Case Summary (BLD) | | | 10/15/2015 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/18/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9262 issued 7-18-02 to the Park Apts. II.
|
Permanent Occupancy | | 7/17/2002 | 7/17/2002 | | DONE |
|
|
|
|
BLD-Final | 7/17/2002 | 7/17/2002 | 7/17/2002 | P | PASS |
Carl Dependahl
|
|
|
dave; Phone #: ###-####
|
Fee Review-notes | 3/14/2001 | 3/14/2001 | 5/23/2002 | | DONE |
|
|
|
|
BLD-Final | 4/26/2002 | 4/26/2002 | 4/26/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/26/2002 at 08:10:04. Contact: ###-####. ok for t/o, c/n rails, plbg, temp glass 4/26/2002 5:07:21 PM
|
Temporary occupancy | | | 4/26/2002 | | DONE |
|
|
|
Temp. Occ. Cert. #4799 issued 4-26-02 to the Park Apts.
|
BLD-Final | 4/24/2002 | 4/25/2002 | 4/25/2002 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 04/24/2002 at 17:01:58. Contact: ###-####. cn issued not ready 4/25/2002 2:58:39 PM
|
FIRE-Final Inspection | 4/23/2002 | 4/24/2002 | 4/24/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 04/23/2002 at 15:34:55. Contact: ###-####.
|
BLD-Final | 4/23/2002 | 4/24/2002 | 4/24/2002 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/23/2002 at 15:35:43. Contact: ###-####.
|
Code Occupancy Approval | | | 4/11/2002 | | PASS |
|
|
|
SIGNED FINAL AS WE ARE HOLDING LARGE BOND FOR LANDSCAPE.
|
Case Summary (BLD) | | | 4/5/2002 | | |
|
|
|
|
BLD-Conference | 1/28/2002 | 1/28/2002 | 1/28/2002 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/28/2002 9:57:12 AM w/ Jeff Langen proj mgr...is faxing flood certs to site, apparently were given to Jim Wylie in pub wks as they weren't in plan chk log; also eng's written report re int shear walls to be provided, observation was made.
|
BLD-Wall cover | 1/18/2002 | 1/22/2002 | 1/22/2002 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/18/2002 at 16:04:47. Contact: ###-####....need eng's ok for 1st fl gypsum shear walls 1/22/2002 3:03:16 PM
|
BLD-Framing/Rough-in | 1/22/2002 | 1/22/2002 | 1/22/2002 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/22/2002 12:24:10 PM part, keep c/n re ext stairs, rest ok
|
BLD-Framing/Rough-in | 1/15/2002 | 1/16/2002 | 1/16/2002 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/15/2002 at 10:34:45. Contact: ###-####.c/n, ok to insul 1/16/2002 6:06:35 PM
|
BLD-Aging Inspection | 12/24/2001 | 12/24/2001 | 12/27/2001 | | NR |
Carl Dependahl
|
|
|
apts, wip 12/27/2001 8:57:03 AM
|
Case Summary (BLD) | | | 12/6/2001 | | |
|
|
|
|
Case Summary (BLD) | | | 12/6/2001 | | |
|
|
|
|
BLD-Conference | 10/23/2001 | 10/23/2001 | 10/23/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/23/2001 8:59:29 AM w/Otis L. at site re "shear" c/n... awaiting add'l eng'g.
|
Plan resubmittals received | | | 10/10/2001 | | DONE |
|
|
|
Recieved one copy of cover letter and information from Structural Eng. Routed to Carl D. kmm
|
Print Pending Permit.LaserJet4 | | | 10/5/2001 | | |
|
|
|
|
BLD-Framing/Rough-in | 9/5/2001 | 9/5/2001 | 9/5/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### jim 1st fl shear nailing ok 9/5/2001 3:45:04 PM
|
BLD-Framing/Rough-in | 8/3/2001 | 8/3/2001 | 8/3/2001 | P | PART |
Carl Dependahl
|
|
|
rebar jim ###-####
|
BLD-Foundation | 7/18/2001 | 7/19/2001 | 7/19/2001 | P | PASS |
Jim Storey
|
|
|
re-bar Jim ###-####
|
Inspection Record Card- Bld | | | 6/5/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/5/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/4/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/11/2001 | | 5/25/2001 | | DONE |
|
|
|
TOOK TO MIKE P
|
Plan Reviewer's activity | | | 5/25/2001 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/25/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/25/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/25/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/25/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/25/2001 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2001 | | DONE |
|
|
|
called permit ready
|
Plan assigned to (M_P) | 3/12/2001 | | 5/25/2001 | | PASS |
Mike Phillips
|
|
|
5/25/2001 09:40:59 M_P - activity updated through activity BLDA022 from case BLD01-00599.
|
Routing - FIRE | 5/8/2001 | | 5/11/2001 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/10/2001 | | DONE |
|
|
|
Received one copy of revised sheet C1.2. Contacted Chad Heimbigner requesting four additional copies. KMM
|
Plan resubmittals received | | | 5/1/2001 | | DONE |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS A1.6, S1.1, S1.2, A6.1, A6.2. TWO COPIES OF REVISED SHEETS A2.1, A2.2, A2.3, A2.4, A2.5, A3.1, A3.2, A3.3, A5.1, A6.1, A6.2, P-1. FOUR COPIES OF RESPONSE LETTER. ROUTED TO MIKE P. KMM
|
Routing - PLAN CHECK | 4/4/2001 | | 4/11/2001 | | FAIL |
|
|
|
Routing to fire.
|
Plan Reviewer's activity | | | 4/11/2001 | | FAIL |
|
|
|
Additional information required for further review.
|
Routing Off Site - STRUCTURAL | 3/15/2001 | | 4/11/2001 | | FAIL |
|
|
|
contacted pdq to take plans to outside eng. KMM
Additional information required for further review.
|
Routing - PLUMBING | 3/30/2001 | | 4/4/2001 | | FAIL |
|
|
|
|
Routing - PARKS DEPARTME | 3/28/2001 | | 3/30/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 3/20/2001 | | 3/28/2001 | | PASS |
|
|
|
Approved by SAR and TKW (DRH00-00239)
|
Routing - PUBLIC WORKS | 3/15/2001 | | 3/20/2001 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/15/2001 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/15/2001 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/14/2001 | | DONE |
|
|
|
|
Application received | | | 3/12/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/12/2001 | | |
|
|
|
|
Received Certificate of Value | | | 3/12/2001 | | DONE |
|
|
|
|