Permit Information
Permit NumberBLD01-00539
StatusFinaled
Name ST LUKES 21504
Site Address 190 E BANNOCK ST
Project NameST LUKES-WEST WING
Customer Number21504
ePlanReviewNo
Description
(ST LUKES-WEST WING-1ST FLR) To remodel an 4,975 sq.ft. area located at the nouth end of the 1st floor to convert from patient rooms to offices per approved plans on file. This area was demolished under BLD00-00081in conjunction with the new stair enclosure, IW008. The interior side of the perimeter walls from Grid Line 'B' to 'I' by '2' to '5', have been seismically upgraded under BLD00-02394. Work to include construction of interior non-bearing, non-combustible wall framing with fire-resistive sheetrock cover; new suspended ceiling grid system, electrical, mechanical & plumbing; interior floor & wall finish; sprinkler system; and construction of a portion of the 2-hour exit passageway that will serve as an extension of the interior two hour stair enclosure serving the upper floors; to install a new exterior exit system, stairs & entry between grid lines 'I' to 'K'. NOTE: Phase "B" will be remodeled under separate permit when Phase "A" is completed. This building is fully sprinklered. A "Letter of Completion" is required as a condition of final approval for occupancy of Phase "A" area. A C.O. will be issued for the entire 1st floor when the entire floor is completed under future permit. PC#01-180/drs
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes3/5/20013/5/20013/22/2004 DONE
BLD-Aging Inspection10/13/200310/13/200310/13/2003 PASS
DetailsDave Hannah
wip 10/13/2003 8:11:43 AM
BLD-Aging Inspection8/5/20038/5/20038/5/2003 PASS
DetailsCarl Dependahl
awaiting c/n resolution re doors at 2hr wall...phased project, WIP. 8/5/2003 9:33:06 AM
BLD-Aging Inspection6/3/20036/3/20036/3/2003 DONE
DetailsCarl Dependahl
has c/n...wip per supt. Kelly. 6/3/2003 1:37:11 PM
BLD-Final4/1/20034/1/20034/1/2003PPART
DetailsCarl Dependahl
kelly; Phone #: ###-#### Internet Inspection Request from: Annette Moore...c/n re hand rails & 90 min occ. sep. doors; ok to use 1st fl exec offices. 4/1/2003 5:01:49 PM
BLD-Final3/21/20033/24/20033/24/2003AFAIL
DetailsCarl Dependahl
KELLY; Phone #: ###-#### Internet Inspection Request from: Darla Downs... 3/24/2003 11:23:52 AM; c/n, other insps, complete glazing, submit stamped modifications, show rated details 3/24/2003 11:51:32 AM
FIRE-Final Inspection3/20/20033/21/20033/21/2003APASS
DetailsRick Jackson
ed; Phone #: ###-#### Internet Inspection Request from: Annette Moore
BLD-Framing/Rough-in3/5/20033/6/20033/6/2003AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 3/5/2003 at 6:51:02 AM. Contact: ###-####....ok to tile lids at office & west portion; need to remove misc. penetrations at exit passageway....large conduit w/o boxes, piping, etc. advise supt. 3/6/2003 3:59:40 PM
BLD-Framing/Rough-in2/11/20032/12/20032/12/2003ANR
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 2/11/2003 at 7:32:26 AM. Contact: ###-####.
BLD-Framing/Rough-in2/12/20032/12/20032/12/2003PNR
DetailsCarl Dependahl
need eng's ok for substandard spec. insp report...hvac permit expired? 2/12/2003 2:28:52 PM
Case Summary (BLD)  2/7/2003  
BLD-Conference12/23/200212/26/200212/26/2002APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/23/2002 at 09:13:53. Contact: ###-####.
BLD-Conference12/26/200212/26/200212/26/2002PPASS
DetailsTom Arcoraci
BLD-Framing/Rough-in7/25/20027/25/20027/25/2002PPART
DetailsCarl Dependahl
dan; Phone #: ###-####...clg grid nr, wip; advised supt that shell not finalled ...need eng's ok, re mti reports of failure 7/25/2002 9:02:02 AM
BLD-Framing/Rough-in3/7/20023/8/20023/8/2002AFAIL
DetailsCarl Dependahl
fr insp - dan ###-#### ; need special insp for spray-on f.p. remove ducts at exit (back of communications rm.) & repair 2hr wall...firestop toggles at same. 3/8/2002 1:53:36 PM
BLD-Framing/Rough-in2/11/20022/12/20022/12/2002APART
DetailsCarl Dependahl
###-#### firestop floors, clarify shaft penetration(hvac) 2/12/2002 12:51:36 PM
BLD-Framing/Rough-in2/7/20022/8/20022/8/2002PNR
DetailsCarl Dependahl
###-#### DAN; need eng's approval re seismic upgrade, verify other ok's. recall. 2/8/2002 5:37:01 PM
BLD-Conference12/17/200112/17/200112/17/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 12/17/2001 3:06:15 PM w/eng'r, need report for struct upgrade & appropriate testing.
BLD-Aging Inspection12/10/200112/10/200112/17/2001 NR
DetailsCarl Dependahl
wip, 1st fl. west wing. 12/17/2001 3:05:17 PM
BLD-Aging Inspection10/8/200110/8/200110/8/2001 NR
DetailsCarl Dependahl
wip 10/9/2001 2:57:25 PM
BLD-Aging Inspection8/6/20018/6/20018/6/2001 PASS
DetailsCarl Dependahl
wip 8/6/2001 10:11:07 AM
Issue & PRINT to be Invoiced  8/1/2001 DONE
Inspection Record Card- Bld  7/31/2001 DONE
Print Occupancy Form  7/31/2001 DONE
Telephone call  7/31/2001 DONE
e-mailed curtis
Routing - PLAN CHECK7/30/20017/30/20017/30/2001 PASS
Approved as noted and per attached plan review conditions, all as part of the approved plans.
PLANS/APPL TAKEN TO FRONT DESK  7/30/2001 PASS
To permit desk to issue.
Plan Review Completed(1st rev)  7/30/2001 PASS
Routing - FIRE7/25/2001 7/30/2001 PASS
Plan assigned to (DRS)3/19/2001 7/30/2001 PASS
DetailsDan Stuart
7/30/2001 15:24:19 DRS - activity updated through activity BLDA022 from case BLD01-00539.
Routing - PLAN CHECK3/22/2001 7/25/2001 PEND
NOTE: Other SLRMC projects were inserted in place of this permit by request of SLRMC and this permit was delayed to this time. 7/6/01 - Received new floor plan defining peramiters of the "Phase 'A" portion. defining accessible route and the temporary exit corridor to be constructed to maintain the rated exit path between the "I-1.1, Central Wing" and the "B, West Wing, South 1/2". 7/25/01 - Routing to fire code analyst for review.
Additional plans submitted  7/25/2001  
Received new sheets A3.1A & A4.0 not submitted with original plans but referenced in plan sections originally submitted.
Additional plans submitted  7/6/2001  
Received new sheets A2.1A of "Phase A" with full dimensions and the limits of work shown. Also revceived copy of sheet A1.0 with the accessible route indicated for accessing the building from the Jefferson Street side by existing ramp.
BLD-Conference5/30/20015/30/20015/30/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 5/30/2001 2:41:01 PM w/ St Lukes...wip
Routing - PLUMBING3/20/2001 3/22/2001 PASS
min. vent lines are not to exceed 1/3 of their total permitted length.
Routing - PUBLIC WORKS3/19/2001 3/20/2001 PASS
Pending Assignment by MYS3/5/2001 3/19/2001 DONE
DetailsMarlene Southard
Application received  3/5/2001  
Plans ACCEPTED BY PLAN TECH  3/5/2001 PEND
Plans not fully dimensioned. KMM
Received Certificate of Value  3/5/2001 DONE
Routing - PLAN CHECK7/30/2001