 4:10:48 PM
|
BLD-Wall cover | 4/25/2001 | 4/26/2001 | 4/26/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/25/2001 at 15:21:28. Contact: ###-####.complete firestops & submit detail for tunnel...ok to cover 4/26/2001 12:24:43 PM
|
BLD-Wall cover | 4/19/2001 | 4/19/2001 | 4/19/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/19/2001 at 11:11:01. Contact: ###-####. top of corridor ceilling only. 4/19/2001 3:01:59 PM
|
Plan Reviewer's activity | | | 4/17/2001 | | PASS |
|
|
|
Approved TI sprinkler modifications without a FIR permit, based on conditions of letter dated 4/16/2001 from Treasure Valley FP, replacing shell SSU's with SSP's in TI area, using same K factor heads, same spacing, one head/drop.
|
Plan resubmittals received | | | 4/17/2001 | | DONE |
|
|
|
Received plan resubmittals from Sam Burrows, Lombard - Conrad Architects Two sets. Same forwarded to Ron Hill. 4/17/01 DAR
|
Print Occupancy Form | | | 4/13/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/2001 | | DONE |
|
|
|
|
Telephone call | | | 4/13/2001 | | DONE |
|
|
|
called permit ready
|
Print Occupancy Form | | | 4/13/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/13/2001 | | DONE |
|
|
|
|
Plan Review Completed(1st rev) | | | 4/12/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/12/2001 | | 4/12/2001 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2001 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (R_H) | 3/19/2001 | | 4/12/2001 | | PASS |
|
|
|
4/12/2001 15:44:49 RMH - activity updated through activity BLDA022 from case BLD01-00525.
|
Routing - FIRE | 4/9/2001 | | 4/12/2001 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/9/2001 | | PASS |
Ron Hill
|
|
|
No corrections required, Routed to fire for review on 4-9-01
|
Case Summary (BLD) | | | 4/9/2001 | | |
|
|
|
|
Routing - PLAN CHECK | 3/20/2001 | | 4/9/2001 | | PEND |
Ron Hill
|
|
|
Permit Pending fire departments plan review and approval. No corrections are required from building plan review. Routed to fire on 4-9-01.
|
Routing - PUBLIC WORKS | 3/19/2001 | | 3/20/2001 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/5/2001 | | DONE |
|
|
|
|
Application received | | | 3/2/2001 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/2/2001 | | DONE |
|
|
|
|