Case Summary (BLD) | | | 8/21/2012 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/9/2009 | | DONE |
Tisha Gallop
|
|
|
|
Fee Review-notes | 7/7/2003 | 7/7/2003 | 7/7/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/24/2003 | | |
|
|
|
|
Permanent Occupancy | | 7/17/2002 | 7/17/2002 | | DONE |
|
|
|
|
BLD-Final | 7/16/2002 | 7/17/2002 | 7/17/2002 | A | PASS |
Carl Dependahl
|
|
|
scott; Phone #: ###-#### rec'd eng's affidavit...ok 7/17/2002 11:36:50 AM
|
Permanent occupancy | | | 7/17/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9253 issued 7-17-02 to the River Walk Apts., sec. 1 of 3.
|
BLD-Final | 6/17/2002 | 6/18/2002 | 6/18/2002 | A | NR |
Carl Dependahl
|
|
|
see bld00-03519 6/18/2002 11:35:05 AM
|
BLD-Final | 6/17/2002 | 6/17/2002 | 6/17/2002 | P | NR |
Carl Dependahl
|
|
|
SCOTT ###-####
|
BLD-Final | 6/14/2002 | 6/14/2002 | 6/14/2002 | P | NR |
Carl Dependahl
|
|
|
scott ###-#### fn will recall 6/14/2002 5:17:46 PM
|
BLD-Final | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | NR |
Jim Storey
|
|
|
|
Fee Review-notes | 3/14/2001 | 3/14/2001 | 1/28/2002 | | DONE |
|
|
|
|
BLD-Final | 1/16/2002 | 1/17/2002 | 1/17/2002 | A | PART |
Carl Dependahl
|
|
|
###-####, c/n, ok for t/o. 1/17/2002 3:51:20 PM
|
Temporary occupancy | | | 1/17/2002 | | PARA |
|
|
|
Temp. Occ. Cert. #4704 issued 1-17-02 to Sec. 1 of 3 of the River Walk Apts.
|
FIRE-Final Inspection | 1/15/2002 | 1/16/2002 | 1/16/2002 | A | PASS |
Rick Jackson
|
|
|
###-#### okay to occupy this permitted area only pending structural approval 1/16/2002 2:06:28 PM
|
BLD-Final | 1/14/2002 | 1/14/2002 | 1/14/2002 | P | NR |
Carl Dependahl
|
|
|
###-####, need all ok's, recall. 1/14/2002 6:06:37 PM
|
BLD-Final | 1/9/2002 | 1/9/2002 | 1/11/2002 | P | CANC |
Carl Dependahl
|
|
|
###-####
|
BLD-Final | 1/10/2002 | 1/10/2002 | 1/10/2002 | P | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Aging Inspection | 12/10/2001 | 12/10/2001 | 12/11/2001 | | NR |
Carl Dependahl
|
|
|
wip 12/11/2001 9:58:37 AM
|
BLD-Framing/Rough-in | 10/10/2001 | 10/10/2001 | 10/10/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-#### DRYWALL complete draft stops, firestops....sec 1 drywall ok 10/10/2001 6:02:08 PM
|
BLD-Framing/Rough-in | 10/8/2001 | 10/9/2001 | 10/9/2001 | A | NR |
Carl Dependahl
|
|
|
fr insp -scott ###-####
|
BLD-Conference | 10/8/2001 | 10/8/2001 | 10/8/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/8/2001 10:45:38 AM reviewed archs letter to Dixie re use pf factory spec for dryer duct length...should be perm. labeled.
|
BLD-Conference | 10/5/2001 | 10/5/2001 | 10/5/2001 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/05/2001 at 09:59:15. Contact: ###-####...install 2 layers gyp at 2hr walls at ext sections...or equal 10/5/2001 5:13:50 PM
|
BLD-Conference | 10/4/2001 | 10/4/2001 | 10/4/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/4/2001 11:19:11 AM w/ bldr re 2hr wall terminations... need remove nailers, combustibles, & provide full depth blocking at floor lines & loft area
|
BLD-Energy code compliance | 10/3/2001 | 10/3/2001 | 10/3/2001 | P | PART |
Carl Dependahl
|
|
|
scott-- ###-#### energy code 1st fl, sec 1 10/3/2001 11:15:14 AM
|
BLD-Framing/Rough-in | 10/3/2001 | 10/3/2001 | 10/3/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 10/3/2001 8:52:14 AM reinsp Scott ###-#### 1st/2nd fls sec 1ok to begin cover...drywall/firestop insp req'd 10/3/2001 5:39:24 PM c/n re 2hr walls at loft areas (4th fl.) 10/3/2001 5:41:34 PM
|
BLD-Energy code compliance | 10/3/2001 | 10/3/2001 | 10/3/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/3/2001 5:40:48 PM 2nd fl ins ok, sec 1
|
BLD-Energy code compliance | 10/1/2001 | 10/2/2001 | 10/2/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 10/01/2001 at 19:00:05. Contact: ###-####. 2nd fl. sec 1...complete firestops at plbg, elec per listing...recall 10/2/2001 10:58:37 AM
|
BLD-Energy code compliance | 10/2/2001 | 10/2/2001 | 10/2/2001 | P | NR |
Carl Dependahl
|
|
|
scott ###-#### energy code ... fix plbg firestops. 10/2/2001 4:42:51 PM
|
BLD-Energy code compliance | 9/28/2001 | 10/1/2001 | 10/1/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### SCOTT 2nd fl, sec 1 ok to strip (rc channel), stock, & begin cover, keep c/n at remainder 10/1/2001 6:20:57 PM
|
BLD-Framing/Rough-in | 9/21/2001 | 9/24/2001 | 9/24/2001 | A | PART |
Carl Dependahl
|
|
|
###-#### scott part, sec 1; keep c/n, ok to insul. 9/24/2001 5:35:34 PM
|
BLD-Framing/Rough-in | 9/20/2001 | 9/21/2001 | 9/21/2001 | A | FAIL |
Carl Dependahl
|
|
|
SCOTT ###-#### complete draft & fire stops verify all other r/i oks...keep c/n. 9/21/2001 4:34:45 PM
|
BLD-Framing/Rough-in | 9/18/2001 | 9/19/2001 | 9/19/2001 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 09/18/2001 at 18:16:20. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/18/2001 | 9/18/2001 | 9/18/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-####- scott fr sec 1, 1st fl; c/n fire stops/ blocks, draftstops, 2hr wall... 9/18/2001 6:20:48 PM 9/18/2001 6:21:59 PM
|
BLD-Framing/Rough-in | 9/17/2001 | 9/17/2001 | 9/17/2001 | P | CANC |
Carl Dependahl
|
|
|
###-#### carl i ran out of time to do these insp. 301 9/17/2001 7:11:56 PM
|
BLD-Concrete | 8/31/2001 | 9/4/2001 | 9/4/2001 | A | PART |
Carl Dependahl
|
|
|
scott ###-#### concrete; decks only, ok w/ spec insp. 9/4/2001 9:30:10 AM
|
BLD-Concrete | 8/27/2001 | 8/27/2001 | 8/27/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### scott upper floor exit balconies. 8/27/2001 3:44:20 PM
|
BLD-Concrete | 8/22/2001 | 8/22/2001 | 8/22/2001 | P | PART |
Carl Dependahl
|
|
|
scott ###-####; 1st fl walks, exit balcony. 8/22/2001 1:45:35 PM
|
BLD-Conference | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PASS |
Carl Dependahl
|
|
|
###-#### scott tre fireblocks, firestops at loft party walls, rock both sides truss to deck 8/20/2001 11:47:25 AM
|
(F) Reprint permit | | | 8/17/2001 | | DONE |
|
|
|
|
BLD-Conference | 8/9/2001 | 8/10/2001 | 8/10/2001 | A | PART |
Carl Dependahl
|
|
|
scott ###-#### for conference ; c/n : firestops, 2hr wall assy, damaged shear walls, fireblox/draftstops, etc. ok to continue; keep c/n re 3hr occ sep...elev. shaft protection. 8/10/2001 4:53:05 PM
|
BLD-Conference | 8/1/2001 | 8/2/2001 | 8/2/2001 | P | PASS |
Carl Dependahl
|
|
|
scott ###-####, w/ bldr re exhaust duc 8/2/2001 5:39:39 PM s 8/2/2001 5:39:47 PM
|
BLD-Conference | 7/27/2001 | 7/30/2001 | 7/30/2001 | A | PART |
Carl Dependahl
|
|
|
Scott kimball ###-####; c/n issued re shaft, 3hr protection at elev.; firestop at tubs 7/30/2001 4:44:13 PM
|
BLD-Conference | 7/24/2001 | 7/25/2001 | 7/25/2001 | P | CANC |
Russ Owen
|
|
|
###-#### Scott .wil recall for carl. 7/25/2001 1:07:51 PM
|
BLD-Conference | 7/10/2001 | 7/10/2001 | 7/10/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/10/2001 3:56:59 PM w/Mike Phillips, need 3hr door at elevator ( or equal as approved) as noted during inspection; shafts to be req'd per plan check interpretation of 710 & 711.3 ubc 7/10/2001 4:04:05 PM
|
BLD-Conference | 6/29/2001 | 7/3/2001 | 7/3/2001 | A | PART |
Carl Dependahl
|
|
|
scott ###-#### please call before going out; need to address opening at 3hr floor for elev. 7/3/2001 12:13:15 PM
|
Plan resubmittals received | | | 6/22/2001 | | DONE |
|
|
|
Received two copies of revsied sheet M3.10 and one copy of cover letter. routed to Carl d. KMM
|
BLD-Conference | 6/19/2001 | 6/19/2001 | 6/19/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/19/2001 12:18:59 PM re 2hr walls w/ framer; show approved details.
|
BLD-Conference | 6/18/2001 | 6/18/2001 | 6/18/2001 | P | PART |
Carl Dependahl
|
|
|
scott ###-####, need all spec insp reprts for parking gar.6/19/2001 5:34:30 PM 6/19/2001 5:38:52 PM
|
Issue PAID IN FULL permit | | | 6/12/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/11/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/11/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/11/2001 | | DONE |
|
|
|
|
Telephone call | | | 6/11/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plan resubmittals received | | | 6/8/2001 | | DONE |
|
|
|
Received two sets of plan resubmittals plus small Documents from John Price, of Tamura and Associates, forwarded same to Mike Phillips. 6/8/01 DAR
|
Plan Reviewer's activity | | | 6/8/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/8/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/8/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 3/5/2001 | | 6/8/2001 | | PASS |
Mike Phillips
|
|
|
6/8/2001 16:32:59 M_P - activity updated through activity BLDA022 from case BLD01-00531.
|
Routing - PLAN CHECK | 5/31/2001 | | 6/8/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 6/7/2001 | | FAIL |
|
|
|
Additional informaiton required for further review. Called and talked to John Price ands advised him of the issues.
|
Case Summary (BLD) | | | 5/31/2001 | | DONE |
|
|
|
|
Routing - PLANNING | 5/30/2001 | 5/30/2001 | 5/30/2001 | | PASS |
|
|
|
Per Boise River System Permit #CFH00-00023 and Flood Plain Permit #CFH00-00024.
|
Routing - PLANNING | 5/22/2001 | | 5/25/2001 | | PASS |
|
|
|
Approved per DRH00-161 & as per revised plans in the DR file dated received May 24, 2001. Pending River Systems Permit approval for CFH00-23 & 24.
|
Routing - PLAN CHECK | 5/7/2001 | | 5/22/2001 | | |
|
|
|
|
Plan Review Completed(1st rev) | | | 5/7/2001 | | FAIL |
|
|
|
|
Routing - FIRE | 5/2/2001 | | 5/7/2001 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/9/2001 | | 5/2/2001 | | FAIL |
|
|
|
Routing to fire.
|
Plan Reviewer's activity | | | 5/2/2001 | | FAIL |
|
|
|
Additional information required for further review.
|
Routing Off Site - STRUCTURAL | 3/14/2001 | | 4/26/2001 | | PASS |
|
|
|
Contacted pdq to take plans to outside eng. KMM
|
Plan resubmittals received | | | 4/10/2001 | | DONE |
|
|
|
Received three copies of revised struct. calcs. and sheets a8.0, a8.1, a8.2, a10.1, s0.1, s1.1, s1.2, s2.1, s2.2, s3.1, s3.2, s9.0, s9.1. Routed to Mike P. KMM
|
Routing - PLANNING | 4/3/2001 | | 4/9/2001 | | FAIL |
|
|
|
Community Foresty conditions not met, and several details still need to be provided to Staff for review and approval (e.g., a secondary wall color, guardrails, etc.).
|
Routing - PLUMBING | 3/30/2001 | | 4/3/2001 | | PASS |
|
|
|
per plans and 97 upc, pipe 1st follr water heater pan drains to garage floor also.
|
Routing - PARKS DEPARTME | 3/21/2001 | | 3/30/2001 | | PASS |
|
|
|
Dave Selvage
|
Plan resubmittals received | | | 3/27/2001 | | DONE |
|
|
|
Received two copies of revised sheets C1.O. One copy of cover letter and one copy of attached revised parking garage plans showing the garage drain and sand and grease trap per the plumbing inspectors comments. Routed to Mike Phillips. Routed two separate copies to Gary Ziegler and two separate copies to Lee Rice. KMM
|
Plan resubmittals received | | | 3/22/2001 | | DONE |
|
|
|
Received two copies of sheets A3.14, A3.17, A3.18 and A3.19. These are enlarged floor plans of the new and revised units shown on sheets A2.1 thru A2.4. These were not included in the orifinal submittal. Routed to Mike P. KMM
|
Routing - PUBLIC WORKS | 3/14/2001 | | 3/20/2001 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/14/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/14/2001 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/14/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/14/2001 | | DONE |
|
|
|
|
Application received | | | 3/5/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/5/2001 | | |
|
|
|
|
Received Certificate of Value | | | 3/5/2001 | | DONE |
|
|
|
|