BLD-Final | 7/5/2001 | 7/6/2001 | 7/6/2001 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/05/2001 at 10:40:17. Contact: ###-####. C/C issued. 7/6/2001 3:54:38 PM
|
DOC - Permit Finaled | 7/6/2001 | 7/6/2001 | 7/6/2001 | P | PASS |
Jim Sly
|
|
|
Added by Inspector: 316 On 7/6/2001 3:54:18 PM
|
BLD-Framing/Rough-in | 5/17/2001 | 5/17/2001 | 5/17/2001 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 10:22:14. Contact: ###-####. Energy Pass 5/17/2001 4:30:25 PM
|
BLD-Framing/Rough-in | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/16/2001 at 08:49:52. Contact: ###-####. o to insul cn issued 5/16/2001 2:39:06 PM
|
BLD-Wall cover | 5/2/2001 | 5/3/2001 | 5/3/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/02/2001 at 08:03:37. Contact: ###-####. Shear OK 5/3/2001 1:27:03 PM
|
BLD-Wall cover | 4/9/2001 | 4/9/2001 | 4/9/2001 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/09/2001 at 10:03:11. Contact: ###-####. Should have been Found insp.....Found PASS. 4/9/2001 3:59:58 PM
|
BLD-Footing | 4/3/2001 | 4/4/2001 | 4/4/2001 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/03/2001 at 16:35:47. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 4/3/2001 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/30/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/30/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/30/2001 | | DONE |
|
|
|
called permit ready
|
Routing - PLANNING | 3/29/2001 | 3/29/2001 | 3/29/2001 | | PASS |
|
|
|
changed back to lot 13 blk 18 the legends no 6
|
Inspection Record Card- Bld | | | 3/26/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/26/2001 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Plan Reviewer's activity | | | 3/23/2001 | | DONE |
|
|
|
not only have we had to go through all the work and time to change lot and block on this house, they now want to modify plans to indicate unfinished basement. both time the plans were completly done, re-done, and setting at front desk to be picked up. this has been triple the work for all departments, including front desk. will assess another plan review fee this time.
|
Case Summary (BLD) | | | 3/23/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 3/23/2001 | | DONE |
|
|
|
|
Routing - PLANNING | 3/20/2001 | 3/20/2001 | 3/21/2001 | | DONE |
|
|
|
SUBMITTED DIFFERENT SITE PLAN DIFFERENT LOT AND BLK
|
Inspection Record Card- Bld | | | 3/21/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/21/2001 | | DONE |
|
|
|
talked to kim gave her new dollar amount
|
Office Staff conference/action | | | 3/20/2001 | | DONE |
|
|
|
Pat took this permit they are changing lots.
|
Print Pending Permit.LaserJet4 | | | 3/20/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/20/2001 | | |
|
|
|
|
Plan assigned to (DJO) | 3/14/2001 | 3/14/2001 | 3/14/2001 | | PASS |
Dan Overy
|
|
|
3/14/2001 15:20:27 DJO - activity updated through activity BLDA022 from case BLD01-00556.
|
Print Pending Permit.LaserJet4 | | | 3/14/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 3/14/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/14/2001 | | DONE |
|
|
|
|
Telephone call | | | 3/14/2001 | | DONE |
|
|
|
left mess that permit is ready
|
Plans ACCEPTED BY PLAN CHECK | | | 3/14/2001 | | |
|
|
|
|
Routing - PLANNING | 3/7/2001 | 3/7/2001 | 3/7/2001 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 3/7/2001 | 3/7/2001 | 3/7/2001 | | PASS |
|
|
|
|
Application received | | | 3/7/2001 | | |
|
|
|
address at 4:30
|
Routing - PLAN CHECK | 3/7/2001 | 3/7/2001 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 3/7/2001 | | | | PEND |
Dan Overy
|
|
|
|